Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: October 26 to November 1, 2026

    Posted October 23, 2026 – This advisory outlines traffic pattern changes from October 26 to November 1, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: October 19 to October 25, 2026

    Posted October 16, 2026 – This advisory outlines traffic pattern changes from October 19 to October 25, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: October 12 to October 18, 2026

    Posted October 9, 2026 – This advisory outlines traffic pattern changes from October 12 to October 18, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: October 5 to October 11, 2026

    Posted October 2, 2026 – This advisory outlines traffic pattern changes from October 5 to October 11, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 28 to October 4, 2026

    Posted September 25, 2026 – This advisory outlines traffic pattern changes from September 28 to October 4, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Traffic Update: Fraser Highway between 154 Street and 160 Street

    Posted March 18, 2025 – Traffic changes will be in effect March 24, 2025, through summer 2026. Lane closures will be implemented on Fraser Highway between 154 Street and 160 Street. Traffic will be reduced…

    Read more

  • Full Closure: Fraser Highway between 140 Street and 96 Avenue

    Posted March 4, 2025 – To accommodate the construction of Green Timbers Station, which will be built directly above Fraser Highway, a full road closure is required.  To safely accommodate this work, Fraser Highway will…

    Read more

  • UPDATED: Temporary access change west of 160 Street and Fraser Highway

    Posted February 26, 2025 – There will be various traffic pattern changes in effect from mid-March 2025 for approximately ten days. Westbound right lane closure on Fraser Highway west of 160 Street. Right turn access to…

    Read more

  • UPDATED: Temporary access change at 154 Street and Fraser Highway

    Posted February 26, 2025 – Vehicle travel lanes between 152 Street and 154 Street will be reduced to single lanes westbound and eastbound. No right turn onto 154 Street for vehicles travelling westbound on Fraser Highway.…

    Read more

  • UPDATED: Traffic Update: Fraser Highway between 162 Street and 164 Street

    Posted February 19, 2025 – To support utility work, traffic pattern changes will be in effect until late February. Vehicle travel lanes on Fraser Highway between 162 Street and 164 Street will be shifted south…

    Read more

  • Piling activities at various locations on Fraser Highway

    Posted August 20, 2024 – Construction activities including geotechnical investigations and test piling activities are scheduled along Fraser Highway in September at various locations. There may be an increase of noise generated by the drilling…

    Read more

  • Demolition work at 18543 and 18565 Fraser Highway

    Posted August 7, 2024 – Demolition will take place at 18543 Fraser Highway and 18565 Fraser Highway in the coming weeks. This work will include utility disconnections, hazardous material abatements, and other related activities. Construction activities…

    Read more

  • Demolition Work at 8215 166 Street and Fraser Highway

    Posted August 6, 2024 – Demolition of an existing structure including utility disconnections, hazardous material abatements, and other miscellaneous activities, will take place at 8215 166 Street in the coming weeks. Construction activities are expected to…

    Read more

  • Station and Guideway Construction Underway at Langley City Centre Station

    Posted May 13, 2025 – Work is beginning at the new Langley City Centre Station site on 203 Street and Industrial Avenue, for the elevated guideway on Industrial Avenue and at the Propulsion Power Substation…

    Read more

  • Station construction underway at Clayton Station site

    Posted May 5, 2025 – Work is beginning at the new Clayton Station on Fraser Highway at 190 Street (east of 189 Street). Station foundation construction, including pile driving, will begin mid-May and continue through…

    Read more

  • Traffic Update: Closure of 189 Street Intersection North of Fraser Highway

    Posted April 22, 2025 – Current work includes building a new utility crossing at 189 Street, just north of the Fraser Highway intersection. To support this work, traffic changes will be in effect from May…

    Read more

  • Traffic Update: Closure of 68 Avenue North of Fraser Highway

    Posted April 10, 2025 – To support ongoing SkyTrain construction, there will be a closure at 68 Avenue North of Fraser Highway from April 22, 2025, to April 25, 2025. The travelling public can expect…

    Read more

  • Traffic Update: Utility locate activities on Langley Lane (Laneway east of Fraser Highway and south of Highway 10)

    Posted March 27, 2025 – Activities include early works to prepare for construction of the future SkyTrain, including foundation and guideway construction. Single lane alternating traffic will be in effect. Traffic control personnel will be…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.