Archived construction notifications are posted below.

Visit our Current Work webpage to find out what’s happening currently on and near the project alignment.

An image showing traffic pattern changes.
  • Weekly Traffic Advisory: October 5 to October 11, 2026

    Posted October 2, 2026 – This advisory outlines traffic pattern changes from October 5 to October 11, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 28 to October 4, 2026

    Posted September 25, 2026 – This advisory outlines traffic pattern changes from September 28 to October 4, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 21 to September 27, 2026

    Posted September 18, 2026 – This advisory outlines traffic pattern changes from September 21 to September 27, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 14 to September 20, 2026

    Posted September 11, 2026 – This advisory outlines traffic pattern changes from September 14 to September 20, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Weekly Traffic Advisory: September 7 to September 13, 2026

    Posted September 4, 2026 – This advisory outlines traffic pattern changes from September 7 to September 13, 2026 along Fraser Highway from 138 Street to 203 Street and Industrial Avenue. Workplans and schedule are subject to change. View detailed notice If you have any questions about this work, please email surreylangleyskytrain@gov.bc.ca

    Read more

  • Demolition work at 16039 Fraser Highway

    Posted August 7, 2024 – Demolition of select existing structures including utility disconnections, hazardous material abatements, and other related activities, will take place at 16039 Fraser Highway in the coming weeks. Construction activities are expected to…

    Read more

  • Demolition work at various locations near Fraser Hwy

    To prepare for the construction of the Surrey Langley SkyTrain, early works are underway in the area. Demolition of existing structures, including utility disconnections, tree removal, hazardous material abatement and other miscellaneous activities, will take…

    Read more

  • Construction Update: Extended hours at Bakerview-166 Street Station

    Posted November 6, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work at Bakerview-166 Street Station. To carry out this work, extended hours will be in effect on Monday, November 9, 2026, from…

    Read more

  • Construction Update: Extended hours at Fraser Highway and 184 Street

    Posted October 30, 2026 – Surrey Langley SkyTrain construction is underway, including concrete work for the future Hillcrest-184 Street Station. To carry out this work, extended hours will be in effect on November 3, 2026,…

    Read more

  • Construction Update: Sunday work at Bakerview-166 Street and Hillcrest-184 Street Stations

    Posted October 22, 2026 – Surrey Langley SkyTrain construction is underway, including rebar, concrete, and structure work for the future Bakerview-166 Street and Hillcrest-184 Street stations. To carry out these activities, Sunday work will occur…

    Read more

  • UPDATED: No access to 182 Street south of Fraser Highway

    Posted October 1, 2026 – This is an update to the notice posted on September 18, 2026 Surrey Langley SkyTrain construction is progressing, including installation of utilities for future traffic signals. To support this work,…

    Read more

  • Traffic Update: Turn restriction and pedestrian access change at Fraser Highway at 184 Street

    Posted September 14 – To support the installation of new utilities near the future Hillcrest-184 Street Station, the following traffic pattern changes will be in effect from 9 a.m. to 3 p.m. September 14 to…

    Read more

  • Access change and extended hours at Willowbrook Drive north of Fraser Highway

    Posted February 12, 2026 – There will be no access to/from Willowbrook Drive north of Fraser Highway from February 19 to March 8, 2026. Alternate routes are available via 64 Avenue and 200 Street. Business…

    Read more

  • Construction Update: Pile Driving in Langley

    Posted January 16, 2026 – Construction crews will be pile driving for the guideway foundations in Langley City beginning in February 2026. Expect traffic pattern changes, an increase in noise and vibrations, and possible night…

    Read more

  • UPDATED: Fraser Highway between 200 Street and 201A Street

    Posted December 23, 2025 – This is an update to the notice posted on October 16, 2025. Traffic pattern changes are in effect on Fraser Highway from 200 Street to 201A Street until February 2026.…

    Read more

  • Traffic Update: Fraser Highway and 64 Avenue

    Posted December 18, 2025 – Traffic pattern changes will be in effect at the intersection of Fraser Highway and 64 Avenue beginning January 6, 2026 for approximately two weeks. There will be single lane traffic…

    Read more

  • Traffic Update: Access Change to Langley Lane (Laneway East of Highway 10)

    Posted November 21, 2025 – Utility work is beginning in the laneway east of Highway 10 (Langley Lane) in late November 2025 through the end of 2025. Langley Lane will be accessible for business deliveries…

    Read more

An image showing completed concrete guideway segments stored at the precast concrete facility.