Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: October 5 to October 11, 2026

    Posted October 2, 2026 – This advisory outlines traffic pattern changes from October 5 to October 11, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 28 to October 4, 2026

    Posted September 25, 2026 – This advisory outlines traffic pattern changes from September 28 to October 4, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 21 to September 27, 2026

    Posted September 18, 2026 – This advisory outlines traffic pattern changes from September 21 to September 27, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 14 to September 20, 2026

    Posted September 11, 2026 – This advisory outlines traffic pattern changes from September 14 to September 20, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 7 to September 13, 2026

    Posted September 4, 2026 – This advisory outlines traffic pattern changes from September 7 to September 13, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • UPDATED: Traffic Update: Road Closure at 84 Avenue South of Fraser Highway

    Posted August 11, 2025 – This is an update to the notice posted on June 9, 2025. Traffic pattern changes will be in effect for one day on August 12, 2025. There will be no access…

    Read more

  • Traffic Update: Night work and turn restrictions at Fraser Highway and 152 Street

    Posted July 21, 2025 – Night work is required to support activities and reduce overall traffic impacts from August 5 to August 21, 2025. Turning restrictions at the intersection will be in effect from 7…

    Read more

  • Traffic Update: 140 Street and Fraser Highway

    Posted July 11, 2025 – To support the installation of new utilities to power the future SkyTrain and station construction, traffic pattern changes will be in effect from 7 p.m. to 7 a.m. starting July…

    Read more

  • Traffic Update: Road Closure at Fleetwood Way North of Fraser Highway

    Posted July 8, 2025 – Traffic pattern changes will be in effect from July 10, 2025, for approximately one week. Fleetwood Way north of Fraser Highway will be closed with no access to vehicle traffic. An…

    Read more

  • Traffic Update: Temporary access change at 154 Street and Fraser Highway

    Posted June 27, 2025 – Traffic pattern changes will be in effect from July 2, 2025, for up to one week. There will be a temporary access restriction at 154 Street. Access to/from Fraser Highway…

    Read more

  • Construction Update: Extended hours at Bakerview-166 Street Station

    Posted November 6, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work at Bakerview-166 Street Station. To carry out this work, extended hours will be in effect on Monday, November 9, 2026, from…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 184 Street

    Posted October 30, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work for the future Hillcrest-184 Street Station. To carry out this work, extended hours will be in effect on November 3, 2026,…

    Read more

  • Construction Update: Sunday work at Bakerview-166 Street and Hillcrest-184 Street Stations

    Posted October 22, 2026 – Surrey Langley SkyTrain construction is underway, including rebar, concrete, and structure work for the future Bakerview-166 Street and Hillcrest-184 Street stations. To carry out these activities, Sunday work will occur…

    Read more

  • UPDATED: No access to 182 Street south of Fraser Highway

    Posted October 1, 2026 – This is an update to the notice posted on September 18, 2026 Surrey Langley SkyTrain construction is progressing, including installation of utilities for future traffic signals. To support this work,…

    Read more

  • Traffic Update: Turn restriction and pedestrian access change at Fraser Highway at 184 Street

    Posted September 14 – To support the installation of new utilities near the future Hillcrest-184 Street Station, the following traffic pattern changes will be in effect from 9 a.m. to 3 p.m. September 14 to…

    Read more

  • Traffic Update: Closure of 189 Street Intersection North of Fraser Highway

    Posted April 22, 2025 – Current work includes building a new utility crossing at 189 Street, just north of the Fraser Highway intersection. To support this work, traffic changes will be in effect from May…

    Read more

  • Traffic Update: Closure of 68 Avenue North of Fraser Highway

    Posted April 10, 2025 – To support ongoing SkyTrain construction, there will be a closure at 68 Avenue North of Fraser Highway from April 22, 2025, to April 25, 2025. The travelling public can expect…

    Read more

  • Traffic Update: Utility locate activities on Langley Lane (Laneway east of Fraser Highway and south of Highway 10)

    Posted March 27, 2025 – Activities include early works to prepare for construction of the future SkyTrain, including foundation and guideway construction. Single lane alternating traffic will be in effect. Traffic control personnel will be…

    Read more

  • Construction Activities: Industrial Avenue between 200 Street and 203 Street

    Posted March 14, 2025 – Preliminary activities will occur intermittently on Industrial Avenue from 200 Street to 203 Street from March 19, 2025 through spring 2025. Activities include survey work, utility investigation and vegetation management.…

    Read more

  • Traffic Update: Temporary access changes on Fraser Highway between 68 Avenue and 188 Street

    Posted March 7, 2025 – Activities include moving existing utilities to allow for construction, installing new utilities to supply power for the future SkyTrain, site preparation activities, roadwork and foundation construction. To support this work,…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.