Construction Notice Archive
Find notifications that are no longer active.
Archived construction notifications are posted below.
Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.
Archived Notifications
Weekly Traffic Advisories
Find archived weekly summaries of traffic advisories for the Surrey Langley SkyTrain project.

-
Weekly Traffic Advisory: September 15 – September 21, 2025
Posted September 12, 2025 – This advisory outlines traffic pattern changes from September 15, 2025 – September 21, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: September 8 – 14, 2025
Posted September 5, 2025 – This advisory outlines traffic pattern changes from September 8, 2025 – September 14, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory September 1 – 7, 2025
Posted August 29, 2025 – This advisory outlines traffic pattern changes during the week of September 1 to September 7, 2025, along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedules are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: August 25 – 31, 2025
Posted August 22, 2025 – This advisory outlines traffic pattern changes during the week of August 25 to 31, 2025, along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedules are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: August 18 – 24, 2025
Posted August 15, 2025 – This advisory outlines traffic pattern changes during the week of August 18 to 24, 2025, along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedules are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
UPDATED: Traffic Update: 152 Street at Fraser Highway
Posted April 7, 2026 – This is an update to the notice posted on March 5, 2026. Station foundation construction at the station site on the west side of 152 Street and construction of a…
-
Traffic Update: Fraser Highway and 140 Street
Posted February 9, 2026 – Foundation work is occurring on Fraser Highway west of 140 Street and requires large, specialized equipment. Access to businesses west of 140 Street is available from 140 Street southbound only. There…
-
UPDATED: Access Changes North of Fraser Highway at 138 Street
Posted February 4, 2026 – This is an update to the notice posted on January 9, 2026. Construction activities include relocating existing utilities north of Fraser Highway at 138 Street. Traffic pattern changes will be…
-
Access Change at Fraser Highway and 162 Street/84 Avenue
Posted January 30, 2026 – There will be no access to/from 162 Street/84 Avenue from Fraser Highway beginning February 6 to February 13, 2026 and early March 2026 for one day. Please use alternate routes…
-
UPDATED: Traffic Update: 152 Street at Fraser Highway
Posted January 8, 2026 – This is an update to the notice posted on December 3, 2025. Construction activities include station foundation construction at the station site on the west side of 152 Street and…
-
UPDATED: Traffic Pattern and Project Update – Fraser Highway and 166 Street
Posted November 7, 2024 – The work previously planned to start mid-November is being rescheduled for December 2024. This is an update of the notification from October 21, 2024. View detailed notice If you have…
-
Traffic and Night Work Update: Fraser Highway East of Highway 15
Posted October 8, 2024 – The ground for future piers and the elevated guideway, embankment construction, clearing and backfilling, will occur along a section of Fraser Highway east of Highway 15. This work requires longer…
-
UPDATED: Various works along Fraser Highway between 140 & 192 Street
Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…
-
UPDATED: Lane Closure on Fraser Highway between 150 and 170 Street
Posted August 22, 2024- This is an update of the notification from August 1, 2024 as the date of work has changed. Existing streetlights on the south side of Fraser Highway between 150 and 170 Street will…
-
Piling activities at various locations on Fraser Highway
Posted August 20, 2024 – Construction activities including geotechnical investigations and test piling activities are scheduled along Fraser Highway in September at various locations. There may be an increase of noise generated by the drilling…
-
Traffic Update: Fraser Highway between 196 Street and Highway 10
Posted March 7, 2025 – Activities will include roadwork, installing construction fencing around work areas, moving existing utilities to allow for construction and installing new utilities to supply power for the future SkyTrain. Foundation construction…
-
UPDATED: Traffic Update: 203 Street and 203A Street
Posted February, 20, 2025 – Single lane traffic northbound and southbound between Acacia Crescent and just north of Industrial Avenue. 203A Street will be temporarily closed to all through traffic from Locke Lane to Imperial…
-
Traffic Update: 203 Street and 203A Street
Posted February 10, 2025 – Single lane traffic northbound and southbound between Acacia Crescent and just north of Industrial Avenue. 203A Street will be temporarily closed to all through traffic from Locke Lane to Imperial…
-
Traffic Update: Fraser Highway between 64 Avenue and 196 Street
Posted February 5, 2025 – Vehicle travel lanes on Fraser Highway between 64 Avenue and 196 Street/Willowbrook Drive will be reduced to single lanes westbound and eastbound. Traffic pattern changes will be in effect from…
-
UPDATED: Test piling activities at Industrial Ave and 203 Street
Posted November 19, 2024 – Test piling is now scheduled to begin November 20. There will be a temporary increase in noise and vibration while this work is taking place. This is an update of the…
Precast Concrete Facility
Find archived notifications for the precast concrete facility located at 195 Street and 24 Avenue.

No results found