Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: October 26 to November 1, 2026

    Posted October 23, 2026 – This advisory outlines traffic pattern changes from October 26 to November 1, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: October 19 to October 25, 2026

    Posted October 16, 2026 – This advisory outlines traffic pattern changes from October 19 to October 25, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: October 12 to October 18, 2026

    Posted October 9, 2026 – This advisory outlines traffic pattern changes from October 12 to October 18, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: October 5 to October 11, 2026

    Posted October 2, 2026 – This advisory outlines traffic pattern changes from October 5 to October 11, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 28 to October 4, 2026

    Posted September 25, 2026 – This advisory outlines traffic pattern changes from September 28 to October 4, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Construction Update: Night Work at Green Timbers Station (140 Street)

    Posted May 21, 2025 – Our stations and guideway contractors are currently working at the future Green Timbers Station, located within the road closure area on Fraser Highway between 140 Street and 96 Avenue. To…

    Read more

  • Traffic Update: Intersection Work at Fraser Highway and 156 Street

    Posted May 16, 2025 – Activities include construction of a new utility crossing, within the intersection of Fraser Highway at 156 Street, to supply power for the future SkyTrain. Traffic pattern changes will be in…

    Read more

  • Traffic Update: Closure of 144 Street South of Fraser Highway

    Posted April 24, 2025 – 144 Street will be closed to vehicle traffic between Fraser Highway and 92 Avenue from April 29, 2025 to May 2, 2025. Alternate routes are available via 88 Avenue to…

    Read more

  • Traffic Update: Fraser Highway between 148 Street and 152 Street

    Posted April 9, 2025 – To support ongoing SkyTrain construction, there will be traffic changes on Fraser Highway between 148 Street and 152 Street from mid-April 2025 until Spring 2026. The travelling public can expect…

    Read more

  • Cycling Detour: Fraser Highway between 156 Street and 84 Avenue

    Posted March 19, 2025 – To accommodate construction activities along Fraser Highway between 156 Street and 84 Avenue, cyclists will be detoured off of Fraser Highway. During this period, cyclists will be accommodated within existing…

    Read more

  • Piling activities at various locations on Fraser Highway

    Posted August 20, 2024 – Construction activities including geotechnical investigations and test piling activities are scheduled along Fraser Highway in September at various locations. There may be an increase of noise generated by the drilling…

    Read more

  • Demolition work at 18543 and 18565 Fraser Highway

    Posted August 7, 2024 – Demolition will take place at 18543 Fraser Highway and 18565 Fraser Highway in the coming weeks. This work will include utility disconnections, hazardous material abatements, and other related activities. Construction activities…

    Read more

  • Demolition Work at 8215 166 Street and Fraser Highway

    Posted August 6, 2024 – Demolition of an existing structure including utility disconnections, hazardous material abatements, and other miscellaneous activities, will take place at 8215 166 Street in the coming weeks. Construction activities are expected to…

    Read more

  • Traffic Update: Fraser Highway and 64 Avenue

    Posted December 18, 2025 – Traffic pattern changes will be in effect at the intersection of Fraser Highway and 64 Avenue beginning January 6, 2026 for approximately two weeks. There will be single lane traffic…

    Read more

  • Traffic Update: Access Change to Langley Lane (Laneway East of Highway 10)

    Posted November 21, 2025 – Utility work is beginning in the laneway east of Highway 10 (Langley Lane) in late November 2025 through the end of 2025. Langley Lane will be accessible for business deliveries…

    Read more

  • Nightwork at Fraser Highway and 200 Street

    Posted November 21, 2025 – Utility relocations and the installation of new infrastructure to support the future line are underway. Nighttime traffic pattern change will be in effect at the intersection of 200 Street and…

    Read more

  • Traffic Update: Access Changes at Westbrook Centre and Surlang Centre

    Posted November 10, 2025 – There will be access changes to/from Westbrook Centre and Surlang Centre along Fraser Highway west of Willowbrook Drive/196 Street between November 12 – December 4, 2025. View detailed notice If…

    Read more

  • Traffic Update: Fraser Highway between 200 Street and 201A Street

    Posted October 16, 2025 – Traffic pattern changes will be in effect on Fraser Highway from 200 Street to 201A Street from October 20 to late December 2025. The centre left turn lane will be…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.