  • Weekly Traffic Advisory: September 14 to September 20, 2026

    Posted September 11, 2026 – This advisory outlines traffic pattern changes from September 14 to September 20, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 7 to September 13, 2026

    Posted September 4, 2026 – This advisory outlines traffic pattern changes from September 7 to September 13, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: August 31 to September 6, 2026

    Posted August 28, 2026 – This advisory outlines traffic pattern changes from August 31 to September 6, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: August 24 to August 30, 2026

    Posted August 21, 2026 – This advisory outlines traffic pattern changes from August 24 to August 30, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: August 17 to August 23, 2026

    Posted August 14, 2026 – This advisory outlines traffic pattern changes from August 17 to August 23, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Traffic Update: Temporary Access Closure at 159 Street North of Fraser Highway

    Posted August 20, 2025 – To allow for utility work within the intersection at Fraser Highway and 159 Street, traffic pattern changes will be in effect on August 22 and August 25, 2025, as well…

    Read more

  • UPDATED: Traffic Update: Road Closure at 84 Avenue South of Fraser Highway

    Posted August 11, 2025 – This is an update to the notice posted on June 9, 2025. Traffic pattern changes will be in effect for one day on August 12, 2025. There will be no access…

    Read more

  • Traffic Update: Night work and turn restrictions at Fraser Highway and 152 Street

    Posted July 21, 2025 – Night work is required to support activities and reduce overall traffic impacts from August 5 to August 21, 2025. Turning restrictions at the intersection will be in effect from 7…

    Read more

  • Traffic Update: 140 Street and Fraser Highway

    Posted July 11, 2025 – To support the installation of new utilities to power the future SkyTrain and station construction, traffic pattern changes will be in effect from 7 p.m. to 7 a.m. starting July…

    Read more

  • Traffic Update: Road Closure at Fleetwood Way North of Fraser Highway

    Posted July 8, 2025 – Traffic pattern changes will be in effect from July 10, 2025, for approximately one week. Fleetwood Way north of Fraser Highway will be closed with no access to vehicle traffic. An…

    Read more

  • UPDATED: Traffic Update: Closure of 188 Street North of Fraser Highway

    Posted June 13, 2025 – This is an update to the notice distributed on May 23, 2025, to provide the latest schedule for this activity. Traffic pattern changes will be in effect until June 20,…

    Read more

  • Traffic Update: Overnight Closure of 168 Street North of Fraser Highway

    Posted April 16, 2025 – Traffic changes will be in effect from May 4, 2025, to May 9, 2025. 168 Street will be closed to vehicle traffic between Fraser Highway and 80 Avenue from 8…

    Read more

  • Traffic Update: Access closure at Fraser Highway and 185 Street

    Posted March 14, 2025 – Access to/from Fraser Highway at 185 Street will be temporarily closed starting March 17,2025, for up to one week. Access will be available via 184 Street and 70 Avenue. Single…

    Read more

  • Traffic Update: Temporary access changes on Fraser Highway between 68 Avenue and 188 Street

    Posted March 7, 2025 – Activities include moving existing utilities to allow for construction, installing new utilities to supply power for the future SkyTrain, site preparation activities, roadwork and foundation construction. To support this work,…

    Read more

  • UPDATED: Traffic Update: Fraser Highway between 162 Street and 164 Street

    Posted February 19, 2025 – To support utility work, traffic pattern changes will be in effect until late February. Vehicle travel lanes on Fraser Highway between 162 Street and 164 Street will be shifted south…

    Read more

  • Traffic Update: Fraser Highway between 200 Street and 201A Street

    Posted October 16, 2025 – Traffic pattern changes will be in effect on Fraser Highway from 200 Street to 201A Street from October 20 to late December 2025. The centre left turn lane will be…

    Read more

  • Traffic Update: Turning restrictions on Fraser Highway at 195A Street and Willowbrook Drive

    Posted October 10, 2025 – Temporary turning restrictions will be in effect on a 24/7 basis starting the week of October 20 for approximately one week. There will be no left turns to Willowbrook Drive…

    Read more

  • UPDATED: Guideway Construction Underway on Industrial Avenue

    Posted October 3, 2025 – This is an update to the notice distributed on September 10, 2025, to reflect the addition of Saturday work. Construction of the elevated guideway on Industrial Avenue (west of the…

    Read more

  • Traffic Update: Turn restrictions at Fraser Highway and 64 Avenue

    Posted August 14, 2025 – To allow for utility work within the intersection at 64 Avenue and Fraser Highway, traffic pattern changes will be in effect from August 14, 2025, until August 29, 2025. There…

    Read more

  • Traffic Update: Fraser Highway between 196 Street and 200 Street

    Posted August 6, 2025 – Activities include foundation construction, pier construction, utility relocations, installation of new utilities to power the SkyTrain and road works. To carry out this work, traffic pattern changes will be in…