Weekly Traffic Advisory: May 11 – May 17, 2026
Posted May 8, 2026 – This advisory outlines traffic pattern changes from May 11 to May 17, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: May 4 –10, 2026
Posted May 1, 2026 – This advisory outlines traffic pattern changes from May 4-10, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: April 27 – May 3, 2026
Posted April 24, 2026 – This advisory outlines traffic pattern changes from April 27 – May 3, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: April 20 – April 26, 2026
Posted April 17, 2026 – This advisory outlines traffic pattern changes from April 20 – April 26, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: April 13 – April 19, 2026
Posted April 10, 2026 – This advisory outlines traffic pattern changes from April 13 – April 19, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Notice of work on 140 Street and Fraser Highway
Posted September 5, 2024 – Hydrovac work will take place on 140 Street and Fraser Highway on September 9 and September 10. The hydrovac work requires a single lane closure northbound for the trucks and…
-
Site preparations for upcoming construction
Posted September 5, 2024 – Crews will be working on clearing, grubbing, removing and disposing of vegetation and debris along Fraser Highway starting September 9 and lasting for approximately two weeks at the following locations:…
-
UPDATED: Various works along Fraser Highway between 140 & 192 Street
Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…
-
Vegetation management at 15079 Fraser Highway
Posted August 22, 2024 – Vegetation management activities, including tree removal, will take place at 15079 Fraser Highway. This location is a future site office that will accommodate staff and workers of SkyLink Guideway Partners.…
-
UPDATED: Lane Closure on Fraser Highway between 150 and 170 Street
Posted August 22, 2024- This is an update of the notification from August 1, 2024 as the date of work has changed. Existing streetlights on the south side of Fraser Highway between 150 and 170 Street will…
-
UPDATED: No access to 182 Street south of Fraser Highway
Posted October 1, 2026 – This is an update to the notice posted on September 18, 2026 Surrey Langley SkyTrain construction is progressing, including installation of utilities for future traffic signals. To support this work,…
-
Traffic Update: Turn restriction and pedestrian access change at Fraser Highway at 184 Street
Posted September 14 – To support the installation of new utilities near the future Hillcrest-184 Street Station, the following traffic pattern changes will be in effect from 9 a.m. to 3 p.m. September 14 to…
-
Traffic Update: Single lane alternating traffic on Fraser Highway at 184 Street
Posted September 9, 2026 – To support box beam installation work, temporary traffic pattern changes will be in effect on September 11, 2026. Lane reductions on the approach to the intersection on 184 Street. Single…
-
Extended Hours: Fraser Highway east of Highway 15
Posted May 12, 2026 – Extended work hours will be in effect from 10 p.m. to 7 a.m., May 19 to May 22, 2026, to support Surrey Langley SkyTrain construction. Overnight work is required to…
-
Traffic Update: Overnight closure of Highway 15 at Fraser Highway
Posted March 30, 2026 – To support guideway work over Highway 15, a section of Highway 15 south of Fraser Highway will be closed for four consecutive nights, from 12 a.m. to 4 a.m., April…
-
Traffic Update: Access Change Fraser Highway west of 68 Avenue
Posted July 25, 2025 – An access change will be in effect at Fraser Highway west of 68 Avenue from July 28, 2025, for approximately one week. There will be no access to/from Fraser Highway…
-
Traffic Update: Industrial Avenue between 200 Street and 201A Street
Posted July 9, 2025 – Utility relocations will be underway on Industrial Avenue, including upcoming intermittent activities from 200 Street to 201A Street. This work is anticipated through summer 2026. There will be traffic pattern…
-
Traffic Update: Industrial Avenue between 201A Street and 203 Street
Posted June 20, 2025 – Activities include utility relocations on Industrial Avenue, followed by foundation and pier construction starting at 203 Street and moving towards 201A Street. This work is anticipated through summer 2026. There…
-
Traffic Update: Access Closure at Fraser Highway and 189 Street
Posted June 11, 2025 – Traffic pattern changes will be in place at 189 Street and Fraser Highway from July 3 to July 11, 2025. Traffic on Fraser Highway will be reduced to a single…
-
Traffic Update: Utility Activities Near 203 Street and Fraser Highway
Posted May 29, 2025 – Activities include two days of utility inspection work to prepare for the construction of the future Langley City Centre Station. To support this work, temporary traffic changes will be in…
Precast Concrete Facility
Find archived notifications for the precast concrete facility located at 195 Street and 24 Avenue.