Construction Notice Archive
Find notifications that are no longer active.
Archived construction notifications are posted below.
Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.
Archived Notifications
Weekly Traffic Advisories
Find archived weekly summaries of traffic advisories for the Surrey Langley SkyTrain project.

-
Weekly Traffic Advisory: February 17 – February 23
Posted February 14, 2025 – This advisory outlines traffic pattern changes from February 17, 2025 – February 23, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
Weekly Traffic Advisory: February 10 – February 16
Posted February 7, 2025 – This advisory outlines traffic pattern changes from February 10, 2025 – February 16, 2025, along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
Weekly Traffic Advisory: February 3 – February 9
Posted January 31, 2025 – This advisory outlines traffic pattern changes from February 3, 2025 – February 9, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
Weekly Traffic Advisory: January 27 – February 2
Posted January 24, 2025 – This advisory outlines traffic pattern changes from January 27, 2025 – February 2, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
Weekly Traffic Advisory: January 20 – January 26
Posted January 17, 2025 – This advisory outlines traffic pattern changes from January 20, 2025 – January 26, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
Traffic Update: Road Closure at Fleetwood Way North of Fraser Highway
Posted July 8, 2025 – Traffic pattern changes will be in effect from July 10, 2025, for approximately one week. Fleetwood Way north of Fraser Highway will be closed with no access to vehicle traffic. An…
-
Traffic Update: Temporary access change at 154 Street and Fraser Highway
Posted June 27, 2025 – Traffic pattern changes will be in effect from July 2, 2025, for up to one week. There will be a temporary access restriction at 154 Street. Access to/from Fraser Highway…
-
Construction Update: Night Work at Green Timbers Station (140 Street)
Posted May 21, 2025 – Our stations and guideway contractors are currently working at the future Green Timbers Station, located within the road closure area on Fraser Highway between 140 Street and 96 Avenue. To…
-
Traffic Update: Intersection Work at Fraser Highway and 156 Street
Posted May 16, 2025 – Activities include construction of a new utility crossing, within the intersection of Fraser Highway at 156 Street, to supply power for the future SkyTrain. Traffic pattern changes will be in…
-
Traffic Update: Closure of 144 Street South of Fraser Highway
Posted April 24, 2025 – 144 Street will be closed to vehicle traffic between Fraser Highway and 92 Avenue from April 29, 2025 to May 2, 2025. Alternate routes are available via 88 Avenue to…
-
Traffic Update: Access change on 166 Street and Fraser Highway
Posted September 22, 2025 – A traffic pattern change will take place on 166 Street and Fraser Highway from September 22, 2025, for up to one month. Access to 166 Street is available from Fraser…
-
Traffic Update: Overnight Access Change at 166 Street and Fraser Highway
Posted September 8, 2025 – To facilitate guideway construction, access to 166 Street north of Fraser Highway will be temporarily unavailable overnight from 8:00 p.m. to 7.00 a.m. starting September 14, 2025, for up to…
-
Traffic Update: Overnight traffic pattern changes at Fraser Highway and Highway 15
Posted August 14, 2025 – Overnight lane closures will be required on Highway 15, including intermittent turning restrictions at the Fraser Highway and Highway 15 intersection. Traffic changes will be in effect from August 17,…
-
Traffic Update: Access Change Fraser Highway west of 68 Avenue
Posted July 25, 2025 – An access change will be in effect at Fraser Highway west of 68 Avenue from July 28, 2025, for approximately one week. There will be no access to/from Fraser Highway…
-
Traffic Update: Intersection work at Fraser Highway and 184 Street
Posted July 18, 2025 – Traffic changes will be in effect at the Fraser Highway and 184 Street intersection from July 21, 2025, for approximately two weeks. Traffic will be reduced to one lane in…
-
UPDATED: Lane and Parking Impacts Around 203 Street, Industrial Avenue and Acacia Crescent
Posted August 8, 2024 – This is an update of the notification from July 30, 2024 as dates of work have changed. Crews will be conducting pre-condition surveys (PCS) around the future Langley City Centre Station and…
-
Lane Reduction on 203 Street, 203A Street and Acacia Crescent
Posted July 24, 2024 – To prepare for construction of the Surrey Langley SkyTrain, crews will be conducting pre-condition surveys (PCS) around the future Langley City Centre Station and the 201 Street Propulsion Power Substation (PPS)…
-
Notice of Evening Work Near 201A Street and Industrial Avenue
To prepare for construction of the Surrey Langley SkyTrain, crews are starting early works on the site where the future 201 Street Propulsion Power Substation (PPS) will be located. A PPS supplies electrical power to…
-
Notice of Evening Work Near 203 Street and Acacia Crescent
To prepare for construction of the Surrey Langley SkyTrain, crews are starting early works on the property where the future Langley City Centre Station will be located. Materials for gravel surface treatment work will be…
-
Demolition work at 6000 Production Way
Posted June 26, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. Demolition of an existing structure, including utility disconnections, tree removal, hazardous material abatement and…
Precast Concrete Facility
Find archived notifications for the precast concrete facility located at 195 Street and 24 Avenue.

No results found