Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: June 15 to June 21, 2026

    Posted June 12, 2026 – This advisory outlines traffic pattern changes from June 15 to June 21, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: June 8 to June 14, 2026

    Posted June 5, 2026 – This advisory outlines traffic pattern changes from June 8 to June 14, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: June 1 to June 7, 2026

    Posted May 29, 2026 – This advisory outlines traffic pattern changes from June 1 to June 7, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: May 25 to May 31, 2026

    Posted May 22, 2026 – This advisory outlines traffic pattern changes from May 25 to May 31, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: May 18 to May 24, 2026

    Posted May 15, 2026 – This advisory outlines traffic pattern changes from May 18 to May 24, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Traffic Update: 140 Street and Fraser Highway

    Posted July 11, 2025 – To support the installation of new utilities to power the future SkyTrain and station construction, traffic pattern changes will be in effect from 7 p.m. to 7 a.m. starting July…

    Read more

  • Traffic Update: Road Closure at Fleetwood Way North of Fraser Highway

    Posted July 8, 2025 – Traffic pattern changes will be in effect from July 10, 2025, for approximately one week. Fleetwood Way north of Fraser Highway will be closed with no access to vehicle traffic. An…

    Read more

  • Traffic Update: Temporary access change at 154 Street and Fraser Highway

    Posted June 27, 2025 – Traffic pattern changes will be in effect from July 2, 2025, for up to one week. There will be a temporary access restriction at 154 Street. Access to/from Fraser Highway…

    Read more

  • Construction Update: Night Work at Green Timbers Station (140 Street)

    Posted May 21, 2025 – Our stations and guideway contractors are currently working at the future Green Timbers Station, located within the road closure area on Fraser Highway between 140 Street and 96 Avenue. To…

    Read more

  • Traffic Update: Intersection Work at Fraser Highway and 156 Street

    Posted May 16, 2025 – Activities include construction of a new utility crossing, within the intersection of Fraser Highway at 156 Street, to supply power for the future SkyTrain. Traffic pattern changes will be in…

    Read more

  • UPDATED: Traffic Update – Fraser Highway between Highway 15 and 184 Street

    Posted November 14, 2024 – The work previously planned to start mid-November is being rescheduled for late-November. Vehicle travel lanes on Fraser Highway between Highway 15 (176 Street) and 184 Street will be shifted south and…

    Read more

  • UPDATED: Traffic Pattern and Project Update – Fraser Highway and 166 Street

    Posted November 7, 2024 – The work previously planned to start mid-November is being rescheduled for December 2024.  This is an update of the notification from October 21, 2024. View detailed notice If you have…

    Read more

  • Traffic and Night Work Update: Fraser Highway East of Highway 15 

    Posted October 8, 2024 – The ground for future piers and the elevated guideway, embankment construction, clearing and backfilling, will occur along a section of Fraser Highway east of Highway 15. This work requires longer…

    Read more

  • UPDATED: Various works along Fraser Highway between 140 & 192 Street

    Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…

    Read more

  • UPDATED: Lane Closure on Fraser Highway between 150 and 170 Street

    Posted August 22, 2024- This is an update of the notification from August 1, 2024 as the date of work has changed. Existing streetlights on the south side of Fraser Highway between 150 and 170 Street will…

    Read more

  • Traffic Update: Temporary intersection closure at Industrial Avenue and 203 Street

    Posted May 7, 2026 – Temporary traffic changes are required to support Surrey Langley SkyTrain construction, including installation of the elevated guideway. From 7 a.m. May 16 to 10 p.m. May 18, 2026, the intersection…

    Read more

  • Traffic Update: Overnight single lane alternating traffic on Fraser Highway between 189 Street and 64 Avenue

    Posted April 29, 2026 – Construction at the future Clayton Station site is underway. To support survey activities, traffic pattern changes will be in effect the night of April 30, 2026. Survey work is not…

    Read more

  • Station Construction Underway at Willowbrook Station

    Posted April 1, 2026 – Construction for the future Willowbrook Station is underway. Station foundation construction, including pile driving, will begin mid-April and occur for approximately two months, through mid-June 2026. Temporary increases in noise…

    Read more

  • UPDATED: Fraser Highway at 201A Street

    Posted March 13, 2026 – This is an update to the notice posted on February 18, 2026. Activities include utility relocations and installation of new utilities to power the future SkyTrain. As work progresses, the…

    Read more

  • Traffic Update: Turn restrictions at Fraser Highway and Highway 10

    Posted February 25, 2026 – Installation of new utilities underneath Highway 10 to support the future SkyTrain is underway. To support this work, there will be no left turns from Fraser Highway to Highway 10…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.