  • Weekly Traffic Advisory: February 16 – February 22, 2026

    Posted February 13, 2026 – This advisory outlines traffic pattern changes from February 16 – February 22, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: February 9 – February 15, 2026

    Posted February 6, 2026 – This advisory outlines traffic pattern changes from February 9 – February 15, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: February 2 – February 8, 2026

    Posted January 30, 2026 – This advisory outlines traffic pattern changes from February 2 – February 8, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: January 26 – February 1, 2026

    Posted January 23, 2026 – This advisory outlines traffic pattern changes from January 26 – February 1, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: January 19 – January 25, 2026

    Posted January 16, 2026 – This advisory outlines traffic pattern changes from January 19 – January 25, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • UPDATED: Traffic Update: 152 Street at Fraser Highway

    Posted April 7, 2026 – This is an update to the notice posted on March 5, 2026. Station foundation construction at the station site on the west side of 152 Street and construction of a…

    Read more

  • Traffic Update: Fraser Highway and 140 Street

    Posted February 9, 2026 – Foundation work is occurring on Fraser Highway west of 140 Street and requires large, specialized equipment. Access to businesses west of 140 Street is available from 140 Street southbound only. There…

    Read more

  • UPDATED: Access Changes North of Fraser Highway at 138 Street

    Posted February 4, 2026 – This is an update to the notice posted on January 9, 2026. Construction activities include relocating existing utilities north of Fraser Highway at 138 Street. Traffic pattern changes will be…

    Read more

  • Access Change at Fraser Highway and 162 Street/84 Avenue

    Posted January 30, 2026 – There will be no access to/from 162 Street/84 Avenue from Fraser Highway beginning February 6 to February 13, 2026 and early March 2026 for one day. Please use alternate routes…

    Read more

  • UPDATED: Traffic Update: 152 Street at Fraser Highway

    Posted January 8, 2026 – This is an update to the notice posted on December 3, 2025. Construction activities include station foundation construction at the station site on the west side of 152 Street and…

    Read more

  • Demolition work at 18543 and 18565 Fraser Highway

    Posted August 7, 2024 – Demolition will take place at 18543 Fraser Highway and 18565 Fraser Highway in the coming weeks. This work will include utility disconnections, hazardous material abatements, and other related activities. Construction activities…

    Read more

  • Demolition Work at 8215 166 Street and Fraser Highway

    Posted August 6, 2024 – Demolition of an existing structure including utility disconnections, hazardous material abatements, and other miscellaneous activities, will take place at 8215 166 Street in the coming weeks. Construction activities are expected to…

    Read more

  • UPDATED: Guideway Construction Underway on Industrial Avenue

    Posted October 3, 2025 – This is an update to the notice distributed on September 10, 2025, to reflect the addition of Saturday work. Construction of the elevated guideway on Industrial Avenue (west of the…

    Read more

  • Traffic Update: Turn restrictions at Fraser Highway and 64 Avenue

    Posted August 14, 2025 – To allow for utility work within the intersection at 64 Avenue and Fraser Highway, traffic pattern changes will be in effect from August 14, 2025, until August 29, 2025. There…

    Read more

  • Traffic Update: Fraser Highway between 196 Street and 200 Street

    Posted August 6, 2025 – Activities include foundation construction, pier construction, utility relocations, installation of new utilities to power the SkyTrain and road works. To carry out this work, traffic pattern changes will be in…

    Read more

  • Traffic Update: Access Change Fraser Highway west of 68 Avenue

    Posted July 25, 2025 – An access change will be in effect at Fraser Highway west of 68 Avenue from July 28, 2025, for approximately one week. There will be no access to/from Fraser Highway…

    Read more

  • Traffic Update: Industrial Avenue between 200 Street and 201A Street 

    Posted July 9, 2025 – Utility relocations will be underway on Industrial Avenue, including upcoming intermittent activities from 200 Street to 201A Street. This work is anticipated through summer 2026. There will be traffic pattern…