Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: November 4 – November 10, 2024

    Posted November 1 – This advisory outlines traffic pattern changes during the week of November 4 – November 10, 2024. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Traffic Update: Fraser Highway between 140 Street and 148 Street

    Posted January 20, 2025 – Activities include moving existing utilities to allow for construction, installing new utilities to supply power for the future SkyTrain, roadwork and foundation construction. There will be various traffic pattern changes…

    Read more

  • UPDATED: Foundation Construction along Fraser Highway

    Posted January 8, 2025 – Current construction activities for the Surrey Langley SkyTrain project include preparing sites and ground improvements to support the future guideway piers and SkyTrain stations. Foundation construction will occur throughout the…

    Read more

  • Traffic Update: Fraser Highway between 148 and 152 Street

    Posted October 9, 2024 – Travel lanes, pedestrian, and cycling lanes will be adjusted on Fraser Highway between 148 Street and 152 Street. There will be intermittent lane closures on the approach to the intersection…

    Read more

  • Notice of work on 140 Street and Fraser Highway

    Posted September 5, 2024 – Hydrovac work will take place on 140 Street and Fraser Highway on September 9 and September 10. The hydrovac work requires a single lane closure northbound for the trucks and…

    Read more

  • Site preparations for upcoming construction

    Posted September 5, 2024 – Crews will be working on clearing, grubbing, removing and disposing of vegetation and debris along Fraser Highway starting September 9 and lasting for approximately two weeks at the following locations:…

    Read more

  • Construction Update: Extended hours at Bakerview-166 Street Station

    Posted November 6, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work at Bakerview-166 Street Station. To carry out this work, extended hours will be in effect on Monday, November 9, 2026, from…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 184 Street

    Posted October 30, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work for the future Hillcrest-184 Street Station. To carry out this work, extended hours will be in effect on November 3, 2026,…

    Read more

  • Construction Update: Sunday work at Bakerview-166 Street and Hillcrest-184 Street Stations

    Posted October 22, 2026 – Surrey Langley SkyTrain construction is underway, including rebar, concrete, and structure work for the future Bakerview-166 Street and Hillcrest-184 Street stations. To carry out these activities, Sunday work will occur…

    Read more

  • Traffic Update: Turn restrictions at Fraser Highway and 184 Street

    Posted October 16, 2026 – Surrey Langley construction is underway, including road restoration activities and electrical work to support the installation of new traffic signals at the intersection. The following traffic pattern changes are in…

    Read more

  • Construction Update: Extended hours Fraser Highway east of Highway 15

    Posted October 13, 2026 – Surrey Langley SkyTrain construction is underway. A launching gantry, the Clayton Clipper, is installing the guideway for the future SkyTrain. Segment delivery and installation is taking place on Fraser Highway,…

    Read more

  • Traffic Update: Turn restrictions at Fraser Highway and Highway 10

    Posted February 25, 2026 – Installation of new utilities underneath Highway 10 to support the future SkyTrain is underway. To support this work, there will be no left turns from Fraser Highway to Highway 10…

    Read more

  • UPDATED: Foundation Construction Laneway East of Highway 10

    Posted February 12, 2026 – This is an update to the notice posted February 4, 2026. Construction of the elevated guideway is underway in the laneway near Highway 10 and Fraser Highway. Foundation construction in…

    Read more

  • Access change and extended hours at Willowbrook Drive north of Fraser Highway

    Posted February 12, 2026 – There will be no access to/from Willowbrook Drive north of Fraser Highway from February 19 to March 8, 2026. Alternate routes are available via 64 Avenue and 200 Street. Business…

    Read more

  • Construction Update: Pile Driving in Langley

    Posted January 16, 2026 – Construction crews will be pile driving for the guideway foundations in Langley City beginning in February 2026. Expect traffic pattern changes, an increase in noise and vibrations, and possible night…

    Read more

  • UPDATED: Fraser Highway between 200 Street and 201A Street

    Posted December 23, 2025 – This is an update to the notice posted on October 16, 2025. Traffic pattern changes are in effect on Fraser Highway from 200 Street to 201A Street until February 2026.…

    Read more