Construction Notice Archive
Find notifications that are no longer active.
Archived construction notifications are posted below.
Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.
Archived Notifications
Weekly Traffic Advisories
Find archived weekly summaries of traffic advisories for the Surrey Langley SkyTrain project.

-
Weekly Traffic Advisory: October 20 – October 26, 2025
Posted October 17, 2025 – This advisory outlines traffic pattern changes from October 20, 2025 – October 26, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: October 13 – October 19, 2025
Posted October 10, 2025 – This advisory outlines traffic pattern changes from October 13 , 2025 – October 19, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: October 6 – October 12, 2025
Posted October 3, 2025 – This advisory outlines traffic pattern changes from October 6 , 2025 – October 12, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: September 29 – October 5, 2025
Posted September 26, 2025 – This advisory outlines traffic pattern changes from September 29, 2025 – October 5, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Weekly Traffic Advisory: September 22 – September 28, 2025
Posted September 19, 2025 – This advisory outlines traffic pattern changes from September 22, 2025 – September 28, 2025 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca
-
Demolition work at 16039 Fraser Highway
Posted August 7, 2024 – Demolition of select existing structures including utility disconnections, hazardous material abatements, and other related activities, will take place at 16039 Fraser Highway in the coming weeks. Construction activities are expected to…
-
Demolition work at various locations near Fraser Hwy
To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. Demolition of existing structures, including utility disconnections, tree removal, hazardous material abatement and other miscellaneous activities, will take…
-
Construction Update: Extended hours at Bakerview-166 Street Station
Posted November 6, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work at Bakerview-166 Street Station. To carry out this work, extended hours will be in effect on Monday, November 9, 2026, from…
-
Construction Update: Extended hours at Fraser Highway and 184 Street
Posted October 30, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work for the future Hillcrest-184 Street Station. To carry out this work, extended hours will be in effect on November 3, 2026,…
-
Construction Update: Sunday work at Bakerview-166 Street and Hillcrest-184 Street Stations
Posted October 22, 2026 – Surrey Langley SkyTrain construction is underway, including rebar, concrete, and structure work for the future Bakerview-166 Street and Hillcrest-184 Street stations. To carry out these activities, Sunday work will occur…
-
UPDATED: No access to 182 Street south of Fraser Highway
Posted October 1, 2026 – This is an update to the notice posted on September 18, 2026 Surrey Langley SkyTrain construction is progressing, including installation of utilities for future traffic signals. To support this work,…
-
Traffic Update: Turn restriction and pedestrian access change at Fraser Highway at 184 Street
Posted September 14 – To support the installation of new utilities near the future Hillcrest-184 Street Station, the following traffic pattern changes will be in effect from 9 a.m. to 3 p.m. September 14 to…
-
Station and Guideway Construction Underway at Langley City Centre Station
Posted May 13, 2025 – Work is beginning at the new Langley City Centre Station site on 203 Street and Industrial Avenue, for the elevated guideway on Industrial Avenue and at the Propulsion Power Substation…
-
Station construction underway at Clayton Station site
Posted May 5, 2025 – Work is beginning at the new Clayton Station on Fraser Highway at 190 Street (east of 189 Street). Station foundation construction, including pile driving, will begin mid-May and continue through…
-
Traffic Update: Closure of 189 Street Intersection North of Fraser Highway
Posted April 22, 2025 – Current work includes building a new utility crossing at 189 Street, just north of the Fraser Highway intersection. To support this work, traffic changes will be in effect from May…
-
Traffic Update: Closure of 68 Avenue North of Fraser Highway
Posted April 10, 2025 – To support ongoing SkyTrain construction, there will be a closure at 68 Avenue North of Fraser Highway from April 22, 2025, to April 25, 2025. The travelling public can expect…
-
Traffic Update: Utility locate activities on Langley Lane (Laneway east of Fraser Highway and south of Highway 10)
Posted March 27, 2025 – Activities include early works to prepare for construction of the future SkyTrain, including foundation and guideway construction. Single lane alternating traffic will be in effect. Traffic control personnel will be…
Precast Concrete Facility
Find archived notifications for the precast concrete facility located at 195 Street and 24 Avenue.