Current construction information, including notifications of upcoming work near the project area, will be posted to this page.  Major construction on the SkyTrain extension is scheduled to begin in late 2024. 

We provide ongoing updates about construction in advance to email subscribers, through alerts to traffic news outlets and here on our website. Please see notifications below and contact us if you have specific questions about what’s happening currently on and near Fraser Highway. Register to receive construction notices for specific station areas and general updates.

Note: Drones will be used throughout the duration of the Surrey Langley SkyTrain Project to monitor and document project work, with no intention of collecting personal information. Please see our related FOIPPA notice on the use of drones.

General Information

  • Traffic Pattern and Project Update – Fraser Highway and 166 Street

    Posted October 21, 2024 – Construction activities, including drilling piles for foundations and relocating underground utilities, are beginning. Roadway construction will take place in the vicinity of Fraser Highway and 166 Street. Traffic pattern changes…

    Read more

  • UPDATED: Test piling activities at Industrial Ave and 203 Street

    Posted October 18, 2024 – As part of early construction work, crews will complete “test piles” which are expected to begin the week of October 21 and continue through early December 2024. Pile installation involves…

    Read more

  • Geotechnical Investigation on Industrial Ave

    Posted October 10, 2024 – Geotechnical investigation to gather information about ground conditions for the future location of piers will occur on Industrial Avenue, starting October 16 for approximately two weeks. There will be parking…

    Read more

  • Traffic Update: Fraser Highway between 148 and 152 Street

    Posted October 9, 2024 – Travel lanes, pedestrian, and cycling lanes will be adjusted on Fraser Highway between 148 Street and 152 Street. There will be intermittent lane closures on the approach to the intersection…

    Read more

  • Traffic and Night Work Update: Fraser Highway East of Highway 15 

    Posted October 8, 2024 – The ground for future piers and the elevated guideway, embankment construction, clearing and backfilling, will occur along a section of Fraser Highway east of Highway 15. This work requires longer…

    Read more