  • Weekly Traffic Advisory: October 20 – October 26, 2025

    Posted October 17, 2025 – This advisory outlines traffic pattern changes from October 20, 2025 – October 26, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: October 13 – October 19, 2025

    Posted October 10, 2025 – This advisory outlines traffic pattern changes from October 13 , 2025 – October 19, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: October 6 – October 12, 2025

    Posted October 3, 2025 – This advisory outlines traffic pattern changes from October 6 , 2025 – October 12, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 29 – October 5, 2025

    Posted September 26, 2025 – This advisory outlines traffic pattern changes from September 29, 2025 – October 5, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 22 – September 28, 2025

    Posted September 19, 2025 – This advisory outlines traffic pattern changes from September 22, 2025 – September 28, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Site preparations for upcoming construction

    Posted September 5, 2024 – Crews will be working on clearing, grubbing, removing and disposing of vegetation and debris along Fraser Highway starting September 9 and lasting for approximately two weeks at the following locations:…

    Read more

  • UPDATED: Various works along Fraser Highway between 140 & 192 Street

    Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…

    Read more

  • Vegetation management at 15079 Fraser Highway

    Posted August 22, 2024 – Vegetation management activities, including tree removal, will take place at 15079 Fraser Highway. This location is a future site office that will accommodate staff and workers of SkyLink Guideway Partners.…

    Read more

  • UPDATED: Lane Closure on Fraser Highway between 150 and 170 Street

    Posted August 22, 2024- This is an update of the notification from August 1, 2024 as the date of work has changed. Existing streetlights on the south side of Fraser Highway between 150 and 170 Street will…

    Read more

  • Piling activities at various locations on Fraser Highway

    Posted August 20, 2024 – Construction activities including geotechnical investigations and test piling activities are scheduled along Fraser Highway in September at various locations. There may be an increase of noise generated by the drilling…

    Read more

  • Traffic and Night Work Update: Fraser Highway East of Highway 15 

    Posted October 8, 2024 – The ground for future piers and the elevated guideway, embankment construction, clearing and backfilling, will occur along a section of Fraser Highway east of Highway 15. This work requires longer…

    Read more

  • UPDATED: Various works along Fraser Highway between 140 & 192 Street

    Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…

    Read more

  • UPDATED: Lane Closure on Fraser Highway between 150 and 170 Street

    Posted August 22, 2024- This is an update of the notification from August 1, 2024 as the date of work has changed. Existing streetlights on the south side of Fraser Highway between 150 and 170 Street will…

    Read more

  • Piling activities at various locations on Fraser Highway

    Posted August 20, 2024 – Construction activities including geotechnical investigations and test piling activities are scheduled along Fraser Highway in September at various locations. There may be an increase of noise generated by the drilling…

    Read more

  • Demolition work at 18543 and 18565 Fraser Highway

    Posted August 7, 2024 – Demolition will take place at 18543 Fraser Highway and 18565 Fraser Highway in the coming weeks. This work will include utility disconnections, hazardous material abatements, and other related activities. Construction activities…

    Read more

  • UPDATED: Temporary intersection closure and extended hours at Industrial Avenue and 203 Street

    Posted September 28, 2026 – This is an update to the notice posted on September 14, 2026. To support concrete work and concrete pours on a portion of the elevated guideway on Industrial Avenue and over…

    Read more

  • UPDATED: No access to 188 Street from Fraser Highway

    Posted September 15, 2026 – This is an update to the notice posted on September 11, 2026. No access to/from 188 Street and Fraser Highway September 25, 28, 29, and October 1 and 2, 2026 from 7 a.m.…

    Read more

  • UPDATED: Extended hours and no access to Willowbrook Drive/196 Street north of Fraser Highway

    Posted September 22, 2026 – This is an update to the notice posted on September 10, 2026. To support guideway installation, the following traffic pattern changes will be in effect from September 24 to 26,…

    Read more

  • UPDATED: Traffic Update: Pedestrian access change between 62A Avenue and Fraser Highway 

    Posted September 1, 2026 – This is an update to the notice posted on August 19, 2026.  To support guideway installation as the launching gantry moves east, a pedestrian access change will be in effect until September…

    Read more

  • Traffic Update: No access to 68 Avenue north of Fraser Highway

    Posted August 18, 2026 – To support the installation of a new traffic signal and road restoration work, temporary traffic pattern changes will be in effect from August 24 to September 1, 2026. No access…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.