  • Weekly Traffic Advisory: June 2- June 8, 2025

    Posted May 30, 2025 – This advisory outlines traffic pattern changes from June 2, 2025 – June 8, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: May 26 – June 1, 2025

    Posted May 23, 2025 – This advisory outlines traffic pattern changes from May 26, 2025 – June 1, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: May 19 – May 25

    Posted May 16, 2025 – This advisory outlines traffic pattern changes from May 19, 2025 – May 25, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: May 12 – May 18

    Posted May 9, 2025 – This advisory outlines traffic pattern changes from May 12, 2025 – May 18, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: May 5 – May 11

    Posted May 2, 2025 – This advisory outlines traffic pattern changes from May 5, 2025 – May 11, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Traffic Update: Closure of 144 Street South of Fraser Highway

    Posted April 24, 2025 – 144 Street will be closed to vehicle traffic between Fraser Highway and 92 Avenue from April 29, 2025 to May 2, 2025. Alternate routes are available via 88 Avenue to…

    Read more

  • Traffic Update: Fraser Highway between 148 Street and 152 Street

    Posted April 9, 2025 – To support ongoing SkyTrain construction, there will be traffic changes on Fraser Highway between 148 Street and 152 Street from mid-April 2025 until Spring 2026. The travelling public can expect…

    Read more

  • Full Closure: Fraser Highway between 140 Street and 96 Avenue

    Posted March 4, 2025 – To accommodate the construction of Green Timbers Station, which will be built directly above Fraser Highway, a full road closure is required.  To safely accommodate this work, Fraser Highway will…

    Read more

  • UPDATED: Temporary access change west of 160 Street and Fraser Highway

    Posted February 26, 2025 – There will be various traffic pattern changes in effect from mid-March 2025 for approximately ten days. Westbound right lane closure on Fraser Highway west of 160 Street. Right turn access to…

    Read more

  • UPDATED: Temporary access change at 154 Street and Fraser Highway

    Posted February 26, 2025 – Vehicle travel lanes between 152 Street and 154 Street will be reduced to single lanes westbound and eastbound. No right turn onto 154 Street for vehicles travelling westbound on Fraser Highway.…

    Read more

  • Traffic Update: Overnight closure of Highway 15 at Fraser Highway

    Posted March 30, 2026 – To support guideway work over Highway 15, a section of Highway 15 south of Fraser Highway will be closed for four consecutive nights, from 12 a.m. to 4 a.m., April…

    Read more

  • Traffic Update: Access change on 166 Street north of Fraser Highway

    Posted March 5, 2026 – To support utility installations, there will be no access to the Surrey Sport & Leisure Complex from the north end of 166 Street starting March 9, 2026, for up to…

    Read more

  • Station Construction Underway at Hillcrest-184 Street Station

    Posted December 18, 2025 – Station foundation construction, including pile driving, will begin mid-January 2026 and occur for approximately two months, through mid-March 2026. Temporary increases in noise and vibrations are anticipated.  View detailed notice…

    Read more

  • Station Construction Underway at Bakerview-166 Street Station

    Posted November 27, 2025 – Construction is underway for the future Bakerview-166 Street Station. Station foundation construction, including pile driving, will begin early December and occur for approximately three months, through mid-February 2026. Access to…

    Read more

  • Traffic Update: Access change on 166 Street and Fraser Highway

    Posted September 22, 2025 – A traffic pattern change will take place on 166 Street and Fraser Highway from September 22, 2025, for up to one month. Access to 166 Street is available from Fraser…

    Read more

  • Geotechnical Investigation on Industrial Ave

    Posted October 10, 2024 – Geotechnical investigation to gather information about ground conditions for the future location of piers will occur on Industrial Avenue, starting October 16 for approximately two weeks. There will be parking…

    Read more

  • Site preparations for upcoming construction

    Posted September 5, 2024 – Crews will be working on clearing, grubbing, removing and disposing of vegetation and debris along Fraser Highway starting September 9 and lasting for approximately two weeks at the following locations:…

    Read more

  • UPDATED: Various works along Fraser Highway between 140 & 192 Street

    Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…

    Read more

  • UPDATED: Lane and Parking Impacts Around 203 Street, Industrial Avenue and Acacia Crescent

    Posted August 8, 2024 – This is an update of the notification from July 30, 2024 as dates of work have changed. Crews will be conducting pre-condition surveys (PCS) around the future Langley City Centre Station and…

    Read more

  • Lane Reduction on 203 Street, 203A Street and Acacia Crescent

    Posted July 24, 2024 – To prepare for construction of the Surrey Langley SkyTrain, crews will be conducting pre-condition surveys (PCS) around the future Langley City Centre Station and the 201 Street Propulsion Power Substation (PPS)…

    Read more