  • Weekly Traffic Advisory: February 17 – February 23

    Posted February 14, 2025 – This advisory outlines traffic pattern changes from February 17, 2025 – February 23, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: February 10 – February 16

    Posted February 7, 2025 – This advisory outlines traffic pattern changes from February 10, 2025 – February 16, 2025, along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: February 3 – February 9

    Posted January 31, 2025 – This advisory outlines traffic pattern changes from February 3, 2025 – February 9, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: January 27 – February 2

    Posted January 24, 2025 – This advisory outlines traffic pattern changes from January 27, 2025 – February 2, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: January 20 – January 26

    Posted January 17, 2025 – This advisory outlines traffic pattern changes from January 20, 2025 – January 26, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • UPDATED: Temporary Access Closure at 154 Street and Fraser Highway

    Posted September 3, 2025 – This is an update to the notice posted July 30, 2025. Traffic pattern changes will be in effect from September 8-19, 2025. There will be no access at 154 Street. Access…

    Read more

  • Traffic Update: Temporary Access Closure at 159 Street North of Fraser Highway

    Posted August 20, 2025 – To allow for utility work within the intersection at Fraser Highway and 159 Street, traffic pattern changes will be in effect on August 22 and August 25, 2025, as well…

    Read more

  • UPDATED: Traffic Update: Road Closure at 84 Avenue South of Fraser Highway

    Posted August 11, 2025 – This is an update to the notice posted on June 9, 2025. Traffic pattern changes will be in effect for one day on August 12, 2025. There will be no access…

    Read more

  • Traffic Update: Night work and turn restrictions at Fraser Highway and 152 Street

    Posted July 21, 2025 – Night work is required to support activities and reduce overall traffic impacts from August 5 to August 21, 2025. Turning restrictions at the intersection will be in effect from 7…

    Read more

  • Traffic Update: 140 Street and Fraser Highway

    Posted July 11, 2025 – To support the installation of new utilities to power the future SkyTrain and station construction, traffic pattern changes will be in effect from 7 p.m. to 7 a.m. starting July…

    Read more

  • Traffic Update: Access change on 166 Street and Fraser Highway

    Posted September 22, 2025 – A traffic pattern change will take place on 166 Street and Fraser Highway from September 22, 2025, for up to one month. Access to 166 Street is available from Fraser…

    Read more

  • Traffic Update: Overnight Access Change at 166 Street and Fraser Highway

    Posted September 8, 2025 – To facilitate guideway construction, access to 166 Street north of Fraser Highway will be temporarily unavailable overnight from 8:00 p.m. to 7.00 a.m. starting September 14, 2025, for up to…

    Read more

  • Traffic Update: Overnight traffic pattern changes at Fraser Highway and Highway 15

    Posted August 14, 2025 – Overnight lane closures will be required on Highway 15, including intermittent turning restrictions at the Fraser Highway and Highway 15 intersection. Traffic changes will be in effect from August 17,…

    Read more

  • Traffic Update: Access Change Fraser Highway west of 68 Avenue

    Posted July 25, 2025 – An access change will be in effect at Fraser Highway west of 68 Avenue from July 28, 2025, for approximately one week. There will be no access to/from Fraser Highway…

    Read more

  • Traffic Update: Intersection work at Fraser Highway and 184 Street

    Posted July 18, 2025 – Traffic changes will be in effect at the Fraser Highway and 184 Street intersection from July 21, 2025, for approximately two weeks. Traffic will be reduced to one lane in…

    Read more

  • UPDATED: Lane and Parking Impacts Around 203 Street, Industrial Avenue and Acacia Crescent

    Posted August 8, 2024 – This is an update of the notification from July 30, 2024 as dates of work have changed. Crews will be conducting pre-condition surveys (PCS) around the future Langley City Centre Station and…

    Read more

  • Lane Reduction on 203 Street, 203A Street and Acacia Crescent

    Posted July 24, 2024 – To prepare for construction of the Surrey Langley SkyTrain, crews will be conducting pre-condition surveys (PCS) around the future Langley City Centre Station and the 201 Street Propulsion Power Substation (PPS)…

    Read more

  • Notice of Evening Work Near 201A Street and Industrial Avenue

    To prepare for construction of the Surrey Langley SkyTrain, crews are starting early works on the site where the future 201 Street Propulsion Power Substation (PPS) will be located. A PPS supplies electrical power to…

    Read more

  • Notice of Evening Work Near 203 Street and Acacia Crescent

    To prepare for construction of the Surrey Langley SkyTrain, crews are starting early works on the property where the future Langley City Centre Station will be located. Materials for gravel surface treatment work will be…

    Read more

  • Demolition work at 6000 Production Way

    Posted June 26, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. Demolition of an existing structure, including utility disconnections, tree removal, hazardous material abatement and…

    Read more