Construction Notice Archive
Find notifications that are no longer active.
Archived construction notifications are posted below.
Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.
Archived Notifications
Weekly Traffic Advisories
Find archived weekly summaries of traffic advisories for the Surrey Langley SkyTrain project.

-
Weekly Traffic Advisory: October 19 to October 25, 2026
Posted October 16, 2026 – This advisory outlines traffic pattern changes from October 19 to October 25, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: October 12 to October 18, 2026
Posted October 9, 2026 – This advisory outlines traffic pattern changes from October 12 to October 18, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: October 5 to October 11, 2026
Posted October 2, 2026 – This advisory outlines traffic pattern changes from October 5 to October 11, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: September 28 to October 4, 2026
Posted September 25, 2026 – This advisory outlines traffic pattern changes from September 28 to October 4, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: September 21 to September 27, 2026
Posted September 18, 2026 – This advisory outlines traffic pattern changes from September 21 to September 27, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Demolition work at 16039 Fraser Highway
Posted August 7, 2024 – Demolition of select existing structures including utility disconnections, hazardous material abatements, and other related activities, will take place at 16039 Fraser Highway in the coming weeks. Construction activities are expected to…
-
Demolition work at various locations near Fraser Hwy
To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. Demolition of existing structures, including utility disconnections, tree removal, hazardous material abatement and other miscellaneous activities, will take…
-
Traffic Update: Overnight Closure of 168 Street North of Fraser Highway
Posted April 16, 2025 – Traffic changes will be in effect from May 4, 2025, to May 9, 2025. 168 Street will be closed to vehicle traffic between Fraser Highway and 80 Avenue from 8…
-
Traffic Update: Access closure at Fraser Highway and 185 Street
Posted March 14, 2025 – Access to/from Fraser Highway at 185 Street will be temporarily closed starting March 17,2025, for up to one week. Access will be available via 184 Street and 70 Avenue. Single…
-
Traffic Update: Temporary access changes on Fraser Highway between 68 Avenue and 188 Street
Posted March 7, 2025 – Activities include moving existing utilities to allow for construction, installing new utilities to supply power for the future SkyTrain, site preparation activities, roadwork and foundation construction. To support this work,…
-
UPDATED: Traffic Update: Fraser Highway between 162 Street and 164 Street
Posted February 19, 2025 – To support utility work, traffic pattern changes will be in effect until late February. Vehicle travel lanes on Fraser Highway between 162 Street and 164 Street will be shifted south…
-
Traffic Update: Fraser Highway between 168 Street and east of Highway 15
Posted February 4, 2025 – Vehicle travel lanes on Fraser Highway between 168 Street and east of Highway 15 will be reduced to single lanes westbound and eastbound. Traffic pattern changes will be in effect…
-
Construction Update: Pile driving on Industrial Avenue
Posted May 11, 2026 – Construction to support Surrey Langley SkyTrain will advance with pile driving for column foundations starting May 14, 2026, and continuing through early 2027, beginning at 200 Street and moving east.…
-
Traffic Update: Temporary intersection closure at Industrial Avenue and 203 Street
Posted May 7, 2026 – Temporary traffic changes are required to support Surrey Langley SkyTrain construction, including installation of the elevated guideway. From 7 a.m. May 16 to 10 p.m. May 18, 2026, the intersection…
-
Traffic Update: Overnight single lane alternating traffic on Fraser Highway between 189 Street and 64 Avenue
Posted April 29, 2026 – Construction at the future Clayton Station site is underway. To support survey activities, traffic pattern changes will be in effect the night of April 30, 2026. Survey work is not…
-
Station Construction Underway at Willowbrook Station
Posted April 1, 2026 – Construction for the future Willowbrook Station is underway. Station foundation construction, including pile driving, will begin mid-April and occur for approximately two months, through mid-June 2026. Temporary increases in noise…
-
UPDATED: Fraser Highway at 201A Street
Posted March 13, 2026 – This is an update to the notice posted on February 18, 2026. Activities include utility relocations and installation of new utilities to power the future SkyTrain. As work progresses, the…
Precast Concrete Facility
Find archived notifications for the precast concrete facility located at 195 Street and 24 Avenue.

No results found



