Construction Notice Archive
Find notifications that are no longer active.
Archived construction notifications are posted below.
Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.
Archived Notifications
Weekly Traffic Advisories
Find archived weekly summaries of traffic advisories for the Surrey Langley SkyTrain project.

-
Weekly Traffic Advisory: May 12 – May 18
Posted May 9, 2025 – This advisory outlines traffic pattern changes from May 12, 2025 – May 18, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: May 5 – May 11
Posted May 2, 2025 – This advisory outlines traffic pattern changes from May 5, 2025 – May 11, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: April 28 – May 4
Posted April 25, 2025 – This advisory outlines traffic pattern changes from April 28, 2025 – May 4, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: April 21 – April 27
Posted April 17, 2025 – This advisory outlines traffic pattern changes from April 21, 2025 – April 27, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: April 14-20
Posted April 11, 2025 – This advisory outlines traffic pattern changes from April 14, 2025 – April 20, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.
-
Traffic Update: 152 Street at Fraser Highway
Posted December 3, 2025 – Construction activities include station foundation construction at the station site on the west side of 152 Street and construction of a station entrance (head house) on the east side of…
-
Traffic Update: Fraser Highway and 160 Street
Posted November 27, 2025 – To carry out the installation of new utilities, there will be left and right turn restrictions at the intersection of Fraser Highway and 160 Street from December 1 until December…
-
UPDATED: Access Change at Fleetwood Way and Fraser Highway
Posted November 3, 2025 – This is an update to the notice distributed on October 23, 2025 to reflect the schedule change. To support foundation construction for the future guideway, there will be no access to/from…
-
Traffic Update: Temporary Access Closure at 159 Street North of Fraser Highway
Posted October 22, 2025 – There will be no access to/from 159 Street north of Fraser Highway from October 22 to November 14, 2025. Single lane alternating access will be available east of 159 Street…
-
UPDATED: Full Closure of Fraser Highway between 140 Street and 96 Avenue extended to mid-December
Posted October 21, 2025 – This is an update to the notice distributed on March 4, 2025, to reflect the extension of the closure. To accommodate the construction of Green Timbers Station, a full road closure…
-
Demolition work at 18543 and 18565 Fraser Highway
Posted August 7, 2024 – Demolition will take place at 18543 Fraser Highway and 18565 Fraser Highway in the coming weeks. This work will include utility disconnections, hazardous material abatements, and other related activities. Construction activities…
-
Demolition Work at 8215 166 Street and Fraser Highway
Posted August 6, 2024 – Demolition of an existing structure including utility disconnections, hazardous material abatements, and other miscellaneous activities, will take place at 8215 166 Street in the coming weeks. Construction activities are expected to…
-
UPDATED: Temporary intersection closure and extended hours at Industrial Avenue and 203 Street
Posted September 28, 2026 – This is an update to the notice posted on September 14, 2026. To support concrete work and concrete pours on a portion of the elevated guideway on Industrial Avenue and over…
-
UPDATED: No access to 188 Street from Fraser Highway
Posted September 15, 2026 – This is an update to the notice posted on September 11, 2026. No access to/from 188 Street and Fraser Highway September 25, 28, 29, and October 1 and 2, 2026 from 7 a.m.…
-
UPDATED: Extended hours and no access to Willowbrook Drive/196 Street north of Fraser Highway
Posted September 22, 2026 – This is an update to the notice posted on September 10, 2026. To support guideway installation, the following traffic pattern changes will be in effect from September 24 to 26,…
-
UPDATED: Traffic Update: Pedestrian access change between 62A Avenue and Fraser Highway
Posted September 1, 2026 – This is an update to the notice posted on August 19, 2026. To support guideway installation as the launching gantry moves east, a pedestrian access change will be in effect until September…
-
Traffic Update: No access to 68 Avenue north of Fraser Highway
Posted August 18, 2026 – To support the installation of a new traffic signal and road restoration work, temporary traffic pattern changes will be in effect from August 24 to September 1, 2026. No access…
Precast Concrete Facility
Find archived notifications for the precast concrete facility located at 195 Street and 24 Avenue.

No results found