Construction Notice Archive
Find notifications that are no longer active.
Archived construction notifications are posted below.
Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.
Archived Notifications
Weekly Traffic Advisories
Find archived weekly summaries of traffic advisories for the Surrey Langley SkyTrain project.

-
Weekly Traffic Advisory: May 4 –10, 2026
Posted May 1, 2026 – This advisory outlines traffic pattern changes from May 4-10, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: April 27 – May 3, 2026
Posted April 24, 2026 – This advisory outlines traffic pattern changes from April 27 – May 3, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: April 20 – April 26, 2026
Posted April 17, 2026 – This advisory outlines traffic pattern changes from April 20 – April 26, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: April 13 – April 19, 2026
Posted April 10, 2026 – This advisory outlines traffic pattern changes from April 13 – April 19, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: April 6 – April 12, 2026
Posted April 2, 2026 – This advisory outlines traffic pattern changes from April 6 – April 12, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Demolition Work Continues Adjacent to Fraser Highway Near 152 Street
Posted August 14, 2024 – Demolition of select existing structures including utility disconnections, hazardous material abatements, and other miscellaneous activities, will continue to take place adjacent to Fraser Highway near 152 Street in the coming…
-
Demolition work at 16039 Fraser Highway
Posted August 7, 2024 – Demolition of select existing structures including utility disconnections, hazardous material abatements, and other related activities, will take place at 16039 Fraser Highway in the coming weeks. Construction activities are expected to…
-
Demolition work at various locations near Fraser Hwy
To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. Demolition of existing structures, including utility disconnections, tree removal, hazardous material abatement and other miscellaneous activities, will take…
-
Demolition work at 18543 and 18565 Fraser Highway
Posted August 7, 2024 – Demolition will take place at 18543 Fraser Highway and 18565 Fraser Highway in the coming weeks. This work will include utility disconnections, hazardous material abatements, and other related activities. Construction activities…
-
Demolition Work at 8215 166 Street and Fraser Highway
Posted August 6, 2024 – Demolition of an existing structure including utility disconnections, hazardous material abatements, and other miscellaneous activities, will take place at 8215 166 Street in the coming weeks. Construction activities are expected to…
-
Geotechnical Investigation on Industrial Ave
Posted October 10, 2024 – Geotechnical investigation to gather information about ground conditions for the future location of piers will occur on Industrial Avenue, starting October 16 for approximately two weeks. There will be parking…
-
Site preparations for upcoming construction
Posted September 5, 2024 – Crews will be working on clearing, grubbing, removing and disposing of vegetation and debris along Fraser Highway starting September 9 and lasting for approximately two weeks at the following locations:…
-
UPDATED: Various works along Fraser Highway between 140 & 192 Street
Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…
-
UPDATED: Lane and Parking Impacts Around 203 Street, Industrial Avenue and Acacia Crescent
Posted August 8, 2024 – This is an update of the notification from July 30, 2024 as dates of work have changed. Crews will be conducting pre-condition surveys (PCS) around the future Langley City Centre Station and…
-
Lane Reduction on 203 Street, 203A Street and Acacia Crescent
Posted July 24, 2024 – To prepare for construction of the Surrey Langley SkyTrain, crews will be conducting pre-condition surveys (PCS) around the future Langley City Centre Station and the 201 Street Propulsion Power Substation (PPS)…
Precast Concrete Facility
Find archived notifications for the precast concrete facility located at 195 Street and 24 Avenue.

No results found



