Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: March 24 – 30

    Posted March 21, 2025 – This advisory outlines traffic pattern changes from March 24, 2025 – March 30, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: March 17 – 23

    Posted March 14, 2025 – This advisory outlines traffic pattern changes from March 17, 2025 – March 23, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: March 10 – 16

    Posted March 7, 2025 – This advisory outlines traffic pattern changes from March 10, 2025 – March 16, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: March 3 – 9

    Posted February 28, 2025 – This advisory outlines traffic pattern changes from March 3-9, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: February 24 – March 2

    Posted February 21, 2025 – This advisory outlines traffic pattern changes from February 24, 2025 – March 2, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • UPDATED: Temporary Access Closure at 154 Street and Fraser Highway

    Posted September 3, 2025 – This is an update to the notice posted July 30, 2025. Traffic pattern changes will be in effect from September 8-19, 2025. There will be no access at 154 Street. Access…

    Read more

  • Traffic Update: Temporary Access Closure at 159 Street North of Fraser Highway

    Posted August 20, 2025 – To allow for utility work within the intersection at Fraser Highway and 159 Street, traffic pattern changes will be in effect on August 22 and August 25, 2025, as well…

    Read more

  • UPDATED: Traffic Update: Road Closure at 84 Avenue South of Fraser Highway

    Posted August 11, 2025 – This is an update to the notice posted on June 9, 2025. Traffic pattern changes will be in effect for one day on August 12, 2025. There will be no access…

    Read more

  • Traffic Update: Night work and turn restrictions at Fraser Highway and 152 Street

    Posted July 21, 2025 – Night work is required to support activities and reduce overall traffic impacts from August 5 to August 21, 2025. Turning restrictions at the intersection will be in effect from 7…

    Read more

  • Traffic Update: 140 Street and Fraser Highway

    Posted July 11, 2025 – To support the installation of new utilities to power the future SkyTrain and station construction, traffic pattern changes will be in effect from 7 p.m. to 7 a.m. starting July…

    Read more

  • UPDATED: Various works along Fraser Highway between 140 & 192 Street

    Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…

    Read more

  • UPDATED: Lane Closure on Fraser Highway between 150 and 170 Street

    Posted August 22, 2024- This is an update of the notification from August 1, 2024 as the date of work has changed. Existing streetlights on the south side of Fraser Highway between 150 and 170 Street will…

    Read more

  • Piling activities at various locations on Fraser Highway

    Posted August 20, 2024 – Construction activities including geotechnical investigations and test piling activities are scheduled along Fraser Highway in September at various locations. There may be an increase of noise generated by the drilling…

    Read more

  • Demolition work at 18543 and 18565 Fraser Highway

    Posted August 7, 2024 – Demolition will take place at 18543 Fraser Highway and 18565 Fraser Highway in the coming weeks. This work will include utility disconnections, hazardous material abatements, and other related activities. Construction activities…

    Read more

  • Demolition Work at 8215 166 Street and Fraser Highway

    Posted August 6, 2024 – Demolition of an existing structure including utility disconnections, hazardous material abatements, and other miscellaneous activities, will take place at 8215 166 Street in the coming weeks. Construction activities are expected to…

    Read more

  • Construction Activities: Industrial Avenue between 200 Street and 203 Street

    Posted March 14, 2025 – Preliminary activities will occur intermittently on Industrial Avenue from 200 Street to 203 Street from March 19, 2025 through spring 2025. Activities include survey work, utility investigation and vegetation management.…

    Read more

  • Traffic Update: Temporary access changes on Fraser Highway between 68 Avenue and 188 Street

    Posted March 7, 2025 – Activities include moving existing utilities to allow for construction, installing new utilities to supply power for the future SkyTrain, site preparation activities, roadwork and foundation construction. To support this work,…

    Read more

  • Traffic Update: Fraser Highway between 196 Street and Highway 10

    Posted March 7, 2025 – Activities will include roadwork, installing construction fencing around work areas, moving existing utilities to allow for construction and installing new utilities to supply power for the future SkyTrain. Foundation construction…

    Read more

  • UPDATED: Traffic Update: 203 Street and 203A Street

    Posted February, 20, 2025 – Single lane traffic northbound and southbound between Acacia Crescent and just north of Industrial Avenue. 203A Street will be temporarily closed to all through traffic from Locke Lane to Imperial…

    Read more

  • Traffic Update: 203 Street and 203A Street

    Posted February 10, 2025 – Single lane traffic northbound and southbound between Acacia Crescent and just north of Industrial Avenue. 203A Street will be temporarily closed to all through traffic from Locke Lane to Imperial…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.