Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: July 27 to August 2, 2026

    Posted July 24, 2026 – This advisory outlines traffic pattern changes from July 27 to August 2, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: July 20 to July 26, 2026

    Posted July 17, 2026 – This advisory outlines traffic pattern changes from July 20 to July 26, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: July 13 to July 19, 2026

    Posted July 10, 2026 – This advisory outlines traffic pattern changes from July 13 to July 19, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: July 6 to July 12, 2026

    Posted July 3, 2026 – This advisory outlines traffic pattern changes from July 6 to July 12, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: June 29 to July 5, 2026

    Posted June 26, 2026 – This advisory outlines traffic pattern changes from June 29 to July 5, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • UPDATED: Access change 138 Street north of Fraser Highway

    Posted October 28, 2026 – this is an update to the notice posted on October 5, 2026. There will be no vehicle access to/from 138 Street north of Fraser Highway until mid-December 2026. Cyclist and…

    Read more

  • UPDATED: Extended hours and overnight road closures at 140 Street and Fraser Highway

    Posted October 23, 2026 – this is an update to the notice posted on October 22, 2026. Surrey Langley SkyTrain construction is underway. A launching gantry, the Surrey Sprinter, is installing the guideway for the…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 152 Street

    Posted October 16, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work at the future 152 Street Station. To carry out this work, extended hours will be in effect on October 20 and…

    Read more

  • SCHEDULE CHANGE: Turn restriction at Fraser Highway and 152 Street

    Posted October 9, 2026 – This is an update to the notice distributed on October 9, 2026 to reflect a change in dates. The work scheduled for October 13 to November 20, 2026 is being…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 160 Street

    Posted October 7, 2026 – Surrey Langley SkyTrain construction is progressing, including concrete pours and concrete work at the future Fleetwood Station. To carry out this work, extended hours will be in effect on October…

    Read more

  • Construction Update: Extended hours at Bakerview-166 Street Station

    Posted November 6, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work at Bakerview-166 Street Station. To carry out this work, extended hours will be in effect on Monday, November 9, 2026, from…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 184 Street

    Posted October 30, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work for the future Hillcrest-184 Street Station. To carry out this work, extended hours will be in effect on November 3, 2026,…

    Read more

  • Construction Update: Sunday work at Bakerview-166 Street and Hillcrest-184 Street Stations

    Posted October 22, 2026 – Surrey Langley SkyTrain construction is underway, including rebar, concrete, and structure work for the future Bakerview-166 Street and Hillcrest-184 Street stations. To carry out these activities, Sunday work will occur…

    Read more

  • UPDATED: No access to 182 Street south of Fraser Highway

    Posted October 1, 2026 – This is an update to the notice posted on September 18, 2026 Surrey Langley SkyTrain construction is progressing, including installation of utilities for future traffic signals. To support this work,…

    Read more

  • Traffic Update: Turn restriction and pedestrian access change at Fraser Highway at 184 Street

    Posted September 14 – To support the installation of new utilities near the future Hillcrest-184 Street Station, the following traffic pattern changes will be in effect from 9 a.m. to 3 p.m. September 14 to…

    Read more

  • Traffic Update: Access Closure at Fraser Highway and 189 Street

    Posted June 11, 2025 – Traffic pattern changes will be in place at 189 Street and Fraser Highway from July 3 to July 11, 2025. Traffic on Fraser Highway will be reduced to a single…

    Read more

  • Traffic Update: Utility Activities Near 203 Street and Fraser Highway

    Posted May 29, 2025 – Activities include two days of utility inspection work to prepare for the construction of the future Langley City Centre Station. To support this work, temporary traffic changes will be in…

    Read more

  • Traffic Update: Access Closure at Fraser Highway and 191A Street

    Posted May 20, 2025 – Traffic pattern changes will be in effect beginning the week of May 26, 2025, for approximately 10 days. There will be no access to/from Fraser Highway and 191A Street. Alternate…

    Read more

  • Station and Guideway Construction Underway at Langley City Centre Station

    Posted May 13, 2025 – Work is beginning at the new Langley City Centre Station site on 203 Street and Industrial Avenue, for the elevated guideway on Industrial Avenue and at the Propulsion Power Substation…

    Read more

  • Station construction underway at Clayton Station site

    Posted May 5, 2025 – Work is beginning at the new Clayton Station on Fraser Highway at 190 Street (east of 189 Street). Station foundation construction, including pile driving, will begin mid-May and continue through…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.