Find archived weekly summaries of traffic advisories for the Surrey Langley SkyTrain project.

-
Weekly Traffic Advisory: September 14 to September 20, 2026
Posted September 11, 2026 – This advisory outlines traffic pattern changes from September 14 to September 20, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: September 7 to September 13, 2026
Posted September 4, 2026 – This advisory outlines traffic pattern changes from September 7 to September 13, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: August 31 to September 6, 2026
Posted August 28, 2026 – This advisory outlines traffic pattern changes from August 31 to September 6, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: August 24 to August 30, 2026
Posted August 21, 2026 – This advisory outlines traffic pattern changes from August 24 to August 30, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: August 17 to August 23, 2026
Posted August 14, 2026 – This advisory outlines traffic pattern changes from August 17 to August 23, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Traffic Update: Temporary Access Closure at 159 Street North of Fraser Highway
Posted August 20, 2025 – To allow for utility work within the intersection at Fraser Highway and 159 Street, traffic pattern changes will be in effect on August 22 and August 25, 2025, as well…
-
UPDATED: Traffic Update: Road Closure at 84 Avenue South of Fraser Highway
Posted August 11, 2025 – This is an update to the notice posted on June 9, 2025. Traffic pattern changes will be in effect for one day on August 12, 2025. There will be no access…
-
Traffic Update: Night work and turn restrictions at Fraser Highway and 152 Street
Posted July 21, 2025 – Night work is required to support activities and reduce overall traffic impacts from August 5 to August 21, 2025. Turning restrictions at the intersection will be in effect from 7…
-
Traffic Update: 140 Street and Fraser Highway
Posted July 11, 2025 – To support the installation of new utilities to power the future SkyTrain and station construction, traffic pattern changes will be in effect from 7 p.m. to 7 a.m. starting July…
-
Traffic Update: Road Closure at Fleetwood Way North of Fraser Highway
Posted July 8, 2025 – Traffic pattern changes will be in effect from July 10, 2025, for approximately one week. Fleetwood Way north of Fraser Highway will be closed with no access to vehicle traffic. An…
-
Station Construction Underway at Hillcrest-184 Street Station
Posted December 18, 2025 – Station foundation construction, including pile driving, will begin mid-January 2026 and occur for approximately two months, through mid-March 2026. Temporary increases in noise and vibrations are anticipated. View detailed notice…
-
Station Construction Underway at Bakerview-166 Street Station
Posted November 27, 2025 – Construction is underway for the future Bakerview-166 Street Station. Station foundation construction, including pile driving, will begin early December and occur for approximately three months, through mid-February 2026. Access to…
-
Traffic Update: Access change on 166 Street and Fraser Highway
Posted September 22, 2025 – A traffic pattern change will take place on 166 Street and Fraser Highway from September 22, 2025, for up to one month. Access to 166 Street is available from Fraser…
-
UPDATED: Multi-Use Path Closure from 168 Street to Highway 15
Posted September 19, 2025 – This is an update to the notice distributed on May 23, 2025. A multi-use path closure from 168 Street to Highway 15 is in effect until January 2026, with modifications.…
-
Extended hours on Fraser Highway between 170 Street to 180 Street
Posted September 18, 2025 – Activities in this area include foundation construction, using driven and vibratory methods, rebar installation and concrete work. These activities are expected to continue through March 2026 and require extended hours,…
-
Station Construction Underway at Willowbrook Station
Posted April 1, 2026 – Construction for the future Willowbrook Station is underway. Station foundation construction, including pile driving, will begin mid-April and occur for approximately two months, through mid-June 2026. Temporary increases in noise…
-
UPDATED: Fraser Highway at 201A Street
Posted March 13, 2026 – This is an update to the notice posted on February 18, 2026. Activities include utility relocations and installation of new utilities to power the future SkyTrain. As work progresses, the…
-
Traffic Update: Turn restrictions at Fraser Highway and Highway 10
Posted February 25, 2026 – Installation of new utilities underneath Highway 10 to support the future SkyTrain is underway. To support this work, there will be no left turns from Fraser Highway to Highway 10…
-
UPDATED: Foundation Construction Laneway East of Highway 10
Posted February 12, 2026 – This is an update to the notice posted February 4, 2026. Construction of the elevated guideway is underway in the laneway near Highway 10 and Fraser Highway. Foundation construction in…
-
Access change and extended hours at Willowbrook Drive north of Fraser Highway
Posted February 12, 2026 – There will be no access to/from Willowbrook Drive north of Fraser Highway from February 19 to March 8, 2026. Alternate routes are available via 64 Avenue and 200 Street. Business…
Precast Concrete Facility
Find archived notifications for the precast concrete facility located at 195 Street and 24 Avenue.