Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: January 13 – January 19

    Posted January 10, 2025 – This advisory outlines traffic pattern changes from January 13, 2025 – January 19, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: January 6 – January 12

    Posted January 3, 2025 – This advisory outlines traffic pattern changes from January 6, 2025 – January 12, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: December 23 – January 5

    Posted December 20, 2024 – This advisory outlines traffic pattern changes from December 23, 2024 – January 5, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: December 16 – December 22

    Posted December 13, 2024 – This advisory outlines traffic pattern changes during the week of December 16 – December 22, 2024 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: December 9 – December 15

    Posted December 6, 2024 – This advisory outlines traffic pattern changes during the week of December 9 – December 15, 2024 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • UPDATED: Foundation Construction along Fraser Highway

    Posted January 8, 2025 – Current construction activities for the Surrey Langley SkyTrain project include preparing sites and ground improvements to support the future guideway piers and SkyTrain stations. Foundation construction will occur throughout the…

    Read more

  • Traffic Update: Fraser Highway between 148 and 152 Street

    Posted October 9, 2024 – Travel lanes, pedestrian, and cycling lanes will be adjusted on Fraser Highway between 148 Street and 152 Street. There will be intermittent lane closures on the approach to the intersection…

    Read more

  • Notice of work on 140 Street and Fraser Highway

    Posted September 5, 2024 – Hydrovac work will take place on 140 Street and Fraser Highway on September 9 and September 10. The hydrovac work requires a single lane closure northbound for the trucks and…

    Read more

  • Site preparations for upcoming construction

    Posted September 5, 2024 – Crews will be working on clearing, grubbing, removing and disposing of vegetation and debris along Fraser Highway starting September 9 and lasting for approximately two weeks at the following locations:…

    Read more

  • UPDATED: Various works along Fraser Highway between 140 & 192 Street

    Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…

    Read more

  • UPDATED: Various works along Fraser Highway between 140 & 192 Street

    Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…

    Read more

  • UPDATED: Lane Closure on Fraser Highway between 150 and 170 Street

    Posted August 22, 2024- This is an update of the notification from August 1, 2024 as the date of work has changed. Existing streetlights on the south side of Fraser Highway between 150 and 170 Street will…

    Read more

  • Piling activities at various locations on Fraser Highway

    Posted August 20, 2024 – Construction activities including geotechnical investigations and test piling activities are scheduled along Fraser Highway in September at various locations. There may be an increase of noise generated by the drilling…

    Read more

  • Demolition work at 18543 and 18565 Fraser Highway

    Posted August 7, 2024 – Demolition will take place at 18543 Fraser Highway and 18565 Fraser Highway in the coming weeks. This work will include utility disconnections, hazardous material abatements, and other related activities. Construction activities…

    Read more

  • Demolition Work at 8215 166 Street and Fraser Highway

    Posted August 6, 2024 – Demolition of an existing structure including utility disconnections, hazardous material abatements, and other miscellaneous activities, will take place at 8215 166 Street in the coming weeks. Construction activities are expected to…

    Read more

  • Nightwork at Fraser Highway and 200 Street

    Posted November 21, 2025 – Utility relocations and the installation of new infrastructure to support the future line are underway. Nighttime traffic pattern change will be in effect at the intersection of 200 Street and…

    Read more

  • Traffic Update: Access Changes at Westbrook Centre and Surlang Centre

    Posted November 10, 2025 – There will be access changes to/from Westbrook Centre and Surlang Centre along Fraser Highway west of Willowbrook Drive/196 Street between November 12 – December 4, 2025. View detailed notice If…

    Read more

  • Traffic Update: Turning restrictions on Fraser Highway at 195A Street and Willowbrook Drive

    Posted October 10, 2025 – Temporary turning restrictions will be in effect on a 24/7 basis starting the week of October 20 for approximately one week. There will be no left turns to Willowbrook Drive…

    Read more

  • UPDATED: Guideway Construction Underway on Industrial Avenue

    Posted October 3, 2025 – This is an update to the notice distributed on September 10, 2025, to reflect the addition of Saturday work. Construction of the elevated guideway on Industrial Avenue (west of the…

    Read more

  • Traffic Update: Turn restrictions at Fraser Highway and 64 Avenue

    Posted August 14, 2025 – To allow for utility work within the intersection at 64 Avenue and Fraser Highway, traffic pattern changes will be in effect from August 14, 2025, until August 29, 2025. There…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.