Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: May 18 to May 24, 2026

    Posted May 15, 2026 – This advisory outlines traffic pattern changes from May 18 to May 24, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: May 11 – May 17, 2026

    Posted May 8, 2026 – This advisory outlines traffic pattern changes from May 11 to May 17, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: May 4 –10, 2026

    Posted May 1, 2026 – This advisory outlines traffic pattern changes from May 4-10, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: April 27 – May 3, 2026

    Posted April 24, 2026 – This advisory outlines traffic pattern changes from April 27 – May 3, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: April 20 – April 26, 2026

    Posted April 17, 2026 – This advisory outlines traffic pattern changes from April 20 – April 26, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Traffic Update: Fraser Highway between 140 Street and 96 Avenue

    Posted December 5, 2025 – Following the re-opening of the Fraser Highway closure area between 140 Street and 96 Avenue on December 14, 2025, there will be single lane traffic in each direction on Fraser…

    Read more

  • Traffic Update: 152 Street at Fraser Highway

    Posted December 3, 2025 – Construction activities include station foundation construction at the station site on the west side of 152 Street and construction of a station entrance (head house) on the east side of…

    Read more

  • Traffic Update: Fraser Highway and 160 Street

    Posted November 27, 2025 – To carry out the installation of new utilities, there will be left and right turn restrictions at the intersection of Fraser Highway and 160 Street from December 1 until December…

    Read more

  • UPDATED: Access Change at Fleetwood Way and Fraser Highway

    Posted November 3, 2025 – This is an update to the notice distributed on October 23, 2025 to reflect the schedule change. To support foundation construction for the future guideway, there will be no access to/from…

    Read more

  • Traffic Update: Temporary Access Closure at 159 Street North of Fraser Highway

    Posted October 22, 2025 – There will be no access to/from 159 Street north of Fraser Highway from October 22 to November 14, 2025. Single lane alternating access will be available east of 159 Street…

    Read more

  • UPDATED: Multi-Use Path Closure from 168 Street to Highway 15

    Posted September 19, 2025 – This is an update to the notice distributed on May 23, 2025. A multi-use path closure from 168 Street to Highway 15 is in effect until January 2026, with modifications.…

    Read more

  • Extended hours on Fraser Highway between 170 Street to 180 Street

    Posted September 18, 2025 – Activities in this area include foundation construction, using driven and vibratory methods, rebar installation and concrete work. These activities are expected to continue through March 2026 and require extended hours,…

    Read more

  • Traffic Update: Turning restrictions at Fraser Highway and Highway 15

    Posted September 11, 2025 – Traffic pattern changes will be in effect from September 15, 2025, for up to three months. There will be no right turns from eastbound Fraser Highway to southbound Highway 15.…

    Read more

  • Traffic Update: Overnight Access Change at 166 Street and Fraser Highway

    Posted September 8, 2025 – To facilitate guideway construction, access to 166 Street north of Fraser Highway will be temporarily unavailable overnight from 8:00 p.m. to 7.00 a.m. starting September 14, 2025, for up to…

    Read more

  • Traffic Update: Overnight traffic pattern changes at Fraser Highway and Highway 15

    Posted August 14, 2025 – Overnight lane closures will be required on Highway 15, including intermittent turning restrictions at the Fraser Highway and Highway 15 intersection. Traffic changes will be in effect from August 17,…

    Read more

  • Traffic Update: Closure of 189 Street Intersection North of Fraser Highway

    Posted April 22, 2025 – Current work includes building a new utility crossing at 189 Street, just north of the Fraser Highway intersection. To support this work, traffic changes will be in effect from May…

    Read more

  • Traffic Update: Closure of 68 Avenue North of Fraser Highway

    Posted April 10, 2025 – To support ongoing SkyTrain construction, there will be a closure at 68 Avenue North of Fraser Highway from April 22, 2025, to April 25, 2025. The travelling public can expect…

    Read more

  • Traffic Update: Utility locate activities on Langley Lane (Laneway east of Fraser Highway and south of Highway 10)

    Posted March 27, 2025 – Activities include early works to prepare for construction of the future SkyTrain, including foundation and guideway construction. Single lane alternating traffic will be in effect. Traffic control personnel will be…

    Read more

  • Construction Activities: Industrial Avenue between 200 Street and 203 Street

    Posted March 14, 2025 – Preliminary activities will occur intermittently on Industrial Avenue from 200 Street to 203 Street from March 19, 2025 through spring 2025. Activities include survey work, utility investigation and vegetation management.…

    Read more

  • Traffic Update: Temporary access changes on Fraser Highway between 68 Avenue and 188 Street

    Posted March 7, 2025 – Activities include moving existing utilities to allow for construction, installing new utilities to supply power for the future SkyTrain, site preparation activities, roadwork and foundation construction. To support this work,…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.