Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: November 11 – November 17, 2024

    Posted November 8, 2024 – This advisory outlines traffic pattern changes during the week of November 11 – November 17, 2024. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: November 4 – November 10, 2024

    Posted November 1 – This advisory outlines traffic pattern changes during the week of November 4 – November 10, 2024. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • UPDATED: Overnight closure and extended hours on Fraser Highway between 140 Street and 96 Avenue

    This is an update to the notice distributed on June 29, 2026. This notice provides details of upcoming overnight construction to support the Surrey Langley SkyTrain. Fraser Highway will be fully closed between 140 Street and 96 Avenue from July 6…

    Read more

  • Traffic Update: Overnight closure on Fraser Highway between 140 Street and 96 Avenue

    Posted June 29, 2026 – This notice provides details of upcoming overnight construction to support the Surrey Langley SkyTrain. Fraser Highway will be fully closed between 140 Street and 96 Avenue from July 6 to…

    Read more

  • UPDATE:  Overnight closures on Fraser Highway between 140 Street and 148 Street

    Posted June 12, 2026 – Overnight closure on Fraser Highway for SkyTrain construction from 9 p.m. to 5:30 a.m. June 10 and June 11, 2026 and 9 p.m. to 5:30 a.m. June 12, 14 and 15, 2026. Pedestrian and…

    Read more

  • Multi-use pathway closure on Fraser Highway at 138 Street

    Posted May 29, 2026 – Temporary multi-use pathway closure on the north side of Fraser Highway at 138 Street until June 9, 2026. Pedestrian access will reopen when work is complete for the day.  Alternate…

    Read more

  • Traffic Update: Turn restrictions at 160 Street and Fraser Highway

    Posted May 27, 2026 – Turn restrictions at 160 Street and Fraser Highway will be in effect during launching gantry operations from June 2 to June 9 2026. Alternate routes available. Turn restrictions removed at…

    Read more

  • Traffic Update: Access change on 166 Street and Fraser Highway

    Posted September 22, 2025 – A traffic pattern change will take place on 166 Street and Fraser Highway from September 22, 2025, for up to one month. Access to 166 Street is available from Fraser…

    Read more

  • UPDATED: Multi-Use Path Closure from 168 Street to Highway 15

    Posted September 19, 2025 – This is an update to the notice distributed on May 23, 2025. A multi-use path closure from 168 Street to Highway 15 is in effect until January 2026, with modifications.…

    Read more

  • Extended hours on Fraser Highway between 170 Street to 180 Street

    Posted September 18, 2025 – Activities in this area include foundation construction, using driven and vibratory methods, rebar installation and concrete work. These activities are expected to continue through March 2026 and require extended hours,…

    Read more

  • Traffic Update: Turning restrictions at Fraser Highway and Highway 15

    Posted September 11, 2025 – Traffic pattern changes will be in effect from September 15, 2025, for up to three months. There will be no right turns from eastbound Fraser Highway to southbound Highway 15.…

    Read more

  • Traffic Update: Overnight Access Change at 166 Street and Fraser Highway

    Posted September 8, 2025 – To facilitate guideway construction, access to 166 Street north of Fraser Highway will be temporarily unavailable overnight from 8:00 p.m. to 7.00 a.m. starting September 14, 2025, for up to…

    Read more

  • Traffic Update: Overnight single lane alternating traffic on Fraser Highway between 189 Street and 64 Avenue

    Posted April 29, 2026 – Construction at the future Clayton Station site is underway. To support survey activities, traffic pattern changes will be in effect the night of April 30, 2026. Survey work is not…

    Read more

  • Station Construction Underway at Willowbrook Station

    Posted April 1, 2026 – Construction for the future Willowbrook Station is underway. Station foundation construction, including pile driving, will begin mid-April and occur for approximately two months, through mid-June 2026. Temporary increases in noise…

    Read more

  • UPDATED: Fraser Highway at 201A Street

    Posted March 13, 2026 – This is an update to the notice posted on February 18, 2026. Activities include utility relocations and installation of new utilities to power the future SkyTrain. As work progresses, the…

    Read more

  • Traffic Update: Turn restrictions at Fraser Highway and Highway 10

    Posted February 25, 2026 – Installation of new utilities underneath Highway 10 to support the future SkyTrain is underway. To support this work, there will be no left turns from Fraser Highway to Highway 10…

    Read more

  • UPDATED: Foundation Construction Laneway East of Highway 10

    Posted February 12, 2026 – This is an update to the notice posted February 4, 2026. Construction of the elevated guideway is underway in the laneway near Highway 10 and Fraser Highway. Foundation construction in…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.