Construction Notice Archive
Find notifications that are no longer active.
Archived construction notifications are posted below.
Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.
Archived Notifications
Weekly Traffic Advisories
Find archived weekly summaries of traffic advisories for the Surrey Langley SkyTrain project.

-
Weekly Traffic Advisory: March 24 – 30
Posted March 21, 2025 – This advisory outlines traffic pattern changes from March 24, 2025 – March 30, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: March 17 – 23
Posted March 14, 2025 – This advisory outlines traffic pattern changes from March 17, 2025 – March 23, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: March 10 – 16
Posted March 7, 2025 – This advisory outlines traffic pattern changes from March 10, 2025 – March 16, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
Weekly Traffic Advisory: March 3 – 9
Posted February 28, 2025 – This advisory outlines traffic pattern changes from March 3-9, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
Weekly Traffic Advisory: February 24 – March 2
Posted February 21, 2025 – This advisory outlines traffic pattern changes from February 24, 2025 – March 2, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
UPDATED: Foundation Construction along Fraser Highway
Posted January 8, 2025 – Current construction activities for the Surrey Langley SkyTrain project include preparing sites and ground improvements to support the future guideway piers and SkyTrain stations. Foundation construction will occur throughout the…
-
Traffic Update: Fraser Highway between 148 and 152 Street
Posted October 9, 2024 – Travel lanes, pedestrian, and cycling lanes will be adjusted on Fraser Highway between 148 Street and 152 Street. There will be intermittent lane closures on the approach to the intersection…
-
Notice of work on 140 Street and Fraser Highway
Posted September 5, 2024 – Hydrovac work will take place on 140 Street and Fraser Highway on September 9 and September 10. The hydrovac work requires a single lane closure northbound for the trucks and…
-
Site preparations for upcoming construction
Posted September 5, 2024 – Crews will be working on clearing, grubbing, removing and disposing of vegetation and debris along Fraser Highway starting September 9 and lasting for approximately two weeks at the following locations:…
-
UPDATED: Various works along Fraser Highway between 140 & 192 Street
Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…
-
UPDATED: Various works along Fraser Highway between 140 & 192 Street
Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…
-
UPDATED: Lane Closure on Fraser Highway between 150 and 170 Street
Posted August 22, 2024- This is an update of the notification from August 1, 2024 as the date of work has changed. Existing streetlights on the south side of Fraser Highway between 150 and 170 Street will…
-
Piling activities at various locations on Fraser Highway
Posted August 20, 2024 – Construction activities including geotechnical investigations and test piling activities are scheduled along Fraser Highway in September at various locations. There may be an increase of noise generated by the drilling…
-
Demolition work at 18543 and 18565 Fraser Highway
Posted August 7, 2024 – Demolition will take place at 18543 Fraser Highway and 18565 Fraser Highway in the coming weeks. This work will include utility disconnections, hazardous material abatements, and other related activities. Construction activities…
-
Demolition Work at 8215 166 Street and Fraser Highway
Posted August 6, 2024 – Demolition of an existing structure including utility disconnections, hazardous material abatements, and other miscellaneous activities, will take place at 8215 166 Street in the coming weeks. Construction activities are expected to…
-
Traffic Update: Access Change Fraser Highway west of 68 Avenue
Posted July 25, 2025 – An access change will be in effect at Fraser Highway west of 68 Avenue from July 28, 2025, for approximately one week. There will be no access to/from Fraser Highway…
-
Traffic Update: Industrial Avenue between 200 Street and 201A Street
Posted July 9, 2025 – Utility relocations will be underway on Industrial Avenue, including upcoming intermittent activities from 200 Street to 201A Street. This work is anticipated through summer 2026. There will be traffic pattern…
-
Traffic Update: Industrial Avenue between 201A Street and 203 Street
Posted June 20, 2025 – Activities include utility relocations on Industrial Avenue, followed by foundation and pier construction starting at 203 Street and moving towards 201A Street. This work is anticipated through summer 2026. There…
-
Traffic Update: Access Closure at Fraser Highway and 189 Street
Posted June 11, 2025 – Traffic pattern changes will be in place at 189 Street and Fraser Highway from July 3 to July 11, 2025. Traffic on Fraser Highway will be reduced to a single…
-
Traffic Update: Utility Activities Near 203 Street and Fraser Highway
Posted May 29, 2025 – Activities include two days of utility inspection work to prepare for the construction of the future Langley City Centre Station. To support this work, temporary traffic changes will be in…
Precast Concrete Facility
Find archived notifications for the precast concrete facility located at 195 Street and 24 Avenue.

No results found



