Construction Notice Archive
Find notifications that are no longer active.
Archived construction notifications are posted below.
Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.
Archived Notifications
Weekly Traffic Advisories
Find archived weekly summaries of traffic advisories for the Surrey Langley SkyTrain project.

-
Weekly Traffic Advisory: September 14 to September 20, 2026
Posted September 11, 2026 – This advisory outlines traffic pattern changes from September 14 to September 20, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: September 7 to September 13, 2026
Posted September 4, 2026 – This advisory outlines traffic pattern changes from September 7 to September 13, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: August 31 to September 6, 2026
Posted August 28, 2026 – This advisory outlines traffic pattern changes from August 31 to September 6, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: August 24 to August 30, 2026
Posted August 21, 2026 – This advisory outlines traffic pattern changes from August 24 to August 30, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: August 17 to August 23, 2026
Posted August 14, 2026 – This advisory outlines traffic pattern changes from August 17 to August 23, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Construction Update: Extended hours at Fraser Highway and 160 Street
Posted October 7, 2026 – Surrey Langley SkyTrain construction is progressing, including concrete pours and concrete work at the future Fleetwood Station. To carry out this work, extended hours will be in effect on October…
-
Traffic Update: No access to 162 Street north of Fraser Highway
Posted September 17, 2026 – Surrey Langley SkyTrain construction is progressing, including road restoration activities. To support this work, there will be no access to/from 162 Street north of Fraser Highway in effect 24/7 from…
-
Traffic Update: No access to Fleetwood Way from Fraser Highway
Posted September 9, 2026 – A launching gantry will be active in this area installing the guideway. No access to/from Fleetwood Way and Fraser Highway from September 12 to 16, 2026 from 7 a.m. to…
-
UPDATED: Overnight closure and extended hours on Fraser Highway between 140 Street and 96 Avenue
This is an update to the notice distributed on June 29, 2026. This notice provides details of upcoming overnight construction to support the Surrey Langley SkyTrain. Fraser Highway will be fully closed between 140 Street and 96 Avenue from July 6…
-
Traffic Update: Overnight closure on Fraser Highway between 140 Street and 96 Avenue
Posted June 29, 2026 – This notice provides details of upcoming overnight construction to support the Surrey Langley SkyTrain. Fraser Highway will be fully closed between 140 Street and 96 Avenue from July 6 to…
-
Station Construction Underway at Hillcrest-184 Street Station
Posted December 18, 2025 – Station foundation construction, including pile driving, will begin mid-January 2026 and occur for approximately two months, through mid-March 2026. Temporary increases in noise and vibrations are anticipated. View detailed notice…
-
Station Construction Underway at Bakerview-166 Street Station
Posted November 27, 2025 – Construction is underway for the future Bakerview-166 Street Station. Station foundation construction, including pile driving, will begin early December and occur for approximately three months, through mid-February 2026. Access to…
-
Traffic Update: Access change on 166 Street and Fraser Highway
Posted September 22, 2025 – A traffic pattern change will take place on 166 Street and Fraser Highway from September 22, 2025, for up to one month. Access to 166 Street is available from Fraser…
-
UPDATED: Multi-Use Path Closure from 168 Street to Highway 15
Posted September 19, 2025 – This is an update to the notice distributed on May 23, 2025. A multi-use path closure from 168 Street to Highway 15 is in effect until January 2026, with modifications.…
-
Extended hours on Fraser Highway between 170 Street to 180 Street
Posted September 18, 2025 – Activities in this area include foundation construction, using driven and vibratory methods, rebar installation and concrete work. These activities are expected to continue through March 2026 and require extended hours,…
-
Demolition work at 6000 Production Way
Posted June 26, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. Demolition of an existing structure, including utility disconnections, tree removal, hazardous material abatement and…
Precast Concrete Facility
Find archived notifications for the precast concrete facility located at 195 Street and 24 Avenue.

No results found