Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: February 17 – February 23

    Posted February 14, 2025 – This advisory outlines traffic pattern changes from February 17, 2025 – February 23, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: February 10 – February 16

    Posted February 7, 2025 – This advisory outlines traffic pattern changes from February 10, 2025 – February 16, 2025, along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: February 3 – February 9

    Posted January 31, 2025 – This advisory outlines traffic pattern changes from February 3, 2025 – February 9, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: January 27 – February 2

    Posted January 24, 2025 – This advisory outlines traffic pattern changes from January 27, 2025 – February 2, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: January 20 – January 26

    Posted January 17, 2025 – This advisory outlines traffic pattern changes from January 20, 2025 – January 26, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • UPDATED: Traffic Update: 152 Street at Fraser Highway

    Posted April 7, 2026 – This is an update to the notice posted on March 5, 2026. Station foundation construction at the station site on the west side of 152 Street and construction of a…

    Read more

  • Traffic Update: Fraser Highway and 140 Street

    Posted February 9, 2026 – Foundation work is occurring on Fraser Highway west of 140 Street and requires large, specialized equipment. Access to businesses west of 140 Street is available from 140 Street southbound only. There…

    Read more

  • UPDATED: Access Changes North of Fraser Highway at 138 Street

    Posted February 4, 2026 – This is an update to the notice posted on January 9, 2026. Construction activities include relocating existing utilities north of Fraser Highway at 138 Street. Traffic pattern changes will be…

    Read more

  • Access Change at Fraser Highway and 162 Street/84 Avenue

    Posted January 30, 2026 – There will be no access to/from 162 Street/84 Avenue from Fraser Highway beginning February 6 to February 13, 2026 and early March 2026 for one day. Please use alternate routes…

    Read more

  • UPDATED: Traffic Update: 152 Street at Fraser Highway

    Posted January 8, 2026 – This is an update to the notice posted on December 3, 2025. Construction activities include station foundation construction at the station site on the west side of 152 Street and…

    Read more

  • UPDATED: Multi-Use Path Closure from 168 Street to Highway 15

    Posted September 19, 2025 – This is an update to the notice distributed on May 23, 2025. A multi-use path closure from 168 Street to Highway 15 is in effect until January 2026, with modifications.…

    Read more

  • Extended hours on Fraser Highway between 170 Street to 180 Street

    Posted September 18, 2025 – Activities in this area include foundation construction, using driven and vibratory methods, rebar installation and concrete work. These activities are expected to continue through March 2026 and require extended hours,…

    Read more

  • Traffic Update: Turning restrictions at Fraser Highway and Highway 15

    Posted September 11, 2025 – Traffic pattern changes will be in effect from September 15, 2025, for up to three months. There will be no right turns from eastbound Fraser Highway to southbound Highway 15.…

    Read more

  • Traffic Update: Overnight Access Change at 166 Street and Fraser Highway

    Posted September 8, 2025 – To facilitate guideway construction, access to 166 Street north of Fraser Highway will be temporarily unavailable overnight from 8:00 p.m. to 7.00 a.m. starting September 14, 2025, for up to…

    Read more

  • Traffic Update: Overnight traffic pattern changes at Fraser Highway and Highway 15

    Posted August 14, 2025 – Overnight lane closures will be required on Highway 15, including intermittent turning restrictions at the Fraser Highway and Highway 15 intersection. Traffic changes will be in effect from August 17,…

    Read more

  • Traffic Update: Overnight single lane alternating traffic on Fraser Highway between 189 Street and 64 Avenue

    Posted April 29, 2026 – Construction at the future Clayton Station site is underway. To support survey activities, traffic pattern changes will be in effect the night of April 30, 2026. Survey work is not…

    Read more

  • UPDATED: Fraser Highway at 201A Street

    Posted March 13, 2026 – This is an update to the notice posted on February 18, 2026. Activities include utility relocations and installation of new utilities to power the future SkyTrain. As work progresses, the…

    Read more

  • Access change and extended hours at Willowbrook Drive north of Fraser Highway

    Posted February 12, 2026 – There will be no access to/from Willowbrook Drive north of Fraser Highway from February 19 to March 8, 2026. Alternate routes are available via 64 Avenue and 200 Street. Business…

    Read more

  • UPDATED: Fraser Highway between 200 Street and 201A Street

    Posted December 23, 2025 – This is an update to the notice posted on October 16, 2025. Traffic pattern changes are in effect on Fraser Highway from 200 Street to 201A Street until February 2026.…

    Read more

  • Traffic Update: Fraser Highway and 64 Avenue

    Posted December 18, 2025 – Traffic pattern changes will be in effect at the intersection of Fraser Highway and 64 Avenue beginning January 6, 2026 for approximately two weeks. There will be single lane traffic…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.