Construction Notice Archive
Find notifications that are no longer active.
Archived construction notifications are posted below.
Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.
Archived Notifications
Weekly Traffic Advisories
Find archived weekly summaries of traffic advisories for the Surrey Langley SkyTrain project.

-
Weekly Traffic Advisory: February 17 – February 23
Posted February 14, 2025 – This advisory outlines traffic pattern changes from February 17, 2025 – February 23, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
Weekly Traffic Advisory: February 10 – February 16
Posted February 7, 2025 – This advisory outlines traffic pattern changes from February 10, 2025 – February 16, 2025, along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
Weekly Traffic Advisory: February 3 – February 9
Posted January 31, 2025 – This advisory outlines traffic pattern changes from February 3, 2025 – February 9, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
Weekly Traffic Advisory: January 27 – February 2
Posted January 24, 2025 – This advisory outlines traffic pattern changes from January 27, 2025 – February 2, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
Weekly Traffic Advisory: January 20 – January 26
Posted January 17, 2025 – This advisory outlines traffic pattern changes from January 20, 2025 – January 26, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
UPDATED: Full Closure of Fraser Highway between 140 Street and 96 Avenue extended to mid-December
Posted October 21, 2025 – This is an update to the notice distributed on March 4, 2025, to reflect the extension of the closure. To accommodate the construction of Green Timbers Station, a full road closure…
-
UPDATED: Temporary Access Closure at 154 Street and Fraser Highway
Posted September 3, 2025 – This is an update to the notice posted July 30, 2025. Traffic pattern changes will be in effect from September 8-19, 2025. There will be no access at 154 Street. Access…
-
Traffic Update: Temporary Access Closure at 159 Street North of Fraser Highway
Posted August 20, 2025 – To allow for utility work within the intersection at Fraser Highway and 159 Street, traffic pattern changes will be in effect on August 22 and August 25, 2025, as well…
-
UPDATED: Traffic Update: Road Closure at 84 Avenue South of Fraser Highway
Posted August 11, 2025 – This is an update to the notice posted on June 9, 2025. Traffic pattern changes will be in effect for one day on August 12, 2025. There will be no access…
-
Traffic Update: Night work and turn restrictions at Fraser Highway and 152 Street
Posted July 21, 2025 – Night work is required to support activities and reduce overall traffic impacts from August 5 to August 21, 2025. Turning restrictions at the intersection will be in effect from 7…
-
Traffic Update: Overnight closure of Highway 15 at Fraser Highway
Posted March 30, 2026 – To support guideway work over Highway 15, a section of Highway 15 south of Fraser Highway will be closed for four consecutive nights, from 12 a.m. to 4 a.m., April…
-
Traffic Update: Access change on 166 Street north of Fraser Highway
Posted March 5, 2026 – To support utility installations, there will be no access to the Surrey Sport & Leisure Complex from the north end of 166 Street starting March 9, 2026, for up to…
-
Station Construction Underway at Hillcrest-184 Street Station
Posted December 18, 2025 – Station foundation construction, including pile driving, will begin mid-January 2026 and occur for approximately two months, through mid-March 2026. Temporary increases in noise and vibrations are anticipated. View detailed notice…
-
Station Construction Underway at Bakerview-166 Street Station
Posted November 27, 2025 – Construction is underway for the future Bakerview-166 Street Station. Station foundation construction, including pile driving, will begin early December and occur for approximately three months, through mid-February 2026. Access to…
-
Traffic Update: Access change on 166 Street and Fraser Highway
Posted September 22, 2025 – A traffic pattern change will take place on 166 Street and Fraser Highway from September 22, 2025, for up to one month. Access to 166 Street is available from Fraser…
-
Traffic Update: Overnight single lane alternating traffic on Fraser Highway between 189 Street and 64 Avenue
Posted April 29, 2026 – Construction at the future Clayton Station site is underway. To support survey activities, traffic pattern changes will be in effect the night of April 30, 2026. Survey work is not…
-
UPDATED: Fraser Highway at 201A Street
Posted March 13, 2026 – This is an update to the notice posted on February 18, 2026. Activities include utility relocations and installation of new utilities to power the future SkyTrain. As work progresses, the…
-
Access change and extended hours at Willowbrook Drive north of Fraser Highway
Posted February 12, 2026 – There will be no access to/from Willowbrook Drive north of Fraser Highway from February 19 to March 8, 2026. Alternate routes are available via 64 Avenue and 200 Street. Business…
-
UPDATED: Fraser Highway between 200 Street and 201A Street
Posted December 23, 2025 – This is an update to the notice posted on October 16, 2025. Traffic pattern changes are in effect on Fraser Highway from 200 Street to 201A Street until February 2026.…
-
Traffic Update: Fraser Highway and 64 Avenue
Posted December 18, 2025 – Traffic pattern changes will be in effect at the intersection of Fraser Highway and 64 Avenue beginning January 6, 2026 for approximately two weeks. There will be single lane traffic…
Precast Concrete Facility
Find archived notifications for the precast concrete facility located at 195 Street and 24 Avenue.

No results found