Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: February 9 – February 15, 2026

    Posted February 6, 2026 – This advisory outlines traffic pattern changes from February 9 – February 15, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: February 2 – February 8, 2026

    Posted January 30, 2026 – This advisory outlines traffic pattern changes from February 2 – February 8, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: January 26 – February 1, 2026

    Posted January 23, 2026 – This advisory outlines traffic pattern changes from January 26 – February 1, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: January 19 – January 25, 2026

    Posted January 16, 2026 – This advisory outlines traffic pattern changes from January 19 – January 25, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: January 12 – January 18, 2026

    Posted January 9, 2026 – This advisory outlines traffic pattern changes from January 12 – January 18, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • UPDATED: Foundation Construction along Fraser Highway

    Posted January 8, 2025 – Current construction activities for the Surrey Langley SkyTrain project include preparing sites and ground improvements to support the future guideway piers and SkyTrain stations. Foundation construction will occur throughout the…

    Read more

  • Traffic Update: Fraser Highway between 148 and 152 Street

    Posted October 9, 2024 – Travel lanes, pedestrian, and cycling lanes will be adjusted on Fraser Highway between 148 Street and 152 Street. There will be intermittent lane closures on the approach to the intersection…

    Read more

  • Notice of work on 140 Street and Fraser Highway

    Posted September 5, 2024 – Hydrovac work will take place on 140 Street and Fraser Highway on September 9 and September 10. The hydrovac work requires a single lane closure northbound for the trucks and…

    Read more

  • Site preparations for upcoming construction

    Posted September 5, 2024 – Crews will be working on clearing, grubbing, removing and disposing of vegetation and debris along Fraser Highway starting September 9 and lasting for approximately two weeks at the following locations:…

    Read more

  • UPDATED: Various works along Fraser Highway between 140 & 192 Street

    Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…

    Read more

  • Extended Hours: Fraser Highway east of Highway 15

    Posted May 12, 2026 – Extended work hours will be in effect from 10 p.m. to 7 a.m., May 19 to May 22, 2026, to support Surrey Langley SkyTrain construction. Overnight work is required to…

    Read more

  • Traffic Update: Overnight closure of Highway 15 at Fraser Highway

    Posted March 30, 2026 – To support guideway work over Highway 15, a section of Highway 15 south of Fraser Highway will be closed for four consecutive nights, from 12 a.m. to 4 a.m., April…

    Read more

  • Traffic Update: Access change on 166 Street north of Fraser Highway

    Posted March 5, 2026 – To support utility installations, there will be no access to the Surrey Sport & Leisure Complex from the north end of 166 Street starting March 9, 2026, for up to…

    Read more

  • Station Construction Underway at Hillcrest-184 Street Station

    Posted December 18, 2025 – Station foundation construction, including pile driving, will begin mid-January 2026 and occur for approximately two months, through mid-March 2026. Temporary increases in noise and vibrations are anticipated.  View detailed notice…

    Read more

  • Station Construction Underway at Bakerview-166 Street Station

    Posted November 27, 2025 – Construction is underway for the future Bakerview-166 Street Station. Station foundation construction, including pile driving, will begin early December and occur for approximately three months, through mid-February 2026. Access to…

    Read more

  • Traffic Update: Access Changes at Westbrook Centre and Surlang Centre

    Posted November 10, 2025 – There will be access changes to/from Westbrook Centre and Surlang Centre along Fraser Highway west of Willowbrook Drive/196 Street between November 12 – December 4, 2025. View detailed notice If…

    Read more

  • Traffic Update: Fraser Highway between 200 Street and 201A Street

    Posted October 16, 2025 – Traffic pattern changes will be in effect on Fraser Highway from 200 Street to 201A Street from October 20 to late December 2025. The centre left turn lane will be…

    Read more

  • Traffic Update: Turning restrictions on Fraser Highway at 195A Street and Willowbrook Drive

    Posted October 10, 2025 – Temporary turning restrictions will be in effect on a 24/7 basis starting the week of October 20 for approximately one week. There will be no left turns to Willowbrook Drive…

    Read more

  • UPDATED: Guideway Construction Underway on Industrial Avenue

    Posted October 3, 2025 – This is an update to the notice distributed on September 10, 2025, to reflect the addition of Saturday work. Construction of the elevated guideway on Industrial Avenue (west of the…

    Read more

  • Traffic Update: Turn restrictions at Fraser Highway and 64 Avenue

    Posted August 14, 2025 – To allow for utility work within the intersection at 64 Avenue and Fraser Highway, traffic pattern changes will be in effect from August 14, 2025, until August 29, 2025. There…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.