Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: March 3 – 9

    Posted February 28, 2025 – This advisory outlines traffic pattern changes from March 3-9, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: February 24 – March 2

    Posted February 21, 2025 – This advisory outlines traffic pattern changes from February 24, 2025 – March 2, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: February 17 – February 23

    Posted February 14, 2025 – This advisory outlines traffic pattern changes from February 17, 2025 – February 23, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: February 10 – February 16

    Posted February 7, 2025 – This advisory outlines traffic pattern changes from February 10, 2025 – February 16, 2025, along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: February 3 – February 9

    Posted January 31, 2025 – This advisory outlines traffic pattern changes from February 3, 2025 – February 9, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Traffic Update: Closure of 144 Street South of Fraser Highway

    Posted April 24, 2025 – 144 Street will be closed to vehicle traffic between Fraser Highway and 92 Avenue from April 29, 2025 to May 2, 2025. Alternate routes are available via 88 Avenue to…

    Read more

  • Traffic Update: Fraser Highway between 148 Street and 152 Street

    Posted April 9, 2025 – To support ongoing SkyTrain construction, there will be traffic changes on Fraser Highway between 148 Street and 152 Street from mid-April 2025 until Spring 2026. The travelling public can expect…

    Read more

  • Full Closure: Fraser Highway between 140 Street and 96 Avenue

    Posted March 4, 2025 – To accommodate the construction of Green Timbers Station, which will be built directly above Fraser Highway, a full road closure is required.  To safely accommodate this work, Fraser Highway will…

    Read more

  • UPDATED: Temporary access change west of 160 Street and Fraser Highway

    Posted February 26, 2025 – There will be various traffic pattern changes in effect from mid-March 2025 for approximately ten days. Westbound right lane closure on Fraser Highway west of 160 Street. Right turn access to…

    Read more

  • UPDATED: Temporary access change at 154 Street and Fraser Highway

    Posted February 26, 2025 – Vehicle travel lanes between 152 Street and 154 Street will be reduced to single lanes westbound and eastbound. No right turn onto 154 Street for vehicles travelling westbound on Fraser Highway.…

    Read more

  • Piling activities at various locations on Fraser Highway

    Posted August 20, 2024 – Construction activities including geotechnical investigations and test piling activities are scheduled along Fraser Highway in September at various locations. There may be an increase of noise generated by the drilling…

    Read more

  • Demolition work at 18543 and 18565 Fraser Highway

    Posted August 7, 2024 – Demolition will take place at 18543 Fraser Highway and 18565 Fraser Highway in the coming weeks. This work will include utility disconnections, hazardous material abatements, and other related activities. Construction activities…

    Read more

  • Demolition Work at 8215 166 Street and Fraser Highway

    Posted August 6, 2024 – Demolition of an existing structure including utility disconnections, hazardous material abatements, and other miscellaneous activities, will take place at 8215 166 Street in the coming weeks. Construction activities are expected to…

    Read more

  • UPDATED: Closure of 64 Avenue north of Fraser Highway

    Posted July 15, 2026 – This is an update to the notice distributed on July 8, 2026. To support Surrey Langley SkyTrain guideway installation, access to and from 64 Avenue north of Fraser Highway will be…

    Read more

  • Traffic Update: Closure of 64 Avenue north of Fraser Highway

    Posted July 8, 2026 – To support Surrey Langley SkyTrain guideway installation, access to and from 64 Avenue north of Fraser Highway will be restricted from July 14 to 17, 2026, during construction hours (7…

    Read more

  • UPDATED: Temporary intersection closure at Industrial Avenue and 203 Street

    Posted June 11, 2026 – This is an update to the notice posted on May 7, 2026. Temporary traffic changes will be in place to support Surrey Langley SkyTrain construction. From 9 a.m. on June 16…

    Read more

  • Traffic Update: Overnight closure of 200 Street between Fraser Highway and Production Way

    Posted May 11, 2026 – Temporary traffic changes will be in place to support Surrey Langley SkyTrain construction. From 12 a.m. to 5 a.m. on May 13, 2026, there will be no through access on…

    Read more

  • Construction Update: Pile driving on Industrial Avenue

    Posted May 11, 2026 – Construction to support Surrey Langley SkyTrain will advance with pile driving for column foundations starting May 14, 2026, and continuing through early 2027, beginning at 200 Street and moving east.…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.