Weekly Traffic Advisories
Find archived weekly summaries of traffic advisories for the Surrey Langley SkyTrain project.

-
Weekly Traffic Advisory: April 20 – April 26, 2026
Posted April 17, 2026 – This advisory outlines traffic pattern changes from April 20 – April 26, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: April 13 – April 19, 2026
Posted April 10, 2026 – This advisory outlines traffic pattern changes from April 13 – April 19, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: April 6 – April 12, 2026
Posted April 2, 2026 – This advisory outlines traffic pattern changes from April 6 – April 12, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: March 30 – April 5, 2026
Posted March 27, 2026 – This advisory outlines traffic pattern changes from March 30 – April 5, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: March 23 – March 29, 2026
Posted March 20, 2026 – This advisory outlines traffic pattern changes from March 23 – March 29, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
UPDATED: Foundation Construction along Fraser Highway
Posted January 8, 2025 – Current construction activities for the Surrey Langley SkyTrain project include preparing sites and ground improvements to support the future guideway piers and SkyTrain stations. Foundation construction will occur throughout the…
-
Traffic Update: Fraser Highway between 148 and 152 Street
Posted October 9, 2024 – Travel lanes, pedestrian, and cycling lanes will be adjusted on Fraser Highway between 148 Street and 152 Street. There will be intermittent lane closures on the approach to the intersection…
-
Notice of work on 140 Street and Fraser Highway
Posted September 5, 2024 – Hydrovac work will take place on 140 Street and Fraser Highway on September 9 and September 10. The hydrovac work requires a single lane closure northbound for the trucks and…
-
Site preparations for upcoming construction
Posted September 5, 2024 – Crews will be working on clearing, grubbing, removing and disposing of vegetation and debris along Fraser Highway starting September 9 and lasting for approximately two weeks at the following locations:…
-
UPDATED: Various works along Fraser Highway between 140 & 192 Street
Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…
-
Extended Hours: Fraser Highway east of Highway 15
Posted May 12, 2026 – Extended work hours will be in effect from 10 p.m. to 7 a.m., May 19 to May 22, 2026, to support Surrey Langley SkyTrain construction. Overnight work is required to…
-
Traffic Update: Overnight closure of Highway 15 at Fraser Highway
Posted March 30, 2026 – To support guideway work over Highway 15, a section of Highway 15 south of Fraser Highway will be closed for four consecutive nights, from 12 a.m. to 4 a.m., April…
-
Traffic Update: Access change on 166 Street north of Fraser Highway
Posted March 5, 2026 – To support utility installations, there will be no access to the Surrey Sport & Leisure Complex from the north end of 166 Street starting March 9, 2026, for up to…
-
Station Construction Underway at Hillcrest-184 Street Station
Posted December 18, 2025 – Station foundation construction, including pile driving, will begin mid-January 2026 and occur for approximately two months, through mid-March 2026. Temporary increases in noise and vibrations are anticipated. View detailed notice…
-
Station Construction Underway at Bakerview-166 Street Station
Posted November 27, 2025 – Construction is underway for the future Bakerview-166 Street Station. Station foundation construction, including pile driving, will begin early December and occur for approximately three months, through mid-February 2026. Access to…
-
Traffic Update: Overnight closure of 200 Street between Fraser Highway and Production Way
Posted May 11, 2026 – Temporary traffic changes will be in place to support Surrey Langley SkyTrain construction. From 12 a.m. to 5 a.m. on May 13, 2026, there will be no through access on…
-
Traffic Update: Temporary intersection closure at Industrial Avenue and 203 Street
Posted May 7, 2026 – Temporary traffic changes are required to support Surrey Langley SkyTrain construction, including installation of the elevated guideway. From 7 a.m. May 16 to 10 p.m. May 18, 2026, the intersection…
-
Traffic Update: Overnight single lane alternating traffic on Fraser Highway between 189 Street and 64 Avenue
Posted April 29, 2026 – Construction at the future Clayton Station site is underway. To support survey activities, traffic pattern changes will be in effect the night of April 30, 2026. Survey work is not…
-
UPDATED: Fraser Highway at 201A Street
Posted March 13, 2026 – This is an update to the notice posted on February 18, 2026. Activities include utility relocations and installation of new utilities to power the future SkyTrain. As work progresses, the…
-
Traffic Update: Turn restrictions at Fraser Highway and Highway 10
Posted February 25, 2026 – Installation of new utilities underneath Highway 10 to support the future SkyTrain is underway. To support this work, there will be no left turns from Fraser Highway to Highway 10…
Precast Concrete Facility
Find archived notifications for the precast concrete facility located at 195 Street and 24 Avenue.

No results found