  • Weekly Traffic Advisory: July 6 to July 12, 2026

    Posted July 3, 2026 – This advisory outlines traffic pattern changes from July 6 to July 12, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: June 29 to July 5, 2026

    Posted June 26, 2026 – This advisory outlines traffic pattern changes from June 29 to July 5, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: June 22 to June 28, 2026

    Posted June 19, 2026 – This advisory outlines traffic pattern changes from June 22 to June 28, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: June 15 to June 21, 2026

    Posted June 12, 2026 – This advisory outlines traffic pattern changes from June 15 to June 21, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: June 8 to June 14, 2026

    Posted June 5, 2026 – This advisory outlines traffic pattern changes from June 8 to June 14, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Traffic Update: Temporary access change at 154 Street and Fraser Highway

    Posted June 27, 2025 – Traffic pattern changes will be in effect from July 2, 2025, for up to one week. There will be a temporary access restriction at 154 Street. Access to/from Fraser Highway…

    Read more

  • Construction Update: Night Work at Green Timbers Station (140 Street)

    Posted May 21, 2025 – Our stations and guideway contractors are currently working at the future Green Timbers Station, located within the road closure area on Fraser Highway between 140 Street and 96 Avenue. To…

    Read more

  • Traffic Update: Intersection Work at Fraser Highway and 156 Street

    Posted May 16, 2025 – Activities include construction of a new utility crossing, within the intersection of Fraser Highway at 156 Street, to supply power for the future SkyTrain. Traffic pattern changes will be in…

    Read more

  • Traffic Update: Closure of 144 Street South of Fraser Highway

    Posted April 24, 2025 – 144 Street will be closed to vehicle traffic between Fraser Highway and 92 Avenue from April 29, 2025 to May 2, 2025. Alternate routes are available via 88 Avenue to…

    Read more

  • Traffic Update: Fraser Highway between 148 Street and 152 Street

    Posted April 9, 2025 – To support ongoing SkyTrain construction, there will be traffic changes on Fraser Highway between 148 Street and 152 Street from mid-April 2025 until Spring 2026. The travelling public can expect…

    Read more

  • Station Construction Underway at Hillcrest-184 Street Station

    Posted December 18, 2025 – Station foundation construction, including pile driving, will begin mid-January 2026 and occur for approximately two months, through mid-March 2026. Temporary increases in noise and vibrations are anticipated.  View detailed notice…

    Read more

  • Station Construction Underway at Bakerview-166 Street Station

    Posted November 27, 2025 – Construction is underway for the future Bakerview-166 Street Station. Station foundation construction, including pile driving, will begin early December and occur for approximately three months, through mid-February 2026. Access to…

    Read more

  • Traffic Update: Access change on 166 Street and Fraser Highway

    Posted September 22, 2025 – A traffic pattern change will take place on 166 Street and Fraser Highway from September 22, 2025, for up to one month. Access to 166 Street is available from Fraser…

    Read more

  • UPDATED: Multi-Use Path Closure from 168 Street to Highway 15

    Posted September 19, 2025 – This is an update to the notice distributed on May 23, 2025. A multi-use path closure from 168 Street to Highway 15 is in effect until January 2026, with modifications.…

    Read more

  • Extended hours on Fraser Highway between 170 Street to 180 Street

    Posted September 18, 2025 – Activities in this area include foundation construction, using driven and vibratory methods, rebar installation and concrete work. These activities are expected to continue through March 2026 and require extended hours,…

    Read more

  • UPDATED: Temporary intersection closure and extended hours at Industrial Avenue and 203 Street

    Posted September 28, 2026 – This is an update to the notice posted on September 14, 2026. To support concrete work and concrete pours on a portion of the elevated guideway on Industrial Avenue and over…

    Read more

  • UPDATED: No access to 188 Street from Fraser Highway

    Posted September 15, 2026 – This is an update to the notice posted on September 11, 2026. No access to/from 188 Street and Fraser Highway September 25, 28, 29, and October 1 and 2, 2026 from 7 a.m.…

    Read more

  • UPDATED: Extended hours and no access to Willowbrook Drive/196 Street north of Fraser Highway

    Posted September 22, 2026 – This is an update to the notice posted on September 10, 2026. To support guideway installation, the following traffic pattern changes will be in effect from September 24 to 26,…

    Read more

  • UPDATED: Traffic Update: Pedestrian access change between 62A Avenue and Fraser Highway 

    Posted September 1, 2026 – This is an update to the notice posted on August 19, 2026.  To support guideway installation as the launching gantry moves east, a pedestrian access change will be in effect until September…

    Read more

  • Traffic Update: No access to 68 Avenue north of Fraser Highway

    Posted August 18, 2026 – To support the installation of a new traffic signal and road restoration work, temporary traffic pattern changes will be in effect from August 24 to September 1, 2026. No access…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.