Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: April 27 – May 3, 2026

    Posted April 24, 2026 – This advisory outlines traffic pattern changes from April 27 – May 3, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: April 20 – April 26, 2026

    Posted April 17, 2026 – This advisory outlines traffic pattern changes from April 20 – April 26, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: April 13 – April 19, 2026

    Posted April 10, 2026 – This advisory outlines traffic pattern changes from April 13 – April 19, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: April 6 – April 12, 2026

    Posted April 2, 2026 – This advisory outlines traffic pattern changes from April 6 – April 12, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: March 30 – April 5, 2026

    Posted March 27, 2026 – This advisory outlines traffic pattern changes from March 30 – April 5, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • UPDATED: Traffic Update: 152 Street at Fraser Highway

    Posted April 7, 2026 – This is an update to the notice posted on March 5, 2026. Station foundation construction at the station site on the west side of 152 Street and construction of a…

    Read more

  • Traffic Update: Fraser Highway and 140 Street

    Posted February 9, 2026 – Foundation work is occurring on Fraser Highway west of 140 Street and requires large, specialized equipment. Access to businesses west of 140 Street is available from 140 Street southbound only. There…

    Read more

  • UPDATED: Access Changes North of Fraser Highway at 138 Street

    Posted February 4, 2026 – This is an update to the notice posted on January 9, 2026. Construction activities include relocating existing utilities north of Fraser Highway at 138 Street. Traffic pattern changes will be…

    Read more

  • Access Change at Fraser Highway and 162 Street/84 Avenue

    Posted January 30, 2026 – There will be no access to/from 162 Street/84 Avenue from Fraser Highway beginning February 6 to February 13, 2026 and early March 2026 for one day. Please use alternate routes…

    Read more

  • UPDATED: Traffic Update: 152 Street at Fraser Highway

    Posted January 8, 2026 – This is an update to the notice posted on December 3, 2025. Construction activities include station foundation construction at the station site on the west side of 152 Street and…

    Read more

  • Traffic Update: Temporary access changes on Fraser Highway between 68 Avenue and 188 Street

    Posted March 7, 2025 – Activities include moving existing utilities to allow for construction, installing new utilities to supply power for the future SkyTrain, site preparation activities, roadwork and foundation construction. To support this work,…

    Read more

  • UPDATED: Traffic Update: Fraser Highway between 162 Street and 164 Street

    Posted February 19, 2025 – To support utility work, traffic pattern changes will be in effect until late February. Vehicle travel lanes on Fraser Highway between 162 Street and 164 Street will be shifted south…

    Read more

  • Traffic and Construction Update: Fraser Highway between 184 Street and 185 Street

    Posted December 2, 2024 – Starting early-December, construction will take place on the north side of Fraser Highway between 184 Street and 185 Street. There will be a temporary access restriction at 185 Street starting…

    Read more

  • Traffic Update: 166 Street and Fraser Highway Intersection

    Posted November 29, 2024 – During upcoming utility work, there will be temporary traffic pattern changes at the intersection of 166 Street and Fraser Highway. Traffic pattern changes are expected to begin December 2, 2024,…

    Read more

  • UPDATED: Traffic Update – Fraser Highway between Highway 15 and 184 Street

    Posted November 14, 2024 – The work previously planned to start mid-November is being rescheduled for late-November. Vehicle travel lanes on Fraser Highway between Highway 15 (176 Street) and 184 Street will be shifted south and…

    Read more

  • Notice of Evening Work Near 201A Street and Industrial Avenue

    To prepare for construction of the Surrey Langley SkyTrain, crews are starting early works on the site where the future 201 Street Propulsion Power Substation (PPS) will be located. A PPS supplies electrical power to…

    Read more

  • Notice of Evening Work Near 203 Street and Acacia Crescent

    To prepare for construction of the Surrey Langley SkyTrain, crews are starting early works on the property where the future Langley City Centre Station will be located. Materials for gravel surface treatment work will be…

    Read more

  • Demolition work at 6000 Production Way

    Posted June 26, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. Demolition of an existing structure, including utility disconnections, tree removal, hazardous material abatement and…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.