Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: November 11 – November 17, 2024

    Posted November 8, 2024 – This advisory outlines traffic pattern changes during the week of November 11 – November 17, 2024. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Weekly Traffic Advisory: November 4 – November 10, 2024

    Posted November 1 – This advisory outlines traffic pattern changes during the week of November 4 – November 10, 2024. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca.

    Read more

  • Traffic Update: 140 Street and Fraser Highway

    Posted July 11, 2025 – To support the installation of new utilities to power the future SkyTrain and station construction, traffic pattern changes will be in effect from 7 p.m. to 7 a.m. starting July…

    Read more

  • Traffic Update: Road Closure at Fleetwood Way North of Fraser Highway

    Posted July 8, 2025 – Traffic pattern changes will be in effect from July 10, 2025, for approximately one week. Fleetwood Way north of Fraser Highway will be closed with no access to vehicle traffic. An…

    Read more

  • Traffic Update: Temporary access change at 154 Street and Fraser Highway

    Posted June 27, 2025 – Traffic pattern changes will be in effect from July 2, 2025, for up to one week. There will be a temporary access restriction at 154 Street. Access to/from Fraser Highway…

    Read more

  • Construction Update: Night Work at Green Timbers Station (140 Street)

    Posted May 21, 2025 – Our stations and guideway contractors are currently working at the future Green Timbers Station, located within the road closure area on Fraser Highway between 140 Street and 96 Avenue. To…

    Read more

  • Traffic Update: Intersection Work at Fraser Highway and 156 Street

    Posted May 16, 2025 – Activities include construction of a new utility crossing, within the intersection of Fraser Highway at 156 Street, to supply power for the future SkyTrain. Traffic pattern changes will be in…

    Read more

  • UPDATED: Traffic Update – Fraser Highway between Highway 15 and 184 Street

    Posted November 14, 2024 – The work previously planned to start mid-November is being rescheduled for late-November. Vehicle travel lanes on Fraser Highway between Highway 15 (176 Street) and 184 Street will be shifted south and…

    Read more

  • UPDATED: Traffic Pattern and Project Update – Fraser Highway and 166 Street

    Posted November 7, 2024 – The work previously planned to start mid-November is being rescheduled for December 2024.  This is an update of the notification from October 21, 2024. View detailed notice If you have…

    Read more

  • Traffic and Night Work Update: Fraser Highway East of Highway 15 

    Posted October 8, 2024 – The ground for future piers and the elevated guideway, embankment construction, clearing and backfilling, will occur along a section of Fraser Highway east of Highway 15. This work requires longer…

    Read more

  • UPDATED: Various works along Fraser Highway between 140 & 192 Street

    Posted September 4, 2024 – To prepare for the construction of the Surrey Langley SkyTrain, early works are underway along Fraser Highway between 140 Street and 192 Street. Borehole investigative works, piling activities, utility disconnections…

    Read more

  • UPDATED: Lane Closure on Fraser Highway between 150 and 170 Street

    Posted August 22, 2024- This is an update of the notification from August 1, 2024 as the date of work has changed. Existing streetlights on the south side of Fraser Highway between 150 and 170 Street will…

    Read more

  • Traffic Update: Closure of 64 Avenue north of Fraser Highway

    Posted July 8, 2026 – To support Surrey Langley SkyTrain guideway installation, access to and from 64 Avenue north of Fraser Highway will be restricted from July 14 to 17, 2026, during construction hours (7…

    Read more

  • UPDATED: Temporary intersection closure at Industrial Avenue and 203 Street

    Posted June 11, 2026 – This is an update to the notice posted on May 7, 2026. Temporary traffic changes will be in place to support Surrey Langley SkyTrain construction. From 9 a.m. on June 16…

    Read more

  • Traffic Update: Overnight closure of 200 Street between Fraser Highway and Production Way

    Posted May 11, 2026 – Temporary traffic changes will be in place to support Surrey Langley SkyTrain construction. From 12 a.m. to 5 a.m. on May 13, 2026, there will be no through access on…

    Read more

  • Construction Update: Pile driving on Industrial Avenue

    Posted May 11, 2026 – Construction to support Surrey Langley SkyTrain will advance with pile driving for column foundations starting May 14, 2026, and continuing through early 2027, beginning at 200 Street and moving east.…

    Read more

  • Traffic Update: Temporary intersection closure at Industrial Avenue and 203 Street

    Posted May 7, 2026 – Temporary traffic changes are required to support Surrey Langley SkyTrain construction, including installation of the elevated guideway. From 7 a.m. May 16 to 10 p.m. May 18, 2026, the intersection…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.