Traffic Alert: Full closure in effect on Fraser Highway between 140 Street and 96 Avenue until end of October, 2025. Alternate route available via 96 Avenue. Click to view detailed notification

Current construction information, including notifications of upcoming work, is posted below. Archived notifications can be found on our Construction Notice Archive webpage.

Major construction on the SkyTrain extension is underway. We are currently focused on utility work, vegetation management, roadworks, foundation construction, and other related activities.

Construction hours across the project are 7 a.m. to 10 p.m. Monday to Saturday with most construction activities being completed by 8 p.m. Some activities may be required outside of regular work hours during lower traffic volumes, to reduce impacts to businesses or to accommodate concrete pours.

People who travel on Fraser Highway should plan additional travel time or consider alternative routes, as work is taking place in multiple locations along the corridor. You can continue to access businesses, services and residences along Fraser Highway and Industrial Avenue throughout construction.

Please see notifications below and contact us if you have specific questions about what’s happening currently on and near the project alignment. Sign up to receive project updates and construction notices.

Advance works by BC Hydro, including vegetation clearing and power line relocation, are currently underway along Fraser Highway. Learn more about their work here: bchydro.com/skytrain

Note: Drones will be used throughout the duration of the Surrey Langley SkyTrain Project to monitor and document project work, with no intention of collecting personal information. Please see our related FOIPPA notice on the use of drones.

Current Work Areas

The Surrey Langley SkyTrain project work areas have been identified to correspond with the future SkyTrain stations. View our station map to see each station location and find project notifications by station area posted below.

Station map showing where each of the new eight stations will be in Surrey and Langley.
  • Construction Update – Spring 2025

    Posted May 14, 2025 – Construction of the Surrey Langley SkyTrain is underway. This newsletter provides an overview of current and upcoming project activities from May 2025 through July 2025 for each project area. View…

    Read more

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: May 26 – June 1, 2025

    Posted May 23, 2025 – This advisory outlines traffic pattern changes from May 26, 2025 – June 1, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to…

    Read more

  • Weekly Traffic Advisory: May 19 – May 25

    Posted May 16, 2025 – This advisory outlines traffic pattern changes from May 19, 2025 – May 25, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to…

    Read more

  • Weekly Traffic Advisory: May 12 – May 18

    Posted May 9, 2025 – This advisory outlines traffic pattern changes from May 12, 2025 – May 18, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to…

    Read more

  • Weekly Traffic Advisory: May 5 – May 11

    Posted May 2, 2025 – This advisory outlines traffic pattern changes from May 5, 2025 – May 11, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to…

    Read more

  • Weekly Traffic Advisory: April 28 – May 4

    Posted April 25, 2025 – This advisory outlines traffic pattern changes from April 28, 2025 – May 4, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to…

    Read more

A rendering of the future Green Timbers Station.
  • Construction Update: Night Work at Green Timbers Station (140 Street)

    Posted May 21, 2025 – Our stations and guideway contractors are currently working at the future Green Timbers Station, located within the road closure area on Fraser Highway between 140 Street and 96 Avenue. To…

    Read more

  • Traffic Update: Closure of 144 Street South of Fraser Highway

    Posted April 24, 2025 – 144 Street will be closed to vehicle traffic between Fraser Highway and 92 Avenue from April 29, 2025 to May 2, 2025. Alternate routes are available via 88 Avenue to…

    Read more

  • Full Closure: Fraser Highway between 140 Street and 96 Avenue

    Posted March 4, 2025 – To accommodate the construction of Green Timbers Station, which will be built directly above Fraser Highway, a full road closure is required.  To safely accommodate this work, Fraser Highway will…

    Read more

  • UPDATED: Foundation Construction along Fraser Highway

    Posted January 8, 2025 – Current construction activities for the Surrey Langley SkyTrain project include preparing sites and ground improvements to support the future guideway piers and SkyTrain stations. Foundation construction will occur throughout the…

    Read more

A rendering of the future 152 Street Station.
  • Traffic Update: Intersection Work at Fraser Highway and 156 Street

    Posted May 16, 2025 – Activities include construction of a new utility crossing, within the intersection of Fraser Highway at 156 Street, to supply power for the future SkyTrain. Traffic pattern changes will be in…

    Read more

  • Traffic Update: Fraser Highway between 148 Street and 152 Street

    Posted April 9, 2025 – To support ongoing SkyTrain construction, there will be traffic changes on Fraser Highway between 148 Street and 152 Street from mid-April 2025 until Spring 2026. The travelling public can expect…

    Read more

  • UPDATED: Foundation Construction along Fraser Highway

    Posted January 8, 2025 – Current construction activities for the Surrey Langley SkyTrain project include preparing sites and ground improvements to support the future guideway piers and SkyTrain stations. Foundation construction will occur throughout the…

    Read more

  • Traffic Update: Fraser Highway between 148 and 152 Street

    Posted October 9, 2024 – Travel lanes, pedestrian, and cycling lanes will be adjusted on Fraser Highway between 148 Street and 152 Street. There will be intermittent lane closures on the approach to the intersection…

    Read more

A rendering of the future Fleetwood Station
  • Traffic Update: Intersection Work at Fraser Highway and 156 Street

    Posted May 16, 2025 – Activities include construction of a new utility crossing, within the intersection of Fraser Highway at 156 Street, to supply power for the future SkyTrain. Traffic pattern changes will be in…

    Read more

  • Cycling Detour: Fraser Highway between 156 Street and 84 Avenue

    Posted March 19, 2025 – To accommodate construction activities along Fraser Highway between 156 Street and 84 Avenue, cyclists will be detoured off of Fraser Highway. During this period, cyclists will be accommodated within existing…

    Read more

  • Traffic Update: Fraser Highway between 154 Street and 160 Street

    Posted March 18, 2025 – Traffic changes will be in effect March 24, 2025, through summer 2026. Lane closures will be implemented on Fraser Highway between 154 Street and 160 Street. Traffic will be reduced…

    Read more

  • UPDATED: Foundation Construction along Fraser Highway

    Posted January 8, 2025 – Current construction activities for the Surrey Langley SkyTrain project include preparing sites and ground improvements to support the future guideway piers and SkyTrain stations. Foundation construction will occur throughout the…

    Read more

A rendering of the future Bakerview-166 Street Station.
  • UPDATED: Traffic Pattern and Project Update – Fraser Highway and 166 Street

    Posted November 7, 2024 – The work previously planned to start mid-November is being rescheduled for December 2024.  This is an update of the notification from October 21, 2024. View detailed notice If you have…

    Read more

A rendering of the future Hillcrest-184 Street Station.
  • Traffic Update: Closure of 188 Street North of Fraser Highway

    Posted April 4, 2024 – To support ongoing SkyTrain construction, including the installation of new utilities,188 Street north of Fraser Highway will be closed April 14, 2025, through April 16, 2025. The travelling public can…

    Read more

  • Traffic Update: Temporary access changes on Fraser Highway between 68 Avenue and 188 Street

    Posted March 7, 2025 – Activities include moving existing utilities to allow for construction, installing new utilities to supply power for the future SkyTrain, site preparation activities, roadwork and foundation construction. To support this work,…

    Read more

  • UPDATED: Foundation Construction along Fraser Highway

    Posted January 8, 2025 – Current construction activities for the Surrey Langley SkyTrain project include preparing sites and ground improvements to support the future guideway piers and SkyTrain stations. Foundation construction will occur throughout the…

    Read more

  • UPDATED: Traffic Update – Fraser Highway between Highway 15 and 184 Street

    Posted November 14, 2024 – The work previously planned to start mid-November is being rescheduled for late-November. Vehicle travel lanes on Fraser Highway between Highway 15 (176 Street) and 184 Street will be shifted south and…

    Read more

A rendering of the future Clayton Station.
  • Traffic Update: Closure of 188 Street North of Fraser Highway

    Posted May 23, 2025 – Construction for the Surrey Langley SkyTrain is underway, including the installation of new utilities to power the future SkyTrain. Traffic pattern changes will be in effect from June 9, 2025,…

    Read more

  • Traffic Update: Access Closure at Fraser Highway and 191A Street

    Posted May 20, 2025 – Traffic pattern changes will be in effect beginning the week of May 26, 2025, for approximately 10 days. There will be no access to/from Fraser Highway and 191A Street. Alternate…

    Read more

  • Station construction underway at Clayton Station site

    Posted May 5, 2025 – Work is beginning at the new Clayton Station on Fraser Highway at 190 Street (east of 189 Street). Station foundation construction, including pile driving, will begin mid-May and continue through…

    Read more

  • Traffic Update: Closure of 189 Street Intersection North of Fraser Highway

    Posted April 22, 2025 – Current work includes building a new utility crossing at 189 Street, just north of the Fraser Highway intersection. To support this work, traffic changes will be in effect from May…

    Read more

  • Traffic Update: Closure of 68 Avenue North of Fraser Highway

    Posted April 10, 2025 – To support ongoing SkyTrain construction, there will be a closure at 68 Avenue North of Fraser Highway from April 22, 2025, to April 25, 2025. The travelling public can expect…

    Read more

A rendering of the future Willowbrook Station.
  • Traffic Update: Utility locate activities on Langley Lane (Laneway east of Fraser Highway and south of Highway 10)

    Posted March 27, 2025 – Activities include early works to prepare for construction of the future SkyTrain, including foundation and guideway construction. Single lane alternating traffic will be in effect. Traffic control personnel will be…

    Read more

  • Traffic Update: Fraser Highway between 196 Street and Highway 10

    Posted March 7, 2025 – Activities will include roadwork, installing construction fencing around work areas, moving existing utilities to allow for construction and installing new utilities to supply power for the future SkyTrain. Foundation construction…

    Read more

  • Traffic Update: Fraser Highway between 64 Avenue and 196 Street

    Posted February 5, 2025 – Vehicle travel lanes on Fraser Highway between 64 Avenue and 196 Street/Willowbrook Drive will be reduced to single lanes westbound and eastbound. Traffic pattern changes will be in effect from…

    Read more

A rendering of the future Langley City Centre Station.
  • Station and Guideway Construction Underway at Langley City Centre Station

    Posted May 13, 2025 – Work is beginning at the new Langley City Centre Station site on 203 Street and Industrial Avenue, for the elevated guideway on Industrial Avenue and at the Propulsion Power Substation…

    Read more

  • Construction Activities: Industrial Avenue between 200 Street and 203 Street

    Posted March 14, 2025 – Preliminary activities will occur intermittently on Industrial Avenue from 200 Street to 203 Street from March 19, 2025 through spring 2025. Activities include survey work, utility investigation and vegetation management.…

    Read more

  • UPDATED: Traffic Update: 203 Street and 203A Street

    Posted February, 20, 2025 – Single lane traffic northbound and southbound between Acacia Crescent and just north of Industrial Avenue. 203A Street will be temporarily closed to all through traffic from Locke Lane to Imperial…

    Read more

An image showing the construction of the production building at the Precast Concrete Facility.
  • Precast Concrete Facility

    Posted January 27, 2025 – The concrete segments for the elevated guideway will be built at a SkyTrain precast concrete facility located at 195 Street and 24 Avenue in Surrey. Once construction of the precast facility is complete, operations at the facility involve casting concrete SkyTrain guideway segments and transporting them to the SkyTrain route…

    Read more