Construction Notice Archive
Find notifications that are no longer active.
Archived construction notifications are posted below.
Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.
Archived Notifications
Weekly Traffic Advisories
Find archived weekly summaries of traffic advisories for the Surrey Langley SkyTrain project.

-
Weekly Traffic Advisory: September 14 to September 20, 2026
Posted September 11, 2026 – This advisory outlines traffic pattern changes from September 14 to September 20, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: September 7 to September 13, 2026
Posted September 4, 2026 – This advisory outlines traffic pattern changes from September 7 to September 13, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: August 31 to September 6, 2026
Posted August 28, 2026 – This advisory outlines traffic pattern changes from August 31 to September 6, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: August 24 to August 30, 2026
Posted August 21, 2026 – This advisory outlines traffic pattern changes from August 24 to August 30, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: August 17 to August 23, 2026
Posted August 14, 2026 – This advisory outlines traffic pattern changes from August 17 to August 23, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
UPDATED: Access Changes North of Fraser Highway at 138 Street
Posted February 4, 2026 – This is an update to the notice posted on January 9, 2026. Construction activities include relocating existing utilities north of Fraser Highway at 138 Street. Traffic pattern changes will be…
-
Access Change at Fraser Highway and 162 Street/84 Avenue
Posted January 30, 2026 – There will be no access to/from 162 Street/84 Avenue from Fraser Highway beginning February 6 to February 13, 2026 and early March 2026 for one day. Please use alternate routes…
-
UPDATED: Traffic Update: 152 Street at Fraser Highway
Posted January 8, 2026 – This is an update to the notice posted on December 3, 2025. Construction activities include station foundation construction at the station site on the west side of 152 Street and…
-
Traffic Update: Fraser Highway between 140 Street and 96 Avenue
Posted December 5, 2025 – Following the re-opening of the Fraser Highway closure area between 140 Street and 96 Avenue on December 14, 2025, there will be single lane traffic in each direction on Fraser…
-
Traffic Update: 152 Street at Fraser Highway
Posted December 3, 2025 – Construction activities include station foundation construction at the station site on the west side of 152 Street and construction of a station entrance (head house) on the east side of…
-
Traffic Update: Turning restrictions at Fraser Highway and Highway 15
Posted September 11, 2025 – Traffic pattern changes will be in effect from September 15, 2025, for up to three months. There will be no right turns from eastbound Fraser Highway to southbound Highway 15.…
-
Traffic Update: Overnight Access Change at 166 Street and Fraser Highway
Posted September 8, 2025 – To facilitate guideway construction, access to 166 Street north of Fraser Highway will be temporarily unavailable overnight from 8:00 p.m. to 7.00 a.m. starting September 14, 2025, for up to…
-
Traffic Update: Overnight traffic pattern changes at Fraser Highway and Highway 15
Posted August 14, 2025 – Overnight lane closures will be required on Highway 15, including intermittent turning restrictions at the Fraser Highway and Highway 15 intersection. Traffic changes will be in effect from August 17,…
-
Traffic Update: Access Change Fraser Highway west of 68 Avenue
Posted July 25, 2025 – An access change will be in effect at Fraser Highway west of 68 Avenue from July 28, 2025, for approximately one week. There will be no access to/from Fraser Highway…
-
Traffic Update: Intersection work at Fraser Highway and 184 Street
Posted July 18, 2025 – Traffic changes will be in effect at the Fraser Highway and 184 Street intersection from July 21, 2025, for approximately two weeks. Traffic will be reduced to one lane in…
-
Traffic Update: Fraser Highway between 200 Street and 201A Street
Posted October 16, 2025 – Traffic pattern changes will be in effect on Fraser Highway from 200 Street to 201A Street from October 20 to late December 2025. The centre left turn lane will be…
-
Traffic Update: Turning restrictions on Fraser Highway at 195A Street and Willowbrook Drive
Posted October 10, 2025 – Temporary turning restrictions will be in effect on a 24/7 basis starting the week of October 20 for approximately one week. There will be no left turns to Willowbrook Drive…
-
UPDATED: Guideway Construction Underway on Industrial Avenue
Posted October 3, 2025 – This is an update to the notice distributed on September 10, 2025, to reflect the addition of Saturday work. Construction of the elevated guideway on Industrial Avenue (west of the…
-
Traffic Update: Turn restrictions at Fraser Highway and 64 Avenue
Posted August 14, 2025 – To allow for utility work within the intersection at 64 Avenue and Fraser Highway, traffic pattern changes will be in effect from August 14, 2025, until August 29, 2025. There…
-
Traffic Update: Fraser Highway between 196 Street and 200 Street
Posted August 6, 2025 – Activities include foundation construction, pier construction, utility relocations, installation of new utilities to power the SkyTrain and road works. To carry out this work, traffic pattern changes will be in…
Precast Concrete Facility
Find archived notifications for the precast concrete facility located at 195 Street and 24 Avenue.

No results found



