Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: February 16 – February 22, 2026

    Posted February 13, 2026 – This advisory outlines traffic pattern changes from February 16 – February 22, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: February 9 – February 15, 2026

    Posted February 6, 2026 – This advisory outlines traffic pattern changes from February 9 – February 15, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: February 2 – February 8, 2026

    Posted January 30, 2026 – This advisory outlines traffic pattern changes from February 2 – February 8, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: January 26 – February 1, 2026

    Posted January 23, 2026 – This advisory outlines traffic pattern changes from January 26 – February 1, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: January 19 – January 25, 2026

    Posted January 16, 2026 – This advisory outlines traffic pattern changes from January 19 – January 25, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • UPDATED: Full Closure of Fraser Highway between 140 Street and 96 Avenue extended to mid-December

    Posted October 21, 2025 – This is an update to the notice distributed on March 4, 2025, to reflect the extension of the closure. To accommodate the construction of Green Timbers Station, a full road closure…

    Read more

  • UPDATED: Temporary Access Closure at 154 Street and Fraser Highway

    Posted September 3, 2025 – This is an update to the notice posted July 30, 2025. Traffic pattern changes will be in effect from September 8-19, 2025. There will be no access at 154 Street. Access…

    Read more

  • Traffic Update: Temporary Access Closure at 159 Street North of Fraser Highway

    Posted August 20, 2025 – To allow for utility work within the intersection at Fraser Highway and 159 Street, traffic pattern changes will be in effect on August 22 and August 25, 2025, as well…

    Read more

  • UPDATED: Traffic Update: Road Closure at 84 Avenue South of Fraser Highway

    Posted August 11, 2025 – This is an update to the notice posted on June 9, 2025. Traffic pattern changes will be in effect for one day on August 12, 2025. There will be no access…

    Read more

  • Traffic Update: Night work and turn restrictions at Fraser Highway and 152 Street

    Posted July 21, 2025 – Night work is required to support activities and reduce overall traffic impacts from August 5 to August 21, 2025. Turning restrictions at the intersection will be in effect from 7…

    Read more

  • Demolition work at 18543 and 18565 Fraser Highway

    Posted August 7, 2024 – Demolition will take place at 18543 Fraser Highway and 18565 Fraser Highway in the coming weeks. This work will include utility disconnections, hazardous material abatements, and other related activities. Construction activities…

    Read more

  • Demolition Work at 8215 166 Street and Fraser Highway

    Posted August 6, 2024 – Demolition of an existing structure including utility disconnections, hazardous material abatements, and other miscellaneous activities, will take place at 8215 166 Street in the coming weeks. Construction activities are expected to…

    Read more

  • Traffic Update: Overnight single lane alternating traffic on Fraser Highway between 189 Street and 64 Avenue

    Posted April 29, 2026 – Construction at the future Clayton Station site is underway. To support survey activities, traffic pattern changes will be in effect the night of April 30, 2026. Survey work is not…

    Read more

  • UPDATED: Fraser Highway at 201A Street

    Posted March 13, 2026 – This is an update to the notice posted on February 18, 2026. Activities include utility relocations and installation of new utilities to power the future SkyTrain. As work progresses, the…

    Read more

  • Access change and extended hours at Willowbrook Drive north of Fraser Highway

    Posted February 12, 2026 – There will be no access to/from Willowbrook Drive north of Fraser Highway from February 19 to March 8, 2026. Alternate routes are available via 64 Avenue and 200 Street. Business…

    Read more

  • UPDATED: Fraser Highway between 200 Street and 201A Street

    Posted December 23, 2025 – This is an update to the notice posted on October 16, 2025. Traffic pattern changes are in effect on Fraser Highway from 200 Street to 201A Street until February 2026.…

    Read more

  • Traffic Update: Fraser Highway and 64 Avenue

    Posted December 18, 2025 – Traffic pattern changes will be in effect at the intersection of Fraser Highway and 64 Avenue beginning January 6, 2026 for approximately two weeks. There will be single lane traffic…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.