Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: October 19 to October 25, 2026

    Posted October 16, 2026 – This advisory outlines traffic pattern changes from October 19 to October 25, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: October 12 to October 18, 2026

    Posted October 9, 2026 – This advisory outlines traffic pattern changes from October 12 to October 18, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: October 5 to October 11, 2026

    Posted October 2, 2026 – This advisory outlines traffic pattern changes from October 5 to October 11, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 28 to October 4, 2026

    Posted September 25, 2026 – This advisory outlines traffic pattern changes from September 28 to October 4, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 21 to September 27, 2026

    Posted September 18, 2026 – This advisory outlines traffic pattern changes from September 21 to September 27, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Demolition work at 16039 Fraser Highway

    Posted August 7, 2024 – Demolition of select existing structures including utility disconnections, hazardous material abatements, and other related activities, will take place at 16039 Fraser Highway in the coming weeks. Construction activities are expected to…

    Read more

  • Demolition work at various locations near Fraser Hwy

    To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. Demolition of existing structures, including utility disconnections, tree removal, hazardous material abatement and other miscellaneous activities, will take…

    Read more

  • Traffic and Construction Update: Fraser Highway between 184 Street and 185 Street

    Posted December 2, 2024 – Starting early-December, construction will take place on the north side of Fraser Highway between 184 Street and 185 Street. There will be a temporary access restriction at 185 Street starting…

    Read more

  • Traffic Update: 166 Street and Fraser Highway Intersection

    Posted November 29, 2024 – During upcoming utility work, there will be temporary traffic pattern changes at the intersection of 166 Street and Fraser Highway. Traffic pattern changes are expected to begin December 2, 2024,…

    Read more

  • UPDATED: Traffic Update – Fraser Highway between Highway 15 and 184 Street

    Posted November 14, 2024 – The work previously planned to start mid-November is being rescheduled for late-November. Vehicle travel lanes on Fraser Highway between Highway 15 (176 Street) and 184 Street will be shifted south and…

    Read more

  • UPDATED: Traffic Pattern and Project Update – Fraser Highway and 166 Street

    Posted November 7, 2024 – The work previously planned to start mid-November is being rescheduled for December 2024.  This is an update of the notification from October 21, 2024. View detailed notice If you have…

    Read more

  • Traffic and Night Work Update: Fraser Highway East of Highway 15 

    Posted October 8, 2024 – The ground for future piers and the elevated guideway, embankment construction, clearing and backfilling, will occur along a section of Fraser Highway east of Highway 15. This work requires longer…

    Read more

  • Traffic Update: Industrial Avenue between 200 Street and 201A Street 

    Posted July 9, 2025 – Utility relocations will be underway on Industrial Avenue, including upcoming intermittent activities from 200 Street to 201A Street. This work is anticipated through summer 2026. There will be traffic pattern…

    Read more

  • Traffic Update: Industrial Avenue between 201A Street and 203 Street

    Posted June 20, 2025 – Activities include utility relocations on Industrial Avenue, followed by foundation and pier construction starting at 203 Street and moving towards 201A Street. This work is anticipated through summer 2026. There…

    Read more

  • Traffic Update: Access Closure at Fraser Highway and 189 Street

    Posted June 11, 2025 – Traffic pattern changes will be in place at 189 Street and Fraser Highway from July 3 to July 11, 2025. Traffic on Fraser Highway will be reduced to a single…

    Read more

  • Traffic Update: Utility Activities Near 203 Street and Fraser Highway

    Posted May 29, 2025 – Activities include two days of utility inspection work to prepare for the construction of the future Langley City Centre Station. To support this work, temporary traffic changes will be in…

    Read more

  • Traffic Update: Access Closure at Fraser Highway and 191A Street

    Posted May 20, 2025 – Traffic pattern changes will be in effect beginning the week of May 26, 2025, for approximately 10 days. There will be no access to/from Fraser Highway and 191A Street. Alternate…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.