Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: November 11 – November 17, 2024

    Posted November 8, 2024 – This advisory outlines traffic pattern changes during the week of November 11 – November 17, 2024. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: November 4 – November 10, 2024

    Posted November 1 – This advisory outlines traffic pattern changes during the week of November 4 – November 10, 2024. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Demolition Work Continues Adjacent to Fraser Highway Near 152 Street

    Posted August 14, 2024 – Demolition of select existing structures including utility disconnections, hazardous material abatements, and other miscellaneous activities, will continue to take place adjacent to Fraser Highway near 152 Street in the coming…

    Read more

  • Demolition work at 16039 Fraser Highway

    Posted August 7, 2024 – Demolition of select existing structures including utility disconnections, hazardous material abatements, and other related activities, will take place at 16039 Fraser Highway in the coming weeks. Construction activities are expected to…

    Read more

  • Demolition work at various locations near Fraser Hwy

    To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. Demolition of existing structures, including utility disconnections, tree removal, hazardous material abatement and other miscellaneous activities, will take…

    Read more

  • Traffic Update: Access change on 166 Street and Fraser Highway

    Posted September 22, 2025 – A traffic pattern change will take place on 166 Street and Fraser Highway from September 22, 2025, for up to one month. Access to 166 Street is available from Fraser…

    Read more

  • UPDATED: Multi-Use Path Closure from 168 Street to Highway 15

    Posted September 19, 2025 – This is an update to the notice distributed on May 23, 2025. A multi-use path closure from 168 Street to Highway 15 is in effect until January 2026, with modifications.…

    Read more

  • Extended hours on Fraser Highway between 170 Street to 180 Street

    Posted September 18, 2025 – Activities in this area include foundation construction, using driven and vibratory methods, rebar installation and concrete work. These activities are expected to continue through March 2026 and require extended hours,…

    Read more

  • Traffic Update: Turning restrictions at Fraser Highway and Highway 15

    Posted September 11, 2025 – Traffic pattern changes will be in effect from September 15, 2025, for up to three months. There will be no right turns from eastbound Fraser Highway to southbound Highway 15.…

    Read more

  • Traffic Update: Overnight Access Change at 166 Street and Fraser Highway

    Posted September 8, 2025 – To facilitate guideway construction, access to 166 Street north of Fraser Highway will be temporarily unavailable overnight from 8:00 p.m. to 7.00 a.m. starting September 14, 2025, for up to…

    Read more

  • Traffic Update: Closure of 64 Avenue north of Fraser Highway

    Posted July 8, 2026 – To support Surrey Langley SkyTrain guideway installation, access to and from 64 Avenue north of Fraser Highway will be restricted from July 14 to 17, 2026, during construction hours (7…

    Read more

  • UPDATED: Temporary intersection closure at Industrial Avenue and 203 Street

    Posted June 11, 2026 – This is an update to the notice posted on May 7, 2026. Temporary traffic changes will be in place to support Surrey Langley SkyTrain construction. From 9 a.m. on June 16…

    Read more

  • Traffic Update: Overnight closure of 200 Street between Fraser Highway and Production Way

    Posted May 11, 2026 – Temporary traffic changes will be in place to support Surrey Langley SkyTrain construction. From 12 a.m. to 5 a.m. on May 13, 2026, there will be no through access on…

    Read more

  • Construction Update: Pile driving on Industrial Avenue

    Posted May 11, 2026 – Construction to support Surrey Langley SkyTrain will advance with pile driving for column foundations starting May 14, 2026, and continuing through early 2027, beginning at 200 Street and moving east.…

    Read more

  • Traffic Update: Temporary intersection closure at Industrial Avenue and 203 Street

    Posted May 7, 2026 – Temporary traffic changes are required to support Surrey Langley SkyTrain construction, including installation of the elevated guideway. From 7 a.m. May 16 to 10 p.m. May 18, 2026, the intersection…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.