Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: June 1 to June 7, 2026

    Posted May 29, 2026 – This advisory outlines traffic pattern changes from June 1 to June 7, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: May 25 to May 31, 2026

    Posted May 22, 2026 – This advisory outlines traffic pattern changes from May 25 to May 31, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: May 18 to May 24, 2026

    Posted May 15, 2026 – This advisory outlines traffic pattern changes from May 18 to May 24, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: May 11 – May 17, 2026

    Posted May 8, 2026 – This advisory outlines traffic pattern changes from May 11 to May 17, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: May 4 –10, 2026

    Posted May 1, 2026 – This advisory outlines traffic pattern changes from May 4-10, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • UPDATED: Access change 138 Street north of Fraser Highway

    Posted October 28, 2026 – this is an update to the notice posted on October 5, 2026. There will be no vehicle access to/from 138 Street north of Fraser Highway until mid-December 2026. Cyclist and…

    Read more

  • UPDATED: Extended hours and overnight road closures at 140 Street and Fraser Highway

    Posted October 23, 2026 – this is an update to the notice posted on October 22, 2026. Surrey Langley SkyTrain construction is underway. A launching gantry, the Surrey Sprinter, is installing the guideway for the…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 152 Street

    Posted October 16, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work at the future 152 Street Station. To carry out this work, extended hours will be in effect on October 20 and…

    Read more

  • SCHEDULE CHANGE: Turn restriction at Fraser Highway and 152 Street

    Posted October 9, 2026 – This is an update to the notice distributed on October 9, 2026 to reflect a change in dates. The work scheduled for October 13 to November 20, 2026 is being…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 160 Street

    Posted October 7, 2026 – Surrey Langley SkyTrain construction is progressing, including concrete pours and concrete work at the future Fleetwood Station. To carry out this work, extended hours will be in effect on October…

    Read more

  • Traffic and Construction Update: Fraser Highway between 184 Street and 185 Street

    Posted December 2, 2024 – Starting early-December, construction will take place on the north side of Fraser Highway between 184 Street and 185 Street. There will be a temporary access restriction at 185 Street starting…

    Read more

  • Traffic Update: 166 Street and Fraser Highway Intersection

    Posted November 29, 2024 – During upcoming utility work, there will be temporary traffic pattern changes at the intersection of 166 Street and Fraser Highway. Traffic pattern changes are expected to begin December 2, 2024,…

    Read more

  • UPDATED: Traffic Update – Fraser Highway between Highway 15 and 184 Street

    Posted November 14, 2024 – The work previously planned to start mid-November is being rescheduled for late-November. Vehicle travel lanes on Fraser Highway between Highway 15 (176 Street) and 184 Street will be shifted south and…

    Read more

  • UPDATED: Traffic Pattern and Project Update – Fraser Highway and 166 Street

    Posted November 7, 2024 – The work previously planned to start mid-November is being rescheduled for December 2024.  This is an update of the notification from October 21, 2024. View detailed notice If you have…

    Read more

  • Traffic and Night Work Update: Fraser Highway East of Highway 15 

    Posted October 8, 2024 – The ground for future piers and the elevated guideway, embankment construction, clearing and backfilling, will occur along a section of Fraser Highway east of Highway 15. This work requires longer…

    Read more

  • Traffic Update: Fraser Highway between 64 Avenue and 196 Street

    Posted February 5, 2025 – Vehicle travel lanes on Fraser Highway between 64 Avenue and 196 Street/Willowbrook Drive will be reduced to single lanes westbound and eastbound. Traffic pattern changes will be in effect from…

    Read more

  • UPDATED: Test piling activities at Industrial Ave and 203 Street

    Posted November 19, 2024 – Test piling is now scheduled to begin November 20. There will be a temporary increase in noise and vibration while this work is taking place. This is an update of the…

    Read more

  • Geotechnical Investigation on Industrial Ave

    Posted October 10, 2024 – Geotechnical investigation to gather information about ground conditions for the future location of piers will occur on Industrial Avenue, starting October 16 for approximately two weeks. There will be parking…

    Read more

  • Site preparations for upcoming construction

    Posted September 5, 2024 – Crews will be working on clearing, grubbing, removing and disposing of vegetation and debris along Fraser Highway starting September 9 and lasting for approximately two weeks at the following locations:…

    Read more

  • UPDATED: Various works along Fraser Highway between 140 & 192 Street

    Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.