Overnight work is underway: A launching gantry is operating overnight and on weekends on Fraser Highway working east from 68 Avenue to 188 Street through March 2026. View postcard for more information.

Major construction on the SkyTrain extension is underway: 

  • Work hours: Mon-Sat, 7 a.m. to 10 p.m. with most activities complete by 8 p.m. Some work may occasionally be permitted outside these regular work hours to minimize business and traffic impacts.
  • Traffic impacts: Single-lane traffic is in effect 24/7 along most of the Fraser Highway corridor, along with some lane closures and pedestrian/cyclist detours.
  • Access remains open to all businesses, services, and residential areas along Fraser Highway and Industrial Avenue.

Stay informed: Subscribe to email updates, follow us on social media (Facebook, Twitter/X), or check this website. See below for current notifications and contact us if you have any questions.

Archived notifications can be found on our Construction Notice Archive webpage.

The Surrey Langley SkyTrain project work areas are divided into three sections corresponding with streets along the project corridor. View our alignment map to see each section and find project notifications by location posted below.

An image showing a specialized lifting machine, known as a launching gantry, lifting elevated guideway segments into place to build the Surrey Langley SkyTrain elevated guideway.
  • Construction Update – Fall 2025

    Posted November 12, 2025 – Construction of the Surrey Langley SkyTrain Project is underway. This newsletter provides an overview of project activities from November 2025 – January 2026. View detailed newsletter If you have any…

    Read more

  • Construction Update – Summer 2025

    Posted August 6, 2025 – Construction of the Surrey Langley SkyTrain Project is underway. This newsletter provides an overview of project activities from August 2025 – October 2025. View detailed newsletter If you have any…

    Read more

  • Construction Update – Spring 2025

    Posted May 14, 2025 – Construction of the Surrey Langley SkyTrain is underway. This newsletter provides an overview of current and upcoming project activities from May 2025 through July 2025 for each project area. View…

    Read more

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: November 24 – November 30, 2025

    Posted November 21, 2025 – This advisory outlines traffic pattern changes from November 24, 2025 – November 30, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to…

    Read more

  • Weekly Traffic Advisory: November 17 – November 23, 2025

    Posted November 14, 2025 – This advisory outlines traffic pattern changes from November 17, 2025 – November 23, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to…

    Read more

  • Weekly Traffic Advisory: November 10 – November 16, 2025

    Posted November 7, 2025 – This advisory outlines traffic pattern changes during the week of November 10-16, 2025, along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedules are subject…

    Read more

  • Weekly Traffic Advisory: November 3 – November 9, 2025

    Posted October 31, 2025 – This advisory outlines traffic pattern changes from November 3, 2025 – November 9, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to…

    Read more

  • Weekly Traffic Advisory: October 27 – November 2, 2025

    Posted October 24, 2025 – This advisory outlines traffic pattern changes from October 27, 2025 – November 2, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to…

    Read more

  • Construction Update: Guideway Installation

    Posted September 9, 2025 – Construction crews are building the elevated guideway for the Surrey Langley SkyTrain using large machines called launching gantries – one of which is now active in this area. Expect temporary…

    Read more

  • Traffic Update: Fraser Highway between 148 Street and 152 Street

    Posted April 9, 2025 – To support ongoing SkyTrain construction, there will be traffic changes on Fraser Highway between 148 Street and 152 Street from mid-April 2025 until Spring 2026. The travelling public can expect…

    Read more

  • Cycling Detour: Fraser Highway between 156 Street and 84 Avenue

    Posted March 19, 2025 – To accommodate construction activities along Fraser Highway between 156 Street and 84 Avenue, cyclists will be detoured off of Fraser Highway. During this period, cyclists will be accommodated within existing…

    Read more

  • Traffic Update: Fraser Highway between 154 Street and 160 Street

    Posted March 18, 2025 – Traffic changes will be in effect March 24, 2025, through summer 2026. Lane closures will be implemented on Fraser Highway between 154 Street and 160 Street. Traffic will be reduced…

    Read more

  • Station Construction Underway at Hillcrest-184 Street Station

    Posted December 18, 2025 – Station foundation construction, including pile driving, will begin mid-January 2026 and occur for approximately two months, through mid-March 2026. Temporary increases in noise and vibrations are anticipated.  View detailed notice…

    Read more

  • Station Construction Underway at Bakerview-166 Street Station

    Posted November 27, 2025 – Construction is underway for the future Bakerview-166 Street Station. Station foundation construction, including pile driving, will begin early December and occur for approximately three months, through mid-February 2026. Access to…

    Read more

  • Construction Update: Guideway Installation

    Posted September 9, 2025 – Construction crews are building the elevated guideway for the Surrey Langley SkyTrain using large machines called launching gantries – one of which is now active in this area. Expect temporary…

    Read more

  • UPDATED: Multi-Use Path Closure from 168 Street to Highway 15

    Posted September 19, 2025 – This is an update to the notice distributed on May 23, 2025. A multi-use path closure from 168 Street to Highway 15 is in effect until January 2026, with modifications.…

    Read more

  • Extended hours on Fraser Highway between 170 Street to 180 Street

    Posted September 18, 2025 – Activities in this area include foundation construction, using driven and vibratory methods, rebar installation and concrete work. These activities are expected to continue through March 2026 and require extended hours,…

    Read more

  • Traffic Update: Fraser Highway at 201A Street 

    Posted February 18, 2026 – Activities include utility relocations and installation of new utilities to power the future SkyTrain. As work progresses, the traffic pattern changes on Fraser Highway from 200 Street to 201A Street…

    Read more

  • UPDATED: Foundation Construction Laneway East of Highway 10

    Posted February 12, 2026 – This is an update to the notice posted February 4, 2026. Construction of the elevated guideway is underway in the laneway near Highway 10 and Fraser Highway. Foundation construction in…

    Read more

  • Access change and extended hours at Willowbrook Drive north of Fraser Highway

    Posted February 12, 2026 – There will be no access to/from Willowbrook Drive north of Fraser Highway from February 19 to March 8, 2026. Alternate routes are available via 64 Avenue and 200 Street. Business…

    Read more

  • Construction Update: Pile Driving in Langley

    Posted January 16, 2026 – Construction crews will be pile driving for the guideway foundations in Langley City beginning in February 2026. Expect traffic pattern changes, an increase in noise and vibrations, and possible night…

    Read more

  • UPDATED: Fraser Highway between 200 Street and 201A Street

    Posted December 23, 2025 – This is an update to the notice posted on October 16, 2025. Traffic pattern changes are in effect on Fraser Highway from 200 Street to 201A Street until February 2026.…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.
  • Construction Update: Extended Hours at Precast Concrete Facility

    Posted February 6, 2026 – The casting of guideway segments at the precast concrete facility at 195 Street and 24 Avenue, and their transport to the SkyTrain route for installation, is underway. Extended hours are required at this facility to support the delivery of these segments to Fraser Highway. Overnight work begins on February 9,…

    Read more

  • Precast Concrete Facility

    Posted January 27, 2025 – The concrete segments for the elevated guideway will be built at a SkyTrain precast concrete facility located at 195 Street and 24 Avenue in Surrey. Once construction of the precast facility is complete, operations at the facility involve casting concrete SkyTrain guideway segments and transporting them to the SkyTrain route…

    Read more