Weekly Traffic Advisories
Find archived weekly summaries of traffic advisories for the Surrey Langley SkyTrain project.

-
Weekly Traffic Advisory: September 14 to September 20, 2026
Posted September 11, 2026 – This advisory outlines traffic pattern changes from September 14 to September 20, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: September 7 to September 13, 2026
Posted September 4, 2026 – This advisory outlines traffic pattern changes from September 7 to September 13, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: August 31 to September 6, 2026
Posted August 28, 2026 – This advisory outlines traffic pattern changes from August 31 to September 6, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: August 24 to August 30, 2026
Posted August 21, 2026 – This advisory outlines traffic pattern changes from August 24 to August 30, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: August 17 to August 23, 2026
Posted August 14, 2026 – This advisory outlines traffic pattern changes from August 17 to August 23, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Traffic Update: Temporary access change at 154 Street and Fraser Highway
Posted June 27, 2025 – Traffic pattern changes will be in effect from July 2, 2025, for up to one week. There will be a temporary access restriction at 154 Street. Access to/from Fraser Highway…
-
Construction Update: Night Work at Green Timbers Station (140 Street)
Posted May 21, 2025 – Our stations and guideway contractors are currently working at the future Green Timbers Station, located within the road closure area on Fraser Highway between 140 Street and 96 Avenue. To…
-
Traffic Update: Intersection Work at Fraser Highway and 156 Street
Posted May 16, 2025 – Activities include construction of a new utility crossing, within the intersection of Fraser Highway at 156 Street, to supply power for the future SkyTrain. Traffic pattern changes will be in…
-
Traffic Update: Closure of 144 Street South of Fraser Highway
Posted April 24, 2025 – 144 Street will be closed to vehicle traffic between Fraser Highway and 92 Avenue from April 29, 2025 to May 2, 2025. Alternate routes are available via 88 Avenue to…
-
Traffic Update: Fraser Highway between 148 Street and 152 Street
Posted April 9, 2025 – To support ongoing SkyTrain construction, there will be traffic changes on Fraser Highway between 148 Street and 152 Street from mid-April 2025 until Spring 2026. The travelling public can expect…
-
Station Construction Underway at Hillcrest-184 Street Station
Posted December 18, 2025 – Station foundation construction, including pile driving, will begin mid-January 2026 and occur for approximately two months, through mid-March 2026. Temporary increases in noise and vibrations are anticipated. View detailed notice…
-
Station Construction Underway at Bakerview-166 Street Station
Posted November 27, 2025 – Construction is underway for the future Bakerview-166 Street Station. Station foundation construction, including pile driving, will begin early December and occur for approximately three months, through mid-February 2026. Access to…
-
Traffic Update: Access change on 166 Street and Fraser Highway
Posted September 22, 2025 – A traffic pattern change will take place on 166 Street and Fraser Highway from September 22, 2025, for up to one month. Access to 166 Street is available from Fraser…
-
UPDATED: Multi-Use Path Closure from 168 Street to Highway 15
Posted September 19, 2025 – This is an update to the notice distributed on May 23, 2025. A multi-use path closure from 168 Street to Highway 15 is in effect until January 2026, with modifications.…
-
Extended hours on Fraser Highway between 170 Street to 180 Street
Posted September 18, 2025 – Activities in this area include foundation construction, using driven and vibratory methods, rebar installation and concrete work. These activities are expected to continue through March 2026 and require extended hours,…
-
Traffic Update: Fraser Highway between 200 Street and 201A Street
Posted October 16, 2025 – Traffic pattern changes will be in effect on Fraser Highway from 200 Street to 201A Street from October 20 to late December 2025. The centre left turn lane will be…
-
Traffic Update: Turning restrictions on Fraser Highway at 195A Street and Willowbrook Drive
Posted October 10, 2025 – Temporary turning restrictions will be in effect on a 24/7 basis starting the week of October 20 for approximately one week. There will be no left turns to Willowbrook Drive…
-
UPDATED: Guideway Construction Underway on Industrial Avenue
Posted October 3, 2025 – This is an update to the notice distributed on September 10, 2025, to reflect the addition of Saturday work. Construction of the elevated guideway on Industrial Avenue (west of the…
-
Traffic Update: Turn restrictions at Fraser Highway and 64 Avenue
Posted August 14, 2025 – To allow for utility work within the intersection at 64 Avenue and Fraser Highway, traffic pattern changes will be in effect from August 14, 2025, until August 29, 2025. There…
-
Traffic Update: Fraser Highway between 196 Street and 200 Street
Posted August 6, 2025 – Activities include foundation construction, pier construction, utility relocations, installation of new utilities to power the SkyTrain and road works. To carry out this work, traffic pattern changes will be in…
Precast Concrete Facility
Find archived notifications for the precast concrete facility located at 195 Street and 24 Avenue.