Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: July 14 – July 20, 2025

    Posted July 11, 2025 – This advisory outlines traffic pattern changes from July 14, 2025 – July 20, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: July 7 – July 13, 2025

    Posted July 4, 2025 – This advisory outlines traffic pattern changes from July 7, 2025 – July 13, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: June 30 – July 6, 2025

    Posted June 27, 2025 – This advisory outlines traffic pattern changes from June 30, 2025 – July 6, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: June 23 – June 29, 2025

    Posted June 20, 2025 – This advisory outlines traffic pattern changes from June 23, 2025 – June 29, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: June 16 – June 22, 2025

    Posted June 13, 2025 – This advisory outlines traffic pattern changes from June 16, 2025 – June 22, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Traffic Update: Closure of 144 Street South of Fraser Highway

    Posted April 24, 2025 – 144 Street will be closed to vehicle traffic between Fraser Highway and 92 Avenue from April 29, 2025 to May 2, 2025. Alternate routes are available via 88 Avenue to…

    Read more

  • Traffic Update: Fraser Highway between 148 Street and 152 Street

    Posted April 9, 2025 – To support ongoing SkyTrain construction, there will be traffic changes on Fraser Highway between 148 Street and 152 Street from mid-April 2025 until Spring 2026. The travelling public can expect…

    Read more

  • Full Closure: Fraser Highway between 140 Street and 96 Avenue

    Posted March 4, 2025 – To accommodate the construction of Green Timbers Station, which will be built directly above Fraser Highway, a full road closure is required.  To safely accommodate this work, Fraser Highway will…

    Read more

  • UPDATED: Temporary access change west of 160 Street and Fraser Highway

    Posted February 26, 2025 – There will be various traffic pattern changes in effect from mid-March 2025 for approximately ten days. Westbound right lane closure on Fraser Highway west of 160 Street. Right turn access to…

    Read more

  • UPDATED: Temporary access change at 154 Street and Fraser Highway

    Posted February 26, 2025 – Vehicle travel lanes between 152 Street and 154 Street will be reduced to single lanes westbound and eastbound. No right turn onto 154 Street for vehicles travelling westbound on Fraser Highway.…

    Read more

  • Traffic Update: Overnight closure of Highway 15 at Fraser Highway

    Posted March 30, 2026 – To support guideway work over Highway 15, a section of Highway 15 south of Fraser Highway will be closed for four consecutive nights, from 12 a.m. to 4 a.m., April…

    Read more

  • Traffic Update: Access change on 166 Street north of Fraser Highway

    Posted March 5, 2026 – To support utility installations, there will be no access to the Surrey Sport & Leisure Complex from the north end of 166 Street starting March 9, 2026, for up to…

    Read more

  • Station Construction Underway at Hillcrest-184 Street Station

    Posted December 18, 2025 – Station foundation construction, including pile driving, will begin mid-January 2026 and occur for approximately two months, through mid-March 2026. Temporary increases in noise and vibrations are anticipated.  View detailed notice…

    Read more

  • Station Construction Underway at Bakerview-166 Street Station

    Posted November 27, 2025 – Construction is underway for the future Bakerview-166 Street Station. Station foundation construction, including pile driving, will begin early December and occur for approximately three months, through mid-February 2026. Access to…

    Read more

  • Traffic Update: Access change on 166 Street and Fraser Highway

    Posted September 22, 2025 – A traffic pattern change will take place on 166 Street and Fraser Highway from September 22, 2025, for up to one month. Access to 166 Street is available from Fraser…

    Read more

  • Traffic Update: Access Change to Langley Lane (Laneway East of Highway 10)

    Posted November 21, 2025 – Utility work is beginning in the laneway east of Highway 10 (Langley Lane) in late November 2025 through the end of 2025. Langley Lane will be accessible for business deliveries…

    Read more

  • Nightwork at Fraser Highway and 200 Street

    Posted November 21, 2025 – Utility relocations and the installation of new infrastructure to support the future line are underway. Nighttime traffic pattern change will be in effect at the intersection of 200 Street and…

    Read more

  • Traffic Update: Access Changes at Westbrook Centre and Surlang Centre

    Posted November 10, 2025 – There will be access changes to/from Westbrook Centre and Surlang Centre along Fraser Highway west of Willowbrook Drive/196 Street between November 12 – December 4, 2025. View detailed notice If…

    Read more

  • Traffic Update: Fraser Highway between 200 Street and 201A Street

    Posted October 16, 2025 – Traffic pattern changes will be in effect on Fraser Highway from 200 Street to 201A Street from October 20 to late December 2025. The centre left turn lane will be…

    Read more

  • Traffic Update: Turning restrictions on Fraser Highway at 195A Street and Willowbrook Drive

    Posted October 10, 2025 – Temporary turning restrictions will be in effect on a 24/7 basis starting the week of October 20 for approximately one week. There will be no left turns to Willowbrook Drive…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.