  • Weekly Traffic Advisory: January 12 – January 18, 2026

    Posted January 9, 2026 – This advisory outlines traffic pattern changes from January 12 – January 18, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: December 22 – January 11, 2026

    Posted December 19, 2025 – This advisory outlines traffic pattern changes from December 22, 2025 – January 11, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: December 15 – December 21, 2025

    Posted December 12, 2025 – This advisory outlines traffic pattern changes from December 15, 2025 – December 21, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: December 8 – December 14, 2025

    Posted December 5, 2025 – This advisory outlines traffic pattern changes from December 8, 2025 – December 14, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: December 1 – December 7, 2025

    Posted November 28, 2025 – This advisory outlines traffic pattern changes from December 1, 2025 – December 7, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Traffic Update: Fraser Highway and 160 Street

    Posted November 27, 2025 – To carry out the installation of new utilities, there will be left and right turn restrictions at the intersection of Fraser Highway and 160 Street from December 1 until December…

    Read more

  • UPDATED: Access Change at Fleetwood Way and Fraser Highway

    Posted November 3, 2025 – This is an update to the notice distributed on October 23, 2025 to reflect the schedule change. To support foundation construction for the future guideway, there will be no access to/from…

    Read more

  • Traffic Update: Temporary Access Closure at 159 Street North of Fraser Highway

    Posted October 22, 2025 – There will be no access to/from 159 Street north of Fraser Highway from October 22 to November 14, 2025. Single lane alternating access will be available east of 159 Street…

    Read more

  • UPDATED: Full Closure of Fraser Highway between 140 Street and 96 Avenue extended to mid-December

    Posted October 21, 2025 – This is an update to the notice distributed on March 4, 2025, to reflect the extension of the closure. To accommodate the construction of Green Timbers Station, a full road closure…

    Read more

  • UPDATED: Temporary Access Closure at 154 Street and Fraser Highway

    Posted September 3, 2025 – This is an update to the notice posted July 30, 2025. Traffic pattern changes will be in effect from September 8-19, 2025. There will be no access at 154 Street. Access…

    Read more

  • Demolition Work at 8215 166 Street and Fraser Highway

    Posted August 6, 2024 – Demolition of an existing structure including utility disconnections, hazardous material abatements, and other miscellaneous activities, will take place at 8215 166 Street in the coming weeks. Construction activities are expected to…

    Read more

  • UPDATED: Temporary intersection closure and extended hours at Industrial Avenue and 203 Street

    Posted September 28, 2026 – This is an update to the notice posted on September 14, 2026. To support concrete work and concrete pours on a portion of the elevated guideway on Industrial Avenue and over…

    Read more

  • UPDATED: No access to 188 Street from Fraser Highway

    Posted September 15, 2026 – This is an update to the notice posted on September 11, 2026. No access to/from 188 Street and Fraser Highway September 25, 28, 29, and October 1 and 2, 2026 from 7 a.m.…

    Read more

  • UPDATED: Extended hours and no access to Willowbrook Drive/196 Street north of Fraser Highway

    Posted September 22, 2026 – This is an update to the notice posted on September 10, 2026. To support guideway installation, the following traffic pattern changes will be in effect from September 24 to 26,…

    Read more

  • UPDATED: Traffic Update: Pedestrian access change between 62A Avenue and Fraser Highway 

    Posted September 1, 2026 – This is an update to the notice posted on August 19, 2026.  To support guideway installation as the launching gantry moves east, a pedestrian access change will be in effect until September…

    Read more

  • Traffic Update: No access to 68 Avenue north of Fraser Highway

    Posted August 18, 2026 – To support the installation of a new traffic signal and road restoration work, temporary traffic pattern changes will be in effect from August 24 to September 1, 2026. No access…

    Read more