Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: August 10 to August 16, 2026

    Posted August 7, 2026 – This advisory outlines traffic pattern changes from August 10 to August 16, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: August 3 to August 9, 2026

    Posted July 31, 2026 – This advisory outlines traffic pattern changes from August 3 to August 9, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: July 27 to August 2, 2026

    Posted July 24, 2026 – This advisory outlines traffic pattern changes from July 27 to August 2, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: July 20 to July 26, 2026

    Posted July 17, 2026 – This advisory outlines traffic pattern changes from July 20 to July 26, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: July 13 to July 19, 2026

    Posted July 10, 2026 – This advisory outlines traffic pattern changes from July 13 to July 19, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • UPDATED: Access Change at Fleetwood Way and Fraser Highway

    Posted November 3, 2025 – This is an update to the notice distributed on October 23, 2025 to reflect the schedule change. To support foundation construction for the future guideway, there will be no access to/from…

    Read more

  • Traffic Update: Temporary Access Closure at 159 Street North of Fraser Highway

    Posted October 22, 2025 – There will be no access to/from 159 Street north of Fraser Highway from October 22 to November 14, 2025. Single lane alternating access will be available east of 159 Street…

    Read more

  • UPDATED: Full Closure of Fraser Highway between 140 Street and 96 Avenue extended to mid-December

    Posted October 21, 2025 – This is an update to the notice distributed on March 4, 2025, to reflect the extension of the closure. To accommodate the construction of Green Timbers Station, a full road closure…

    Read more

  • UPDATED: Temporary Access Closure at 154 Street and Fraser Highway

    Posted September 3, 2025 – This is an update to the notice posted July 30, 2025. Traffic pattern changes will be in effect from September 8-19, 2025. There will be no access at 154 Street. Access…

    Read more

  • Traffic Update: Temporary Access Closure at 159 Street North of Fraser Highway

    Posted August 20, 2025 – To allow for utility work within the intersection at Fraser Highway and 159 Street, traffic pattern changes will be in effect on August 22 and August 25, 2025, as well…

    Read more

  • Construction Update: Extended hours at Bakerview-166 Street Station

    Posted November 6, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work at Bakerview-166 Street Station. To carry out this work, extended hours will be in effect on Monday, November 9, 2026, from…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 184 Street

    Posted October 30, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work for the future Hillcrest-184 Street Station. To carry out this work, extended hours will be in effect on November 3, 2026,…

    Read more

  • Construction Update: Sunday work at Bakerview-166 Street and Hillcrest-184 Street Stations

    Posted October 22, 2026 – Surrey Langley SkyTrain construction is underway, including rebar, concrete, and structure work for the future Bakerview-166 Street and Hillcrest-184 Street stations. To carry out these activities, Sunday work will occur…

    Read more

  • UPDATED: No access to 182 Street south of Fraser Highway

    Posted October 1, 2026 – This is an update to the notice posted on September 18, 2026 Surrey Langley SkyTrain construction is progressing, including installation of utilities for future traffic signals. To support this work,…

    Read more

  • Traffic Update: Turn restriction and pedestrian access change at Fraser Highway at 184 Street

    Posted September 14 – To support the installation of new utilities near the future Hillcrest-184 Street Station, the following traffic pattern changes will be in effect from 9 a.m. to 3 p.m. September 14 to…

    Read more

  • Traffic Update: Fraser Highway between 64 Avenue and 196 Street

    Posted February 5, 2025 – Vehicle travel lanes on Fraser Highway between 64 Avenue and 196 Street/Willowbrook Drive will be reduced to single lanes westbound and eastbound. Traffic pattern changes will be in effect from…

    Read more

  • UPDATED: Test piling activities at Industrial Ave and 203 Street

    Posted November 19, 2024 – Test piling is now scheduled to begin November 20. There will be a temporary increase in noise and vibration while this work is taking place. This is an update of the…

    Read more

  • Geotechnical Investigation on Industrial Ave

    Posted October 10, 2024 – Geotechnical investigation to gather information about ground conditions for the future location of piers will occur on Industrial Avenue, starting October 16 for approximately two weeks. There will be parking…

    Read more

  • Site preparations for upcoming construction

    Posted September 5, 2024 – Crews will be working on clearing, grubbing, removing and disposing of vegetation and debris along Fraser Highway starting September 9 and lasting for approximately two weeks at the following locations:…

    Read more

  • UPDATED: Various works along Fraser Highway between 140 & 192 Street

    Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…

    Read more