Current Work
Find out about current construction activities.
Summary
Major construction on the SkyTrain extension is underway:
- Work hours: Mon-Sat, 7 a.m. to 10 p.m. with most activities complete by 8 p.m. Some work may occasionally be permitted outside these regular work hours to minimize business and traffic impacts.
- Traffic impacts: Single-lane traffic is in effect 24/7 along most of the Fraser Highway corridor, along with some lane closures and pedestrian/cyclist detours.
- Access remains open to all businesses, services, and residential areas along Fraser Highway and Industrial Avenue.
Stay informed: Subscribe to email updates, follow us on social media (Facebook, Threads), or check this website. See below for current notifications and contact us if you have any questions.
Archived notifications can be found on our Construction Notice Archive webpage.
Current Work Areas
The Surrey Langley SkyTrain project work areas are divided into three sections corresponding with streets along the project corridor. View our alignment map to see each section and find project notifications by location posted below.

Alignment Map
Notifications
Quarterly Construction Advisory
An overview of current and upcoming project activities.

-
Construction Advisory – Fall 2026
Posted September 14, 2026 – This advisory provides an overview of project activities from September – November 2026. View detailed advisory If you have any questions, please email surreylangleyskytrain@gov.bc.ca.
-
Construction Advisory – Spring / Summer 2026
Posted June 19, 2026 – This advisory provides an overview of project activities from June 2026 – August 2026. View detailed advisory If you have any questions, please email surreylangleyskytrain@gov.bc.ca.
-
Construction Advisory – Winter 2026
Posted February 23, 2026 – This advisory provides an overview of project activities from February 2026 – May 2026. View detailed advisory If you have any questions, please email surreylangleyskytrain@gov.bc.ca.
-
Construction Advisory – Fall 2025
Posted November 12, 2025 – Construction of the Surrey Langley SkyTrain Project is underway. This newsletter provides an overview of project activities from November 2025 – January 2026. View detailed newsletter If you have any…
-
Construction Advisory – Summer 2025
Posted August 6, 2025 – Construction of the Surrey Langley SkyTrain Project is underway. This newsletter provides an overview of project activities from August 2025 – October 2025. View detailed newsletter If you have any…
Weekly Traffic Advisories
Find a weekly summary of traffic advisories for the Surrey Langley SkyTrain project.

-
Weekly Traffic Advisory: October 19 to October 25, 2026
Posted October 16, 2026 – This advisory outlines traffic pattern changes from October 19 to October 25, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject…
-
Weekly Traffic Advisory: October 12 to October 18, 2026
Posted October 9, 2026 – This advisory outlines traffic pattern changes from October 12 to October 18, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject…
-
Weekly Traffic Advisory: October 5 to October 11, 2026
Posted October 2, 2026 – This advisory outlines traffic pattern changes from October 5 to October 11, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject…
-
Weekly Traffic Advisory: September 28 to October 4, 2026
Posted September 25, 2026 – This advisory outlines traffic pattern changes from September 28 to October 4, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject…
-
Weekly Traffic Advisory: September 21 to September 27, 2026
Posted September 18, 2026 – This advisory outlines traffic pattern changes from September 21 to September 27, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject…
Section 1: 138 Street to 164 Street
- Elevated guideway construction, including work on foundations, columns, and guideway.
- Two launching gantries are operating in this area.
- Station construction.
- Extended work hours between 140 Street and 96 Ave.

No results found
Section 2: East of 164 Street to 184 Street
- Elevated guideway construction, including work on foundations, columns, and guideway.
- A launching gantry is operating in this area. Extended work hours.
- Station construction, including Sunday work.
- Extended work hours between 168 Street and 184 Street
- Preload work at South of Fraser Maintenance and Storage Facility (SFMSF) including work overnight.

-
Construction Update: Sunday work at Bakerview-166 Street and Hillcrest-184 Street Stations
Posted October 22, 2026 – Surrey Langley SkyTrain construction is underway, including rebar, concrete, and structure work for the future Bakerview-166 Street and Hillcrest-184 Street stations. To carry out these activities, Sunday work will occur…
-
Traffic Update: Turn restrictions at Fraser Highway and 184 Street
Posted October 16, 2026 – Surrey Langley construction is underway, including road restoration activities and electrical work to support the installation of new traffic signals at the intersection. The following traffic pattern changes are in…
-
Construction Update: Extended hours Fraser Highway east of Highway 15
Posted October 13, 2026 – Surrey Langley SkyTrain construction is underway. A launching gantry, the Clayton Clipper, is installing the guideway for the future SkyTrain. Segment delivery and installation is taking place on Fraser Highway,…
-
Construction Update: Guideway Installation
Posted September 9, 2025 – Construction crews are building the elevated guideway for the Surrey Langley SkyTrain using large machines called launching gantries – one of which is now active in this area. Expect temporary…
Section 3: East of 184 Street to 203 Street
- Elevated guideway construction, including work on foundations, columns, and guideway.
- A launching gantry is operating in this area.
- Pile driving in Langley on Industrial Avenue. Extended work hours.
- Station construction.

-
Traffic Update: No access to 68 Avenue, 188 and 189 streets north of Fraser Highway
Posted October 22, 2026 – Roadway restoration activities for the Surrey Langley SkyTrain Project will require temporary vehicle access restrictions north of Fraser Highway: These traffic changes will be in effect 24/7. Access to businesses…
-
Traffic Update: No access to 203 Street from Industrial Avenue
Posted October 22, 2026 — To support concrete work and track installation on a portion of the elevated guideway on Industrial Avenue, a daytime closure between 201A Street and 203 Street is required on October…
-
UPDATED: Pile driving and extended hours on Industrial Avenue
Posted September 24, 2026 – This is an update to the notice posted on July 6, 2026. Construction to support the Surrey Langley SkyTrain advances as elevated guideway construction, pile driving for column foundations, and track…
-
Construction Update: Pile Driving in Langley
Posted January 16, 2026 – Construction crews will be pile driving for the guideway foundations in Langley City beginning in February 2026. Expect traffic pattern changes, an increase in noise and vibrations, and possible night…
-
Construction Update: Guideway Installation
Posted September 9, 2025 – Construction crews are building the elevated guideway for the Surrey Langley SkyTrain using large machines called launching gantries – one of which is now active in this area. Expect temporary…
Precast Concrete Facility
Located at 195 Street and 24 Avenue in Surrey.
Activities include producing concrete segments for the elevated guideway.

-
Construction Update: Extended Hours at Precast Concrete Facility
Posted February 6, 2026 – The casting of guideway segments at the precast concrete facility at 195 Street and 24 Avenue, and their transport to the SkyTrain route for installation, is underway. Extended hours are required at this facility to support the delivery of these segments to Fraser Highway. Overnight work begins on February 9,…
-
Precast Concrete Facility
Posted January 27, 2025 – The concrete segments for the elevated guideway will be built at a SkyTrain precast concrete facility located at 195 Street and 24 Avenue in Surrey. Once construction of the precast facility is complete, operations at the facility involve casting concrete SkyTrain guideway segments and transporting them to the SkyTrain route…