Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: November 4 – November 10, 2024

    Posted November 1 – This advisory outlines traffic pattern changes during the week of November 4 – November 10, 2024. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • UPDATED: Access change 138 Street north of Fraser Highway

    Posted October 28, 2026 – this is an update to the notice posted on October 5, 2026. There will be no vehicle access to/from 138 Street north of Fraser Highway until mid-December 2026. Cyclist and…

    Read more

  • UPDATED: Extended hours and overnight road closures at 140 Street and Fraser Highway

    Posted October 23, 2026 – this is an update to the notice posted on October 22, 2026. Surrey Langley SkyTrain construction is underway. A launching gantry, the Surrey Sprinter, is installing the guideway for the…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 152 Street

    Posted October 16, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work at the future 152 Street Station. To carry out this work, extended hours will be in effect on October 20 and…

    Read more

  • SCHEDULE CHANGE: Turn restriction at Fraser Highway and 152 Street

    Posted October 9, 2026 – This is an update to the notice distributed on October 9, 2026 to reflect a change in dates. The work scheduled for October 13 to November 20, 2026 is being…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 160 Street

    Posted October 7, 2026 – Surrey Langley SkyTrain construction is progressing, including concrete pours and concrete work at the future Fleetwood Station. To carry out this work, extended hours will be in effect on October…

    Read more

  • Traffic Update: Temporary access changes on Fraser Highway between 68 Avenue and 188 Street

    Posted March 7, 2025 – Activities include moving existing utilities to allow for construction, installing new utilities to supply power for the future SkyTrain, site preparation activities, roadwork and foundation construction. To support this work,…

    Read more

  • UPDATED: Traffic Update: Fraser Highway between 162 Street and 164 Street

    Posted February 19, 2025 – To support utility work, traffic pattern changes will be in effect until late February. Vehicle travel lanes on Fraser Highway between 162 Street and 164 Street will be shifted south…

    Read more

  • Traffic Update: Fraser Highway between 168 Street and east of Highway 15

    Posted February 4, 2025 – Vehicle travel lanes on Fraser Highway between 168 Street and east of Highway 15 will be reduced to single lanes westbound and eastbound. Traffic pattern changes will be in effect…

    Read more

  • Traffic and Construction Update: Fraser Highway between 184 Street and 185 Street

    Posted December 2, 2024 – Starting early-December, construction will take place on the north side of Fraser Highway between 184 Street and 185 Street. There will be a temporary access restriction at 185 Street starting…

    Read more

  • Traffic Update: 166 Street and Fraser Highway Intersection

    Posted November 29, 2024 – During upcoming utility work, there will be temporary traffic pattern changes at the intersection of 166 Street and Fraser Highway. Traffic pattern changes are expected to begin December 2, 2024,…

    Read more

  • UPDATED: Lane and Parking Impacts Around 203 Street, Industrial Avenue and Acacia Crescent

    Posted August 8, 2024 – This is an update of the notification from July 30, 2024 as dates of work have changed. Crews will be conducting pre-condition surveys (PCS) around the future Langley City Centre Station and…

    Read more

  • Lane Reduction on 203 Street, 203A Street and Acacia Crescent

    Posted July 24, 2024 – To prepare for construction of the Surrey Langley SkyTrain, crews will be conducting pre-condition surveys (PCS) around the future Langley City Centre Station and the 201 Street Propulsion Power Substation (PPS)…

    Read more

  • Notice of Evening Work Near 201A Street and Industrial Avenue

    To prepare for construction of the Surrey Langley SkyTrain, crews are starting early works on the site where the future 201 Street Propulsion Power Substation (PPS) will be located. A PPS supplies electrical power to…

    Read more

  • Notice of Evening Work Near 203 Street and Acacia Crescent

    To prepare for construction of the Surrey Langley SkyTrain, crews are starting early works on the property where the future Langley City Centre Station will be located. Materials for gravel surface treatment work will be…

    Read more

  • Demolition work at 6000 Production Way

    Posted June 26, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. Demolition of an existing structure, including utility disconnections, tree removal, hazardous material abatement and…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.