Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: September 15 – September 21, 2025

    Posted September 12, 2025 – This advisory outlines traffic pattern changes from September 15, 2025 – September 21, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 8 – 14, 2025

    Posted September 5, 2025 – This advisory outlines traffic pattern changes from September 8, 2025 – September 14, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory September 1 – 7, 2025

    Posted August 29, 2025 – This advisory outlines traffic pattern changes during the week of September 1 to September 7, 2025, along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedules are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: August 25 – 31, 2025

    Posted August 22, 2025 – This advisory outlines traffic pattern changes during the week of August 25 to 31, 2025, along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedules are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: August 18 – 24, 2025

    Posted August 15, 2025 – This advisory outlines traffic pattern changes during the week of August 18 to 24, 2025, along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedules are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Demolition Work Continues Adjacent to Fraser Highway Near 152 Street

    Posted August 14, 2024 – Demolition of select existing structures including utility disconnections, hazardous material abatements, and other miscellaneous activities, will continue to take place adjacent to Fraser Highway near 152 Street in the coming…

    Read more

  • Demolition work at 16039 Fraser Highway

    Posted August 7, 2024 – Demolition of select existing structures including utility disconnections, hazardous material abatements, and other related activities, will take place at 16039 Fraser Highway in the coming weeks. Construction activities are expected to…

    Read more

  • Demolition work at various locations near Fraser Hwy

    To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. Demolition of existing structures, including utility disconnections, tree removal, hazardous material abatement and other miscellaneous activities, will take…

    Read more

  • Station Construction Underway at Hillcrest-184 Street Station

    Posted December 18, 2025 – Station foundation construction, including pile driving, will begin mid-January 2026 and occur for approximately two months, through mid-March 2026. Temporary increases in noise and vibrations are anticipated.  View detailed notice…

    Read more

  • Station Construction Underway at Bakerview-166 Street Station

    Posted November 27, 2025 – Construction is underway for the future Bakerview-166 Street Station. Station foundation construction, including pile driving, will begin early December and occur for approximately three months, through mid-February 2026. Access to…

    Read more

  • Traffic Update: Access change on 166 Street and Fraser Highway

    Posted September 22, 2025 – A traffic pattern change will take place on 166 Street and Fraser Highway from September 22, 2025, for up to one month. Access to 166 Street is available from Fraser…

    Read more

  • UPDATED: Multi-Use Path Closure from 168 Street to Highway 15

    Posted September 19, 2025 – This is an update to the notice distributed on May 23, 2025. A multi-use path closure from 168 Street to Highway 15 is in effect until January 2026, with modifications.…

    Read more

  • Extended hours on Fraser Highway between 170 Street to 180 Street

    Posted September 18, 2025 – Activities in this area include foundation construction, using driven and vibratory methods, rebar installation and concrete work. These activities are expected to continue through March 2026 and require extended hours,…

    Read more

  • UPDATED: Temporary intersection closure and extended hours at Industrial Avenue and 203 Street

    Posted September 28, 2026 – This is an update to the notice posted on September 14, 2026. To support concrete work and concrete pours on a portion of the elevated guideway on Industrial Avenue and over…

    Read more

  • UPDATED: No access to 188 Street from Fraser Highway

    Posted September 15, 2026 – This is an update to the notice posted on September 11, 2026. No access to/from 188 Street and Fraser Highway September 25, 28, 29, and October 1 and 2, 2026 from 7 a.m.…

    Read more

  • UPDATED: Extended hours and no access to Willowbrook Drive/196 Street north of Fraser Highway

    Posted September 22, 2026 – This is an update to the notice posted on September 10, 2026. To support guideway installation, the following traffic pattern changes will be in effect from September 24 to 26,…

    Read more

  • UPDATED: Traffic Update: Pedestrian access change between 62A Avenue and Fraser Highway 

    Posted September 1, 2026 – This is an update to the notice posted on August 19, 2026.  To support guideway installation as the launching gantry moves east, a pedestrian access change will be in effect until September…

    Read more

  • Traffic Update: No access to 68 Avenue north of Fraser Highway

    Posted August 18, 2026 – To support the installation of a new traffic signal and road restoration work, temporary traffic pattern changes will be in effect from August 24 to September 1, 2026. No access…

    Read more