Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: March 24 – 30

    Posted March 21, 2025 – This advisory outlines traffic pattern changes from March 24, 2025 – March 30, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: March 17 – 23

    Posted March 14, 2025 – This advisory outlines traffic pattern changes from March 17, 2025 – March 23, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: March 10 – 16

    Posted March 7, 2025 – This advisory outlines traffic pattern changes from March 10, 2025 – March 16, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: March 3 – 9

    Posted February 28, 2025 – This advisory outlines traffic pattern changes from March 3-9, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: February 24 – March 2

    Posted February 21, 2025 – This advisory outlines traffic pattern changes from February 24, 2025 – March 2, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Multi-use pathway closure on Fraser Highway at 138 Street

    Posted May 29, 2026 – Temporary multi-use pathway closure on the north side of Fraser Highway at 138 Street until June 9, 2026. Pedestrian access will reopen when work is complete for the day.  Alternate…

    Read more

  • Traffic Update: Turn restrictions at 160 Street and Fraser Highway

    Posted May 27, 2026 – Turn restrictions at 160 Street and Fraser Highway will be in effect during launching gantry operations from June 2 to June 9 2026. Alternate routes available. Turn restrictions removed at…

    Read more

  • UPDATED: Traffic Update: 152 Street at Fraser Highway

    Posted April 7, 2026 – This is an update to the notice posted on March 5, 2026. Station foundation construction at the station site on the west side of 152 Street and construction of a…

    Read more

  • Traffic Update: Fraser Highway and 140 Street

    Posted February 9, 2026 – Foundation work is occurring on Fraser Highway west of 140 Street and requires large, specialized equipment. Access to businesses west of 140 Street is available from 140 Street southbound only. There…

    Read more

  • UPDATED: Access Changes North of Fraser Highway at 138 Street

    Posted February 4, 2026 – This is an update to the notice posted on January 9, 2026. Construction activities include relocating existing utilities north of Fraser Highway at 138 Street. Traffic pattern changes will be…

    Read more

  • Construction Update: Extended hours at Bakerview-166 Street Station

    Posted November 6, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work at Bakerview-166 Street Station. To carry out this work, extended hours will be in effect on Monday, November 9, 2026, from…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 184 Street

    Posted October 30, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work for the future Hillcrest-184 Street Station. To carry out this work, extended hours will be in effect on November 3, 2026,…

    Read more

  • Construction Update: Sunday work at Bakerview-166 Street and Hillcrest-184 Street Stations

    Posted October 22, 2026 – Surrey Langley SkyTrain construction is underway, including rebar, concrete, and structure work for the future Bakerview-166 Street and Hillcrest-184 Street stations. To carry out these activities, Sunday work will occur…

    Read more

  • UPDATED: No access to 182 Street south of Fraser Highway

    Posted October 1, 2026 – This is an update to the notice posted on September 18, 2026 Surrey Langley SkyTrain construction is progressing, including installation of utilities for future traffic signals. To support this work,…

    Read more

  • Traffic Update: Turn restriction and pedestrian access change at Fraser Highway at 184 Street

    Posted September 14 – To support the installation of new utilities near the future Hillcrest-184 Street Station, the following traffic pattern changes will be in effect from 9 a.m. to 3 p.m. September 14 to…

    Read more

  • Station and Guideway Construction Underway at Langley City Centre Station

    Posted May 13, 2025 – Work is beginning at the new Langley City Centre Station site on 203 Street and Industrial Avenue, for the elevated guideway on Industrial Avenue and at the Propulsion Power Substation…

    Read more

  • Station construction underway at Clayton Station site

    Posted May 5, 2025 – Work is beginning at the new Clayton Station on Fraser Highway at 190 Street (east of 189 Street). Station foundation construction, including pile driving, will begin mid-May and continue through…

    Read more

  • Traffic Update: Closure of 189 Street Intersection North of Fraser Highway

    Posted April 22, 2025 – Current work includes building a new utility crossing at 189 Street, just north of the Fraser Highway intersection. To support this work, traffic changes will be in effect from May…

    Read more

  • Traffic Update: Closure of 68 Avenue North of Fraser Highway

    Posted April 10, 2025 – To support ongoing SkyTrain construction, there will be a closure at 68 Avenue North of Fraser Highway from April 22, 2025, to April 25, 2025. The travelling public can expect…

    Read more

  • Traffic Update: Utility locate activities on Langley Lane (Laneway east of Fraser Highway and south of Highway 10)

    Posted March 27, 2025 – Activities include early works to prepare for construction of the future SkyTrain, including foundation and guideway construction. Single lane alternating traffic will be in effect. Traffic control personnel will be…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.